AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING BIDS AND
AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE
CITY'S STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2009
STREET OVERLAY PROJECT 09-012
DISCUSSION: Introduction
The purpose of this agenda item is to accept the bids and authorize the Mayor
and City Manager to execute the City's Standardized Construction Contract
with Knife River Corporation for the 2009 street overlays. Streets to be
overlaid include the portions of Wilds Parkway, Utility (sewer and water main
repair areas) and the neighborhood maintenance resurfacing project directed
as part of Resolution 08-099 accepting the Brooksville Hills preliminary
Engineering Report.
Historv
On March 16th, 2009, the City Council approved a Resolution rejecting the
bids from the initial bid opening on February 24th, 2009, and authorized re-
advertisement for bids at a reduced scope for the 2009 Overlay Improvements
because of cost limitations.
In order to reduce costs the overlay for Fremont Avenue was delayed until
2010. The following street overlays have been re-identified by staff for recon-
struction/maintenance in 2009:
1. Full Length road overlay.
Route
Wilds Parkway
Description
CSAH 82 to Wilds Maintenance Garage
2. Utility (watermain/sewer) repair area paving.
Route
Glynwater Trail
Lemley Circle
. Wildwood Trail Intersection
Description
28' x 300'
28' x 200'
. 32' X 50' and 32' x 140'
3. Neighborhood maintenance resurfacing directed as part of
Resolution 08-099 accepting Brooksville Hills Preliminary
Engineering Report.
I Route
I 150m Street
Prior South
Description
TH 13 to 6366 150m Street
Blind Lake, Cedar Circle, Dublin Road, Hillcrest
Street, Lyons Avenue and Tacoma Circle
www.cityofpriorlake.com
R:\Council\2009 Agenda Reports\05 04 09~00>llt83~e4~7a~aldclc Fax 952.447.4245
ISSUES:
FINANCIAL
IMPACT:
ALTERNATIVES:
RECOMMENDED
MOTION:
ReviL:d by: !
Frank l!I~i
Current Circumstances
Advertisements for bids were published in both the Prior Lake American and
Construction Bulletin with bids due and opened on April 23, 2009, at 11 :00 am.
The City received eleven (11) bids for this project, which are listed in the chart
below.
Company
Knife River Corporation
I GMH Asphalt
I Prior Lake Blacktop
I Northwest Asphalt
I Valley Paving
I Chard Tiling
I McNamara Contracting
I Wm Mueller & Sons
I Aslakson's
I Hardrives
I Bituminous Roadways, Inc.
Address
Sauk Rapids, MN 56379
Chaska, MN 55318
Prior Lake, MN 55372
Shakopee MN 55379
Shakopee, MN 55379
Belle Plaine, MN 56011
Rosemount, MN 55068
Hamburg, MN 55339
Red Wing, MN 55066
Rogers, MN 55374
Shakopee, MN 55379
Total
$214,273.40
$227,342.06
$227,833.90
$236,989.32
$239,191.20
$240,315.80
$244,857.62
$248,212.80
$261,407.36
$274,867.90
$276,974.00
Conclusion
Staff is recommending awarding the construction contract to the lowest bidder,
Knife River Corporation, in the amount of $214,273.40. Knife River Corpora-
tion has not previously worked for the City of Prior Lake. They however have
successfully completed several similar projects in the City of Motley, Saint
Cloud and are currently awarded Saint Cloud's and Scott Counties 2009 over-
lay projects.
Considering the price of petroleum and petroleum based products which are
conducive to the make-up of bituminous asphalt, we believe that the low bid
represents a good value to the Prior Lake taxpayer. The City's estimate was
$267,400.00 based on the previous bid opening for this project.
The City has budgeted sufficient funding for these improvements in the 2009
General Fund budget, excluding the Prior South portion. Funds for these pro-
jects will be drawn from the General Fund Street Department budget, account
#101-43100-412. The Prior South portion, ($100,000) of this project is being
funded from bonds sold in conjunction with the Brooksville Hills Reconstruction
project. Bond proceeds will be recorded in the General Fund. The budget for
account 101-43100-412 will be amended to reflect the additional $100,000 ex-
penditure for the Prior South portion. The utility repair areas will come from
the Water Utility (601-49400-224) and Sewer Utility (601-49450-224) accounts
respectively.
