HomeMy WebLinkAbout5I -Accept Water Treatment Facility from Rice Lake Construction
MEETING DATE:
AGENDA #:
PREPARED BY:
AGENDA ITEM:
DISCUSSION:
ISSUES:
DECEMBER 21, 2009
51
STEVE ALBRECHT, DIRECTOR OF PUBLIC WORKS
CONSIDER APPROVAL OF A RESOLUTION ACCEPTING THE WATER
TREATMENT FACILITY FROM RICE LAKE CONSTRUCTION AND APPROV-
ING THE FINAL PROJECT BUDGET
Introduction
The purpose of this agenda is for the City Council to accept the Water Treatment
Facility (WTF) from Rice Lake Contracting and approve the final project budget.
Historv
On August 6, 2007, the City Council awarded a contract for construction of the
WTF to Rice Lake Construction. As part of that approval an overall project
budget was also approved. The City began operations of the WTF in March
2009.
Current Circumstances
The WTF has been complete and operational for about nine months. No further
project expenditures are required and it is appropriate for the City Council to ac-
cept the WTF from Rice Lake Construction and to approve the final project
budget.
Only minor punch list items remain and all expenditures have been completed.
The punch list items will be completed prior to release of the final project retain-
age. The facility is currently within the warranty period which will be in effect until
March of 2011.
The total project budget of $14,147,864.85 included the approved de-
sign/construction budget, Met Council/City Permits, approved testing change or-
der and cost of relocating the emergency siren. The total final project cost is
$14,145,759.34 or $2,105.51 under budget. The attached financing summary
shows all of the final cost totals.
Conclusion
The project has been completed and the facility has been operational for nine
months and therefore it is appropriate for the City Council to accept the project
from Rice Lake Construction. Additionally in order to ensure transparency and
clarity for auditing purposes it is appropriate for the City Council to approve the
final project budget and resolution amounts.
The facility has been operating as planned and is complete. In order for the City
to release the escrow funds (retainage) which guarantees completion of the pro-
ject the City Council must accept the project.
All project expenditures have been completed and therefore at this time it is also
appropriate for the City Cquncil .to review and approve the final project budget.
www.C1tyofpnorlake.com
,I?honei95Z"il.47.,9800 / Fax 952.447.4245
FINANCIAL
IMPACT:
This provides documentation of cost approval to meet the City's Auditing and
Purchase Policy guidelines.
Staff has completed a detailed final cost budget for this project. The project
budget including approved resolutions and additions for the building permit and
emergency siren relocation is $14,147,864.85. The final project costs associated
with the project are as follows:
Item
Approved
Expenditure
$12,746,500.00
736,560.00
44,669.50
100,000.00
208,000.00
96,993.58
98,621.63
7,585.79.00
2,432.00
106,502.35
$14,147,864.85
Actual
Expenditure
$12,813,826.00
743,060.53
38,811.07
100,000.00
157,918.34
112,922.72
68,980.00
1,306.33 I
2,432.00 I
106,502.35
$14,145,759.34
WTF Construction (Rice Lk)
Engineering
Testing
City Administration
Bonding Costs
City Building Costs (Landscaping)
City Building Costs (Equip/FFE)
City Construction Budget Unaliocated
Emergency Siren Relocation
Met Council SAC/Building Permit
Total
The City Council should be aware that the following specific changes occurred:
a) The final contract price with Rice Lake Construction is $67,326 over the orig-
inal contract price. This is an overrun of 0.5% due to required enhancements
to the fire sprinkling system as part of final of the occupancy permit, the addi-
tion of two valves at existing well houses and additional grading required to
facilitate drainage to the new pond located in Cardinal Ridge Park as part of
the Brooksville Hills project.
b) $5,858 of work originally scheduled to be completed by Braun Intertec under
the testing contract was completed by Bolton & Menk under the engineering
contract.
c) Additionallandscaping/screening in the amount of $15,929.14 was added to
address concerns by neighbors related to sight lines, lighting and noise. The
approved funding under building equipment was reduced to cover this addi-
tional expense.
d) The Unallocated Construction Budget is funding originally identified but not
required due to actual costs.
The project is complete and no additional funding is required.
ALTERNATIVES: 1. Approve a resolution accepting the WTF from Rice Lake Construction and
adopting the final project budget.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direction.
RECOMMENDED Alternative No. 1
;::11 I
Fffink,BOrl '
RESOLUTION 09-xxx
A RESOLUTION ACCEPTING THE WATER TREATMENT FACILITY FROM RICE LAKE
CONSTRUCTION AND APPROVING THE FINAL PROJECT BUDGET
Motion By:
Second By:
WHEREAS, Construction of the Water Treatment Facility (WTF) was completed in March of 2009;
and
WHEREAS, The City has been operating and maintaining the WTF for nine months and staff
recommends the City Council accept the facility from Rice Lake Construction; and
WHEREAS, All expenditures associated with the WTF have been made; and
WHEREAS, The approved project budget was $14,147,864.85 and the final project cost was
$14,145,759.34 or $2,105.51 under budget; and
WHEREAS, The following resolutions were approved (excludes permit and emergency siren
relocation fees) as part of the project budget with the following actual expenditures:
Resolution No.
06-142 Design/Engineeringllnsp.
06-197 Testing/Insp.
