HomeMy WebLinkAbout9B - Shepherds Path MEETING DATE: AGENDA #: PREPARED BY: AGENDA ITEM: DISCUSSION: FINANCIAL IMPACT: ALTERNATIVES: JUNE 16, 2003 9B SUE MCDERMOTT, CITY ENGINEER CONSIDER APPROVAL OF A RESOLUTION AUTHORIZING AMENDMENT #1 TO THE DEVELOPMENT CONTRACT FOR SHEPHERD'S PATH (PROJECT #00-31) History The City of Prior Lake entered into a development contract with Shepherd of the Lake Lutheran Church on September 16, 2002 for the construction of the Shepherd's Path church and infrastructure. Current Circumstances As part of the infrastructure improvements, the developer installed sanitary sewer and watermain along the east property line adjacent to the north-south portion of McKenna Road. The City requested that the developer install an 8-inch watermain along the north side of the property adjacent to the east-west portion of McKenna Road (see attached exhibit). This was request was made with the understanding that the City would pay for one-half of the cost of the 8-inch watermain extension as an oversizing cost. The original development contract did not address the oversizing or reimbursement for the additional watermain. Based on the bid provided by the developer, the oversizing cost is $16,727.67. Conclusion The staff believes it is appropriate for the City Council to approve amendment #1 to the Shepherd's Path Development Contract. Funding for this amendment in the amount of $16,727.67 IS proposed to be from the Water Enterprise fund. The alternatives are as follows: 1. Adopt a resolution approving Amendment #1 to the Shepherd's Path Development Contract. 162,QQ.~<;;reek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER RECOMMENDED MOTION: shepherdpathamend 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item until some date in the future. Motion and second adopting a resolution approving Amendment #1 to the Shepherd's Path Development Contract in the amount of $16,727.67 to be [ through the Enterprise fund. RE~ RESOLUTION 03-XX d,INNESO't~ RESOLUTION AUTHORIZING AMENDMENT #1 TO THE SHEPHERD'S PATH DEVELOPMENT CONTRACT - CITY PROJECT #00-31 MOTION BY: SECOND BY: WHEREAS, the City of Prior Lake and Shepherd of the Lake Lutheran Church entered into a Development Contract on September 16, 2002, and WHEREAS, Shepherd of the Lake Lutheran Church was required to install infrastructure improvements as a part of the Development Contract, and WHEREAS, the City of Prior Lake requested installation of additional 8-inch watermain over and above what was required to serve the site, and WHEREAS, The City of Prior Lake has a provision for reimbursement for oversizing costs, which are defined as construction of a Developer Installed Improvement that exceeds those that would otherwise be required of the Developer. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA: 1. The recitals set forth above are incorporated herein. 2. Amendment #1 to the Shepherd's Path Development Contract is approved and hereby authorized to be made to Shepherd of the Lake Lutheran Church payment in the amount of $16,727.67 to be paid from the Enterprise Fund, for the oversizing of watermain. Passed and adopted this 16th day of June, 2003. YES NO Hauqen Hauqen Blumberg Blumberq LeMair LeMair Petersen Petersen Zieska Zieska {Seal} Frank Boyles City Manager 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER N W+E S CITY PRO.JECT #00-31 WATERMAIN f!) rv rv HYDRANT 8" DIA. DIP WATERMAIN 16" DIA. DIP WATERMAlN 300 , o 300 Feet , h,. SHEPHERD OF THE LAKE LUTHERAN CHURCH f!) o l:r <( Z Z W ~ o o AMENDMENT #1 TO DEVELOPMENT CONTRACT SHEPHERD'S PATH PROJECT #00-31 This AMENDMENT #1 TO THE DEVELOPMENT CONTRACT is entered into this 16th day of June, 2003, by and between the CITY OF PRIOR LAKE, a Minnesota municipal corporation ("City"), and Shepherd of the Lake Lutheran Church, a Minnesota Nonprofit Corporation (the "Developer"). Based on the mutual promises and covenants set forth herein, the sufficiency of which is not disputed, the City and the Developer (collectively "Parties") agree to amend Paragraph 30 of the DEVELOPMENT CONTRACT dated September 16,2002, to read as follows: 30. OVERSIZING. City