HomeMy WebLinkAbout7C - CR 21 / TH 13 / Main Avenue Feasibility Study MEETING DATE: AGENDA #: PREPARED BY: SEPTEMBER 8, 2009 7C STEVE ALBRECHT, DIRECTOR OF PUBLIC WORKS AGENDA ITEM: PRESENTATION ON CR 21/ TH 13/ MAIN AVENUE FEASIBILITY STUDY OPTIONS DISCUSSION: Introduction The purpose of this item is to present the options considered as part of the CR 21/TH 13/Main Avenue/Feasibility Study to the City Council for feedback and comment prior to finalizing the study. Historv The City has contracted with Bolton & Menk/Hoisington Koegler to pre- pare a feasibility study regarding options and funding for the CR 21/Main Ave/TH 13 improvements. The City held community involvement meetings on May 21 and August 20 to discuss the issues related to this project and potential options as part of the feasibility study. Between 15 and 20 interested business owners attended each meeting. Current Circumstances Based on the public input received, a preferred option that lowers a seg- ment of TH 13 and CR 21 to allow Main Avenue to bridge CR 21 was de- veloped. Prior to completing the Feasibility Study for City Council review and approval at a future meeting Staff believes Council input on the op- tions considered and the preferred option should be received. Chris Chr- omy of BMI and Bruce Chamberlain of HKGI are here tonight to provide the City Council with a presentation on the options considered and to re- ceive Council feedback. Reviewed by: D}5-, /'0 !t~ ~rank Boyle;), City M~nager www.cityofpriorlake.com .phoneQ52.44iZ.9S0Q/,Fa)l, 99~d~A.,7, &245 CR 21/Main Ave/TH 13 Intersection Feasibility Study Presented by: Chris Chromy, P.E., p.T.a.E. Bruce Chamberlain, A.S.L.A. Prepared for: City of Prior Lake September 8, 2009 City Council Work Session IIlII ~ (ln~ EA![~_1!'2.Jll\_1lIILI~{~ft Study Need/History CR 21 Corridor Study Adopted in 2005 · Future Needs Between CSAH 87 to CSAH 42 · CR 21 and Main Avenue - Removal of All-Way Stop - Median Closure - Potential Pedestrian Crossing · CR 21 and Arcadia Avenue · TH 13 and Pleasant Street ..... c.w.ty Hlpway II Conklor Study --- ...- /'" ~~ !2i!!J!. ~~ SEH St.~t~W$;~'$~;1tR~Hf,iif~~~:4f~*$~~d Study Purpose Determine Feasibilitv of Imorovements · Preliminary Engineering - TH 13/CR 21 Intersection - CR 21/Main Avenue Pedestrian Crossing - TH 13/Pleasant Street Intersection · Streetscape and Urban Design · Construction Cost Estimate · Construction Impacts IIII1Ifr\ (ln~ 1:~~tt~~~I~~~~\~~1S'tf$~iS:&WP,~ Stakeholder Input Downtown Steering Committee Inout · Initial Input - May 211 2009 - Access In and Out of Downtown - Connectivity Across CR 21 - Safety of Pedestrian Crossing · I nput on Alternatives - August 20, 2009 - Two Options Under Consideration III 311\ (gn~ _~~_$i.iJ.~~f",,~Billl Study Objectives · Implement CR 21 Corridor Improvements · Phase In Downtown Access Modifications · Unify Main Avenue Experience Across CR 21 - Pedestrians - CR 21/Main Avenue Pedestrian Crossing - TH 13/Pleasant Street Intersection · Streetscape and Urban Design · Construction Cost Estimate III alfr\ (ln~ ~~\l~~~~.~~~~~t{~[~_'litil Preliminary Findings Two Options Under Consideration · Consistent with CR 21 Study Recommendations - Number of Lanes - Intersection Locations · Alignment Shift on CR 21 to Minimize Impacts · Pleasant Street Intersection - Appealing Link from TH 13 - Trail Underpass III 311\ ~n~ 1Il-_l~ .U .llt.l1 Preliminary Findings Two Options Under Consideration · Unify Main Avenue Experience Across CR 21 - Pedestrians - Store Frontage - Traffic · Enhance Downtown Business Environment 1I11~ (ln~ 111:'1" mllrlillllll1Ji .R.llft Preliminary Findings Option 1- Main Avenue At-Grade · Right Turn Access In/Out · Marked Pedestrian Crossing - Clear Visibility for Pedestrian and Motorist - Raise Motorists' Awareness of Pedestrian Activity - Encourage Crossing and Pedestrian Vigilance 1113~ lUn~ 1\ll1M .1il!l;!;ill! Preliminary Findings Option 1- Main Avenue At-Grade IIII1Ifr\ (ln~ ~t _t Preliminary Findings Option 1 - Main Avenue At-Grade ~ ('f) 1iiiIi_'/l,'Jf_Ji- _..a Preliminary Findings Option 1 - Main Avenue At-Grade Preliminary Findings Option 2 - Main Avenue Grade Separated · Lower CR 21 by 22 feet at Main Avenue · Lower TH 13/CR 21 by 8 feet · Bridge Main Avenue Over CR 21 - Reconnect Downtown - Vehicle Access on Perimeter 11I11 ~ (gn~ ~"'-'--'" .~I*.. Preliminary Findings Option 2 - Main Avenue Grade Separated 11I11 ~ ~n~ !ii~~~~1IMj.a~~~~tll Preliminary Findings Option 2 - Main Avenue Grade Separated ~L-_~/ 11I11 ~ (gn~ "lI~.~~m?~~~MK~ Preliminary Findings Option 2 - Main Avenue Grade Separated . . -~ ..- :. _ ~o.tu o f*'If1*h.l~~~l~tt%@d~f. Preliminary Findings Pleasant Street Intersection · Alignment Shift South to allow % Access - Left and Right Turn In, Right Turn Out · Minimize and Mitigate Parking Impacts · Minimize and Mitigate Wetland Impacts · Downtown Entrance Design Elements and Civic Attractions 11I11 ~ (gn~ ~ ~--- . ."""'~";"~~11 Preliminary Findings I \ , " \ .-....re"" 0 1IDB_.~~lf~~m~~, Preliminary Findings Next Steps · Council Input / Feedback on Options · Finalize Project Details - Streetscape and Sustainability Considerations - Construction Impacts - Construction Cost Estimates 11I11 ~ (gn~ -~-------- ~l CR 21/Main Ave/TH 13 Intersection Feasibility Study Presented by: Chris Chromy, P.E., P.T.O.E. Bruce Chamberlain, A.S.L.A. Prepared for: City of Prior Lake September 8, 2009 City Council Work Session 11I11 "" ~n~ ~1f41'''IWIi~lfi1~_~t