LUTION AUTHORIZING CHANGE ORDER NO. 1 TO BARBAROSSA & SONS, INC.
FOR 2002 IMPROVEMENTS - CITY PROJECT #02-11
MOTION BY: ZIESKA SECOND BY: PETERSEN
WHEREAS, Barbarossa & Sons, Inc. was awarded the contract for construction of 2002
Improvements, City Project 02-11 in the amount of $1,547,014.7CI and
WHEREAS, Due to a late construction start date, the subcontractor was unable to install sod
during the 2002 construction season, and
WHEREAS, The NPDES permit issued by the MPCA requires erosion control on all disturbed
areas, and
WHEREAS, The contractor installed hydromulch to stabilize disturbed areas an to prevent
erosion, and
WHEREAS, The contractor has requested $2,510.00 for the additional work over and above the
original awarded contract amount, bringing the contract amount to $1,549,524.70
including the change order, and
WHEREAS, The City Engineer recommends approval of Change Order No 1.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA:
1. The recitals set forth above are incorporated herein.
2. Change Order No. 1 is hereby authorized to be made to Barbarossa & Sons, Inc. in the
amount of $2,510.00 to be paid from the construction fund, amending the contract to
construct 2002 Improvements to $1,549,524.70, City Project 02-11.
Passed and adopted this 6th day of January, 2003.
YES NO
Haugen X Haugen
Blomberg × Blomberg
LeMair X LeMair
Petersen X Petersen
Zieska X "t'~'~~ ~
Frank Boyles, City Manager
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER