HomeMy WebLinkAbout09-180 Water Treatment Facililty Final Budget~~ PRj~ ~~ ti U x ~~/ 4646 Dakota Street S.E. Prior Lake, MN 55372-1714 RESOLUTION 09-180 A RESOLUTION ACCEPTING THE WATER TREATMENT FACILITY FROM RICE LAKE CONSTRUCTION AND APPROVING THE FINAL PROJECT BUDGET Motion By: Hedberg Second By: Erickson WHEREAS, Construction of the Water Treatment Facility (WTF) was completed in March of 2009; and WHEREAS, The City has been operating and maintaining the WTF for nine months and staff recommends the City Council accept the facility from Rice Lake Construction; and WHEREAS, All expenditures associated with the WTF have been made; and WHEREAS, WHEREAS, WHEREAS, The approved project budget was $14,147,864.85 and the final project cost was $14,145,759.34 or $2,105.51 under budget; and The following resolutions were approved (excludes permit and emergency siren relocation fees) as part of the project budget with the following actual expenditures: Resolution No. Approved Cost Actual Cost Variation 06-142 Desi n/En ineerin /Ins $686,560.00 $693,060.53 +$6,500.53 06-197 Testin /Ins $22,239.00 $22,239.00 $0 06-205 Desi n Modifications $50,000.00 $50,000.00 $0 07-145 Ci Pro'ect Administration $100,000.00 $100,000.00 $0 07-145 Construction $12,746,500.00 $12,813,826.00 +$67,326.00 07-145 Bondin Costs $208,000.00 $157,918.34 -$50,081.66 07-145 .Unallocated Ci Costs $7,585.79 $1,306.33 -$6,279.46 08-017 Testin $22,430.50 $16,572.07 -$5,858.43 08-121 Landsca in $41,344.69 $41,377.53 +$32.84 08-133 E ui ment/Furnishin s $98,621.63 $68,980.00 -$29,641.63 09-072 Landsca in $55,648.89 $71,545.19 +$.15,896.30 Total -$2,105.51 and The authorized expenditures for the above listed resolutions are amended to reflect actual final costs for the project. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. City Staff is authorized to release the escrow (retainage) guarantee to Rice Lake Construction upon completion of the punch list. 3. The official start-up date for purposes of the project warranty is recognized as March 1, 2009. 4. The WTF is accepted by the City of Prior Lake. www.ci ofpriorlake.com Phone 952.447.9800 /Fax 952.447.4245 PASSED AND ADOPTED THIS 21st DAY OF DECEMBER 2009. YES NO Hau en X Hau en Erickson X Erickson Hedber X Hedber LeMair X LeMair Millar Absent Millar Fra y ,City Manager M:\COUNCI~\Resolutions\2009\09-180 Water Treatment Facility Final Budget.doc