06-205 Design Modifications
07-145 City Project Administration
07 -145 Construction
07-145 Bonding Costs
07-145 Unallocated City Costs
08-017 Testing
08-121 Landscaping
08-133 Equipment/Furnishings
09-072 Landscaping
Total
; and
Approved
Cost
$686,560.00
$22,239.00
$50,000.00
$100,000.00
$12,746,500.00
$208,000.00
$7,585.79
$22,430.50
$41,344.69
$98,621.63
$55,648.89
Actual
Cost
$693,060.53
$22,239.00
$50,000.00
$100,000.00
$12,813,826.00
$157,918.34
$1,306.33
$16,572.07
$41,377.53
$68,980.00
$71,545.19
Variation
+$6,500.53 I
$0 I
$0 I
$0 I
+$67,326.00 I
-$50,081.66 I
-$6,279.46 I
-$5,858.43 I
+$32.84 I
-$29,641.63 I
+$15,896.30 I
-$2,105.51 I
WHEREAS, The authorized expenditures for the above listed resolutions are amended to reflect
actual final costs for the project.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. City Staff is authorized to release the escrow (retainage) guarantee to Rice Lake Construction upon
completion of the punch list.
3. The official start-up date for purposes of the project warranty is recognized as March 1, 2009.
4. The WTF is accepted by the City of Prior Lake.
www.cityofpriorlake.com
R'lr""n,.ill?nnQ Agpnrla R..n.QLI,,11? ?1...!l.ml.\tlf ...",,<::1 P rl",.
Phone 952.447.9800 / Fax 952.447.4245
PASSED AND ADOPTED THIS 21st DAY OF DECEMBER 2009.
I Haugen
I Erickson
I Hedberg
I LeMair
I Millar
YES
Haugen
Erickson
Hedberg
LeMair
Millar
Frank Boyles, City Manager
R:\Council\2009 Agenda Reports\12 21 09\wtf reso SLP.doc
NO
City Council Approved Design
& Construction Budget
Met CounciVCity Bldg Permit Fees
Testing Service Change Order
Emergency Siren Relocation
Total Project Budget
Final Project Cost
Detailed Resolution Expenditure Approval to Date
WTF Construction Cost
Engineering
Testing
Admin (City of Prior Lake)
Bonding Costs
City BUilding Costs (Landscaping)
City Building Costs (EquipfFum)
City Costs (Relocate Emerg. SirenIMisc)
City Construction Budget Unanocated
Met CounciVCity SAC & WAC Fees
Total
"Reflects additional anticipated work and all co's
Approved CIty Building Costs to Date
Phase 1 Landscaping
SCADA, Computers, FFE.Lighting
Phase 2 Landscaping
Total City Approved Work
. WTF Financing - Final Project Summary
FINAL PROJECT ACCOUNT EXPENDITURES 12-11-09
BUDGET
$14.016.500.00 Res 07-145
$106,502.35 Building Permit
$22,430.50 Res 08-017
~2.432.0Q No Res CM Approval
$14,147,864.85
$14,145,759.34 Acct 505 Total Project Expenses Excluding Sales Tax Reb.
$12,746,500.00 Res 07-145
$736,560.00 Res 08-142,08-205
$44,669.50 Res 08-197,08-017
$100.000.00 Res 07-145
$208,000.00 Res 07-145
$96,993.58 Res 08-121,09-072
$98,621.63 Res 08-133
$2,432.00 No Res/CM Approval
$7.585.79 Res 07-145
$106.502.35 Building Permit
$14,147,864.85
$41,345 08-121
$98,622 08-133
$55.649 09-072
$195,615
S:\Water_Supply\WTF Proj 107-122\20lJ9.12-06 Financing Sumnuuy -FINAL
Expended
Total
$12,813.826.00
$143,060.53
$38,811.07
$100.000.00
$157,918.34
$112,922.72
$68,980.00
$2,432.00
$1,306.33
$106.502.35
$14,145,759.34
$41,377.53
$68,980.00
$71.545.19
$181,902.72
Balance
-$67,326.00
-$6,500.53
$5,858.43
$0.00
$50,081.66
-$15,929.14
$29,641.63
$0.00
56.279.46
$0.00
$2,105.51
($32.84)
$29,641.63
($15.896.30\
$13,712
Remaining
Work
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0
Budgeted Funding Allocation
Water Storage Fund
Trunk Reserve Fund
Water Revenue Bonds
CO Water Storage Fund
Total
FUNDING
$2,108,934 Res 07-145 & Bldg Permit
$2.316.500 Res 07-145
$9.700.000 Res 07-145
Jt22431 Res 08-017
$14,147,865
Projected Final Funding Allocation
Water Storage Fund' $3,322,259
Trunk Reserve Fund- $2,323,500
Water Revenue Bonds $8.500.000
Total $14,145,759
"Includes Investment Earnings, Building Permll Fees and Rebates
~lnc1udes $8k transfer on 514109 to Water Storage Fund
Rebates Received to Date
Xcel Plan Review Rebate
Sales Tax 1/1/08
Sales Tax 7/1/08
Sales Tax 12/31/08
Sales Tax 10/20/09
Total to Date
Investment Earnings to Date
$22,146.00 (8114108)
$25.868.88
552.403.12
$19,106.50
$53.975.99
$173,600.49
$774,731