1. Approve a resolution accepting the bids and authorizing the Mayor and City
Manager to execute the City's Standardized Construction Contract with
Knife River Corporation for the selected street overlays.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direction.
.....
ar rger
Re ~rtS\05 04 09\2009 street overlay agenda.doc
~PR~
tO~ 4646 Dakota Street S.E.
U ~ Prior Lake, MN 55372-1714
~
RESOLUTION 09-xx
A RESOLUTION ACCEPTING BIDS AND AUTHORIZING THE MAYOR AND CITY MANAGER TO
EXECUTE THE CITY'S STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2009 STREET
OVERLAY PROJECT #09-012
Motion By:
Second By:
WHEREAS, The following street overlays have been identified by Staff for construction in 2009:
1. Full length road overlay: Wilds Parkway (Maintenance Garage to CSAH 82)
2. Utility (water/sewer) repair area paving: Glynwater Trail, Lemley Circle and Wildwood
Trail intersection.
3. Neighborhood maintenance (Prior South) resurfacing per Resolution 08-099 for
Brooksville Hills: 150th Street (TH 13 to 6366 150th), Blind Lake, Cedar Circle, Dublin
Road, Hillcrest Circle, Lyons Avenue and Tacoma Circle; and
WHEREAS, The City of Prior Lake is committed to street maintenance by improving the streets
within the City therefore reducing the need of costly reconstruction in the near future;
and
WHEREAS, A total of eleven (11) bids (provided in the chart below) were received for the identified
improvements, with the low bid from Knife River Corporation at a cost of $214,273.40
Company
Knife River Corporation
GMH Asphalt
Prior Lake Blacktop
Northwest Asphalt
Valley Paving
Chard Tiling
McNamara Contracting
WmMueller & Sons
Aslakson's
Hardrives
Bituminous Roadwavs, Inc.
and
Address
Sauk Rapids, MN 56379
Chaska, MN 55318
Prior Lake, MN 55372
Shakopee, MN 55379
Shakopee, MN 55379
Belle Plaine, MN 56011
Rosemount, MN 55068
Hamburg, MN 55339
Red Wing, MN 55066
Rogers, MN 55374
Shakopee, MN 55379
Total I
$214,273.40 I
$227,342.06 I
$227,833.90 I
$236,989.32 I
$239,191.20 I
$240,315.80 I
$244,857.62 I
$248,212.80 I
$261,407.36 I
$274,867.90
$276,974.00
WHEREAS, City Staff recommends award of a contract to Knife River Corporation for the 2009
Overlay Project #09-012; and
WHEREAS, Funds allocated, ($100,000) for the Prior South overlay were obtained from bonds sold
as part of the Brookville Hill Reconstruction Project 09-011 ;and
R:\Council\2009 Agenda Reports\05 04 09\2009 street overlay proj~ct raso.DOC
WWW.clryotpnorfake.com
Phone 952.447.9800 / Fax 952.447.4245
WHEREAS, The 2009 Street Overlay costs shares are allocated as follows:
I Activity
Bituminous Overlay
Watermain Repair Paving
I Sewer Repair Paving
Cost
$ 201,273.40
$5,500.00
$7,500.00
Account Number
101-43100-412
601-49400-224
601-49450-224
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City's Standardized
Construction Contract for the identified street overlays with Knife River Corporation for a cost not to
exceed $214,273.40.
3. The budget for the General Fund Street Department (account #101-43100-412) will be amended to
reflect the $100,000 construction cost for the Prior South Overlay Project.
4. Proceeds from the bond sale for the Prior South Overlay Project will be deposited in the General
Fund.
PASSED AND ADOPTED THIS 4TH DAY OF MAY 2009.
YES
NO
Haugen
Erickson
Hedberg
LeMair
Millar
Haugen
Erickson
Hedberg
LeMair
Millar
Frank Boyles, City Manager