DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
JUNE 16,2003
10A
SUE MCDERMOTT, CITY ENGINEER
CONSIDER APPROVAL OF A RESOLUTION ORDERING
PREPARATION OF FEASIBILITY REPORT FOR THE 2004
RECONSTRUCTION IMPROVEMENT PROJECT, CITY
PROJECT #04-11
DISCUSSION:
HISTORY
The City uses the Five Year Capital Improvement Program
to plan its infrastructure improvements and the financing for
capital improvements. The proposed 2004 street
reconstruction program includes several street and utility
improvement projects. The purpose of this Agenda item is
to initiate the process for local improvements set forth in the
2004 portion of the 2004-2008 Capital Improvement
Program in accordance with Minnesota Statutes (M.S.),
Chapter 429.
This process applies to all projects that will be financed in
whole or part through special assessments or bond
proceeds. The first step in the process is for the Council to
order preparation of a Feasibility Report for the improvement
projects.
The Feasibility Report will address street reconstruction in
the Gateway Shores Area: (Breezy Point, Stefan Circle,
Bianca Circle, Adrian Circle, Red Oaks Road, Rutledge
Street and Lakeview Circle) (see attached location
map)( collectively "project").
CURRENT CIRCUMSTANCES
This Project is in the 2004 Capital Improvement Program.
Attached is a page from the C.I.P. which provides additional
information on the Project. The Project requires special
assessments and financing through bond proceeds,
therefore requires the City to follow the requirements of M.S.
Chapter 429.
164QOF&.ag1e Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
ISSUES
The City is required to assess a minimum of 20% of the cost
of a public improvement project completed through the
Chapter 429 process and financed through G.O. bonds. The
City will meet the minimum assessment requirement. The
Feasibility Report will determine the estimated costs of the
improvements and methods of financing. This 2004 Project
is expected to involve 40% assessments for all benefited
parcels.
The preparation of the Feasibility Report is only the first step
in the public improvement process. Following receipt of the
Feasibility Report, the Council can schedule a Public
Hearing to move forward. Following a Public Hearing, the
Council may consider authorizing the preparation of plans
and specifications. Once completed, the City Council would
be asked to approve the plans and specifications, and
authorize advertisement for bids and finally, award a
contract. The City is not committed to doing the projects at
any of the steps outlined above prior to awarding the
contract. The following schedule outlines an approach to
complete this 2004 Project:
Acce t Feasibili Stud /Call for Public Hearin
Hold Informational Meetin
Conduct Public Hearing! Accept
and S ecifications
Hold Informational Meetin
Approve Plans and
Advertisements for Bids
o en Bids
Acce t Bids/Award Contract
Be in Construction
Authorize Amount to be Assessed/Schedule
Assessment Hearin for 9/04
Conduct Assessment Hearin Ado t Assessment Roll
Com lete Base Course of Bituminous
10/03
10/03
Project/Order Plans 11/03
2/04
Specifications/Order 3/04
4/04
5/04
6/04
8/04
9/04
9/04
Council members have expressed a desire to award bid as
soon as possible in the spring. The sooner the feasibility
report is initiated the earlier other steps in the project can be
accomplished.
04CIPFEA
FISCAL IMPACT:
ALTERNATIVES:
RECOMMENDED
MOTION:
REVIEWED BY:
04CIPFEA
Beyond the Engineering staff time required to prepare the
Feasibility Report and complete surveying, we will also
complete soil borings which are needed to determine the
estimated costs of the Project. This cost will be taken from
the Construction Fund.
There are three alternatives for the City Council to consider:
1. Approve a resolution ordering preparation of a Feasibility
Report for: Street reconstruction in the Gateway Shores
Area: (Breezy Point, Stefan Circle, Bianca Circle, Adrian
Circle, Red Oaks Road, Rutledge Street and Lakeview
Circle ).
2. Deny this item for a specific reason and provide staff with
direction.
3. Table this item until some date in the future.
A motion and second as part of the consent agenda to
approve a resolution ordering preparation of a Feasibility
Report for: Street reconstruction in the Gateway Shores
Area: (Breezy Point, Stefan Circle, Bianca Circle, Adrian
Circle, Red Oaks Road, Rutledge Street and Lakeview
Circle ).
RESOLUTION 03-XX
ORDERING PREPARATION OF FEASIBILITY REPORT
FOR THE 2004 RECONSTRUCTION IMPROVEMENT PROJECT
CITY PROJECT #04-11
MOTION BY:
SECOND BY:
WHEREAS, it is proposed to construct improvements on Breezy Point, Stefan Circle, Bianca Circle,
Adrian Circle, Red Oaks Road, Rutledge Street and Lakeview Circle, including the
construction of storm sewer, sanitary sewer and watermain repairs, aggregate base,
concrete curb and gutter, bituminous surfacing, street lights, and appurtenant work;
and
WHEREAS, it is proposed to assess the benefited property for all or a portion of the cost of the
improvements, pursuant to Minnesota Statutes, Chapter 429,
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA,
that the proposed improvements be referred to the City Engineer for study and that she is instructed
to report to the Council with all convenient speed advising the Council in a preliminary way as to
whether the proposed improvements are necessary, cost-effective and feasible and as to whether
they should best be made as proposed or in connection with other improvements, and the estimated
costs for the improvements as recommended.
Passed and adopted this 16th day of June, 2003.
HauQen HauQen
SlumberQ SlumberQ
LeMair LeMair
Petersen Petersen
Zieska Zieska
YES
NO
{Seal}
Frank Boyles, City Manager
~..o Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
~~
a:::
o
a:::
a..
a:::
w
?:
o
-'
~
z.~ ~
~
-e
::s
o
Q)
"!
o
c
o
o
};
-0=
cu::S
0"
O:::~
o
~
~
c..
I-
Z
o
a:::
u.
w
~
CITY PROJECT #04-11
PROJECT AREA MAP
EXHIBIT 1
2004 CAPITAL BUDGET
and 2005 - 2008 CAPITAL IMPROVEMENTS
I. Description and Location:
Street reconstruction in the Gateway Shores Area:
(Breezy Point, Stefan Circle, Bianca Circle, Adrian
Circle, Red Oaks Rd., Rutledge, and Lakeview Circle).
Department:
Project Title:
Public Works
Street Reconstruction
II. Purpose:
To rehabilitate and restore streets to a 7 ton design
standard.
Project Number:
Project Useful Life: 20 Years
III. Needs Assessment:
Priority Rating
IV. Cost/Benefit Impact Statement:
Improved streets will reduce maintenance costs.
H
1
Project Financing:
Property Tax
Project Levy
Special Assessments
Federal
State
County
City MSA Funds
Capital Park Fund
Fund Balance
Eouipment Certificates
Grant/Contributions
Other/(Utilitv Fund)
Total
2004
2005
2006
2007
2008
840,000
560,000
300,000
1,700,000
Project Expenditures:
Construction (New)
RenovationlRepairs
Land Acquisition
Buildine;s and Plant
Equipment
Vehicles
Other
2004
1,700,000
2005
2006
2007
2008
Total
1,700,000
CIP 31