HomeMy WebLinkAbout5K - Final Payment for Ida Circle Street Improvement Project MEETING DATE: AGENDA #: PREPARED BY: AGENDA ITEM: DISCUSSION: ISSUES: FINANCIAL IMPACT: ALTERNATIVES: CITY COUNCIL AGENDA REPORT DECEMBER 7,2009 5K LARRY POPPLER, ASSISTANT CITY ENGINEER CONSIDER APPROVAL OF A RESOLUTION AUTHORIZING FULL AND FINAL PAYMENT TO SM HENTGES AND SONS INC. FOR THE IDA CIRCLE AND HIGHWAY 13 IMPROVEMENTS (CITY PROJECT #06-11) Introduction The purpose of this item is to authorize full and final payment for the Ida Circle and Highway 13 Improvements. This project included sanitary sewer and watermain extension to Ida Circle and four homes along Highway 13. Historv On January 22, 2008 the City Council awarded a contract to SM Hentges and Sons Inc. for the Ida Circle and Highway 13 Improvements, (06-11). All work under the contract has been completed in accordance with the contract. All punch list items have been completed and any additional repairs will be covered under the project warranty. As a first time improvement, property owners on this project were assessed as much as $17,812 per unit. They also had to pay City connection charges. All thirteen homes on this project have now connected to the City sewer and water. Current Circumstances The full and final payment is $3,060.41 more than the original contract amount. This accounts for approximately 2% of the original contract amount. The overruns are due to changes in various project quantities primarily related to site restoration on Highway 13. The original estimates for the construction limits along Highway 13 fell short on how much was actually disturbed. Nate Briese, the Project Inspector, did a good job documenting the quantities in the field and the final quantities reflect the actual work performed. There are no issues regarding this agenda item. The original contract amount was $234,008.18. Due to quantity over-runs, the final contract amount is $237,068.59 or 2.0% over the original amount. Funding for this amount is available in the Construction Fund. There are three alternatives for the City Council to consider: 1. Approve Resolution 09-XX authorizing full and final payment to SM Hentges and Sons Inc. for the Ida Circle and Highway 13 Improvements. 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item to a certain date in the future. www.cityofpriorlake.com Phone 952.447.9800 / Fax 952.447.4245 RECOMMENDED MOTION: A motion and second to approve Resolution 09-XX as part of the consent agenda authorizing final payment to SM Hentges and Sons Inc. 1J 4646 Dakota Street S.E. Prior Lake, MN 55372-1714 RESOL TION 09-XXX RESOLUTION AUTHORIZING FULL AND FINAL PAYMENT TO SM HENTGES AND SONS INC. FOR THE IDA CIRCLE AND HIGHWAY 13 IMPROVEMENTS (CITY PROJECT #06-11) Motion By: Second By: WHEREAS SM Hentges and Sons Inc. of Jordan, Minnesota was awarded the contract for the Ida Circle and Highway 13 Improvements, City Project 06-11 in the amount of $234,008.18; and WHEREAS, As a result of quantity over-runs the contract amount was increased by $3,060.41 to a total of $237,068.59, and WHEREAS, SM Hentges and Sons, Inc. has completed the contract work for the Ida Circle and Highway 13 Improvements, and WHEREAS, City Staff recommends acceptance of the project and Final Payment of the contract. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. Full and final payment is hereby authorized to be made to SM Hentges and Sons Inc. in the amount of $16,617.87 for the total contract amount of $237,068.59 for the Ida Circle and Highway 13 Improvements, City Project 06-11. 3. Funding for the final payment shall come from the Construction Fund Account #501-48362-501 PASSED AND ADOPTED THIS 7th DAY OF DECEMBER 2009. YES NO Haugen Erickson Hedberg leMair Millar Haugen Erickson Hedberg leMair Millar Frank Boyles, City Manager R:\Council\2009 Agenda Reports\12 07 09\1da Circle final oavmqt,re.sdoc 1 k WWW.Ch).orpnorae.com Phone 952.447.9800 / Fax 952.447.4245