CITY COUNCIL AGENDA REPORT
AGENDA ITEM:
JULY 20, 2009
9C
STEVE ALBRECHT, DIRECTOR OF PUBLIC WORKS
CONSIDER APPROVAL OF A RESOLUTION AUTHORIZING
PREPARATION OF PLANS AND SPECIFICATIONS FOR CR 21
WATERMAIN PROJECT
MEETING DATE:
AGENDA #:
PREPARED BY:
DISCUSSION:
Introduction
The purpose of this agenda item is for the City Council to authorize
preparation of plans and specifications for CR 21 Watermain Project.
Histol"{
As the City Council is aware, during the week of February 1 sl the City shut
down CR 21 for a period of three days to complete repairs to the 24-inch
diameter watermain located in CR 21 between Eau Claire Trail and Wagon
Bridge Circle. In 2007 the City completed a large repair to this watermain just
east of the Wagon Bridge. The total cost of repairs for these two events will
most likely exceed $100,000.
The 24-inch main is the City's largest watermain and provides one of three
east! west connections from the east to west side of Prior Lake. The
watermain is ductile iron and was constructed in the late 70s. Under normal
conditions this main would be expected to have a 50+ year life. It is currently
about 30 years old. This main is especially important during high water use
periods and large fire events.
During the 2007 incident it was determined that a large rock placed during
construction of the bridge or roadway most likely created the hole in the main.
Over time the vibration of this rock against the pipe created a weak spot that
eventually failed. However an inspection of the pipe during the repair did not
indicate any other unusual wear on the pipe.
The repairs in 2009 revealed that the bottom side of the watermain was
corroded and failed due to vibration of small rocks near corroded areas. The
corrosion was most likely due to acidic soils in the area that over time reacted
with the ductile pipe and decayed the underside. In 2007 part of CR 21 was
reconstructed over a portion of the watermain. The pipe was insulated during
that project and no corrosion was noted on the top side of the pipe. This is
consistent with the repair findings. Based on City observation, it appears that
the cold winter with deep frost conditions of more than five feet in the roadway
may have also contributed to the failure. While the pipe did not freeze, the
frost reached to the insulation layer and created a connection transferring
vibrations from the roadway to the pipe and causing small stones to penetrate
the corroded sections of pipe. A total of three areas were repaired during this
latest episode.
www.cityofpriorlake.com
Phone 952.447.9800 / Fax 952.447.4245
On June 15, 2009 the City Council accepted the feasibility study for the project
and authorized Staff to pursue relocation of the watermain to the northern
boulevard of CR 21 utilizing directional drilling. SRF was authorized to
proceed with easement acquisition on the City's behalf.
Current Circumstances
SRF has already obtained right of entries from 2 of the 3 property owners and
has indicated the remaining property owner is supportive of the project but
wants additional information prior to providing a right of entry. Based on the
status of acquisition Staff believes the City should begin preparation of the
plans and specifications for the project.
Staff has solicited quotes for professional design services for the project from
SRF, AE2S and Bolton & Menk. SRF notified the City that they would not be
providing a quote as they did not have staff available to complete the work in
accordance with the City's schedule. The City did receive quotes from Bolton
& Menk and AE2S in the amounts of $39,412 and $31,750 respectively.
Based on the cost and project experience City Staff recommends award of the
City's Standardized Professional services contract to AE2S for the CR 21
Watermain Project.
ISSUES:
In order to allow adequate time for construction this fall it is important to
proceed with design of the project. The following project schedule is
necessary in order to ensure completion before weather inhibits construction
and restoration of the CR 21.
- City Council Approves Plans & Specifications
Authorizes Advertisement for Bids.................... . August 17,2009
- City Council Awards Bid...... ............ ... ... ............ .....September 21,2009
- Project Completed.................................... ... ... ..... ...December, 2009
The City does not currently have staff available to design the project and does
not have the in-house expertise to complete the directional drilling design. For
these reasons Staff is recommending contracting with AE2S to complete the
design and assist with construction administration.
FINANCIAL
IMPACT:
The proposed design and construction services costs are less than 5% of the
estimated project construction cost. This is a very good value for this amount
of work. The funding for this project is available and will come from the Water
Utility Fund.
ALTERNATIVES:
1. Approve a resolution authorizing preparation of the plans and
specifications for the CR 21 Watermain Replacement Project.
2. Table the Resolution for a specific reason.
3. Deny the Resolution.
RECOMMENDED Alternative # 1
MOTION:
~o~ PRI01> \
[... ~ \ 4646 Dakota Street S.E.
U ~ Prior Lake, MN 55372,1714
~lNNESO't~// RESOLUTION 09-XXX
RESOLUTION AUTHORIZING PREPARATION OF PLANS AND SPECIFICATIONS FOR THE CR 21
WATERMAIN PROJECT
Motion By:
Second By:
WHEREAS, The CR 21 watermain between Eau Claire Trail and Quincy Street is an important piece
of the City's water infrastructure; and
WHEREAS, Breaks occurring this past winter revealed that if left unrepaired the watermain will most
likely continue to fail annually at considerable cost to the City; and,
WHEREAS, On June 15, 2009 the City Council accepted the feasibility study for the project and
authorized Staff to pursue relocation of the watermain to the northern boulevard of CR
21 utilizing directional drilling. SRF was authorized to proceed with easement
acquisition on the City's behalf; and
WHEREAS, In order to complete the project this fall the City needs to begin design of the project;
and
WHEREAS, The City does not have in-house staff or expertise for design of a directional drilling
project and solicited quotes from the City's Professional Services Pool; and
WHEREAS, The low quote was provided by AE2S in the amount of $31,750; and
WHEREAS, AE2S has the experience and expertise to complete the project.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are authorized to execute the City's Standardized Professional
Services contract with AE2S for an amount not to exceed $31,750 for design and construction
services.
3. Funding for these services shall come from account # 601-49400.
PASSED AND ADOPTED THIS 20th DAY OF JULY 2009.
YES
NO
I Haugen
I Erickson
I Hedberg
I LeMair
I Millar
Haugen
Erickson
Hedberg
LeMair
Millar