and Developer agree that the Developer Installed Improvements should be oversized for the benefit of future development. Oversizing is the construction of a Developer Installed Improvement to City specifications that exceeds those that would otherwise be required of the Developer. Oversizing improvements include, but are not limited to, sanitary sewer, water, storm drainage facilities, and road improvements. If the City Engineer determines that oversizing is required, the City shall reimburse the Developer for the costs associated with this work and as approved in this contract. The g:\projects\2000\31sheplk\amendment to development contract2.doc Page 1 6/9/03 City required the Developer to extend an 8" watermain along the northern property line adjacent to McKenna Road. The City's agreed to share 50% of the cost of the extension of watermain. City and Developer agree that the cost of extending the system to be reimbursed to the Developer is $16,727.67 based upon a cost estimate by the City Engineer as determined by an engineer's estimate or contractors bid to be provided by the Developer and application of the City's Assessment Policy based on a final engineering design. The calculation for oversizing is attached as Exhibit D. CITY OF PRIOR LAKE (SEAL) By: Jack G. Haugen, Mayor By: Frank Boyles, City Manager DEVELOPER: By: Its: By: Its: STATE OF MINNESOTA ) ( ss. COUNTY OF SCOTT) The foregoing instrument was acknowledged before me this _ day of , 20_, by Jack G. Haugen, Mayor, and by Frank Boyles, City Manager, of the City of Prior Lake, a Minnesota municipal corporation, on behalf of the corporation and pursuant to the authority granted by its City Council. NOTARY PUBLIC g:\projects\2000\31 sheplk\amendment to development contract2.doc 6/9/03 Page 2 STATE OF MINNESOTA ) ( ss. COUNTY OF ) The foregoing instrument was acknowledged before me this day of ,20_, by NOTARY PUBLIC DRAFTED BY: City of Prior Lake 16200 Eagle Creek Avenue SE Prior Lake, Minnesota 55372 g:\projects\2000\3l sheplk\amendment to development contract2.doc 6/9/03 Page 3 MORTGAGEE CONSENT TO DEVELOPMENT CONTRACT , which holds a mortgage on the subject property, the development of which is governed by the foregoing Development Contract, agrees that the Development Contract shall remain in full force and effect even if it forecloses on its mortgage. Dated this _ day of ,20_. STATE OF MINNESOTA ) ( ss. COUNTY OF ) The foregoing instrument was acknowledged before me this _ day of 20_, by NOTARY PUBLIC DRAFTED BY: City of Prior Lake 16200 Eagle Creek Avenue SE Prior Lake, Minnesota 55372 g:\projects\2000\31 sheplk\amendment to development contract2.doc 6/9/03 Page 4 EXHIBIT" A" TO DEVELOPMENT CONTRACT Legal Description of Property to be developed as Shepherd's Path: That part of the east 101.63 feet of the Southeast Quarter of the Southwest Quarter of Section 22, Township 115, Range 22, Scott County, Minnesota lying south of the north 66.00 feet of said Southeast Quarter of the Southwest Quarter of Section 22. Together with that part of the Southwest Quarter of the Southeast Quarter of said Section 22, lying westerly of the east 515.31 feet of said Southwest Quarter ofthe Southeast Quarter of Section 22. Except the north 66.00 feet of the west 33.00 feet of said Southwest Quarter of the Southeast Quarter of Section 22. Also except the east 1200.00 feet of the south 800.00 feet of said Southwest Quarter of the Southeast Quarter of Section 22. g:\projects\2000\31 sheplk\amendment to development contract2.doc 6/9/03 Page 5 EXHIBIT "D" TO DEVELOPMENT CONTRACT (Oversizing Calculations for Developer Installed Improvements) A. OVERSIZING ITEM NO DESCRIPTION WATERMAlN 1 8" DIP WATERMAIN 2 8" GATE VALVE 3 HYDRANT 4 8 x 6 TEE 5 8" PLUG SUBTOTAL TOTAL OVERSIZING SHEPHERD'S PATH UNIT QTY. UNIT PRICE LF 1010 $ 21.64 EA 1 $ 1,363.39 EA 3 $ 3,217.24 EA 3 $ 173.22 EA 1 $ 64.17 g:\projects\2000\3lsheplk\amendment to development contract2.doc 6/9/03 TOTAL COST $ 21,856.40 $ 1,363.39 $ 9,651.72 $ 519.66 $ 64.17 $ 33,455.34 CITY COST (1/2 OF TOTAL) $ 10,928.20 $ 681.70 $ 4,825.86 $ 259.83 $ 32.09 $ 16,727.67 $ 16,727.67 Page 6