HomeMy WebLinkAbout01-131 RESOLUTION 01-131
A RESOLUTION AUTHORIZING FULL AND FINAL PAYMENT
TO SUNRAM CONSTRUCTION, INC. FOR CONSTRUCTION OF
BOUDIN'S MANOR DRAINAGE IMPROVEMENT
(CITY PROJECT #11-00)
Motion By: ERICSON Second By: ZIESKA
WHEREAS, Sunram Construction, Inc. was awarded the contract for construction of Boudin's Manor
Drainage Improvement, City Project #11-00; and
WHEREAS, Sunram Construction, Inc. has in all respects completed the cotract for construction of
Boudin's Manor drainage improvements; and
WHEREAS, the original contract for the Boudin's Manor drainage improvement is $37,114.00; and
WHEREAS, the final contract amount is $36,119.50 which is $994.50 less than the original awarded
contract amount; and
WHEREAS, the City Engineer and Project Engineer recommend acceptance of the project and final
payment of the contract.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA
that:
1. The recitals set forth above are incorporated herein.
2. Final payment is hereby authorized to be made to Sunram Construction, Inc. in the amount of
$5,912.50 which amounts to a total payment of $36,119.50 for the contract to construct Boudin's
Manor drainage improvement (City Project #11-00).
PASSED AND ADOPTED THIS 3rd DAY OF DECEMBER, 2001.
YES NQ
Mader X Mader
Ericson X Ericson
Gundlach X Gundlach
Petersen X Petersen (,~a~ j~,~
Zieska X Zieska _
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245