HomeMy WebLinkAbout9A - 2010 Street Resurfacing Project #10-012
0' PR/04>
co~ 4646 Dakota Street S.E.
U ~ Prior Lake, MN 55372-1714
I't1
I\rlNNESO~~ CITY COUNCIL AGENDA REPORT
MEETING DATE:
AGENDA #:
PREPARED BY:
APRIL 5,2010
9A
LARRY POPPLER, ASSISTANT CITY ENGINEER
AGENDA ITEM:
CONSIDER APPROVAL OF A RESOLUTION ACCEPTING BIDS AND
AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE
CITY'S STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2010
STREET RESURFACING PROJECT #10-012
DISCUSSION:
Introduction
The purpose of this agenda item is to accept the bids and authorize the Mayor
and City Manager to execute the City's Standardized Construction Contract
with McNamara Contracting for the 2010 street resurfacing project. The
following streets are scheduled for resurfacing in 2010:
1. Fremont Avenue,
2. Crossandra from Franklin Trail to Bounty Street,
3. Lords Street Neighborhood (Lords Street, Quaker Trail, Fairbanks Trail,
and Edgewater Circle),
4. Rustic Road Neighborhood (Rustic Road, Maple Trail, Glendale Avenue,
Oakland Beach Avenue, Kneafseys Street, Seven Acres Street, and Cove
Avenue), and
5. Shady Beach Neighborhood (Shady Beach Trail and Bayview Circle).
Historv
In 2009, in an effort to quickly address deteriorating streets, the City Council
approved a new program in the Capital Improvement Program (CIP) to keep
streets safe and useable until they can be reconstructed. Currently the City
has a 10+ year backlog of neighborhood street projects that are worthy of im-
mediate reconstruction. The 2009 Transportation Plan, adopted as part of the
CIP, proposes the resurfacing of streets in several neighborhoods to extend
the useable life a minimum of 10 years to allow the City to catch up with the
backlog of deteriorating neighborhood streets. The Council was very clear in
directing that only streets where existing watermain and sanitary sewer sys-
tems are in adequate condition or can be operated with minor repairs to meet
the life of the resurfacing, should be considered for this program.
The street resurfacing project involves making spot utility repairs which include
replacement of valves and hydrants that are no longer functioning properly,
along with any needed drainage repairs. The streets and infrastructure in this
year's project area were originally constructed in the 1970s. Once utility re-
pairs are made, the existing roadway will be milled and leveled as needed to
provide a surface for the new 1 'Y2-inch bituminous overlay surface. Because
the subgrade of the road is not being reconstructed, this is a far less expen-
sive construction method. However, this resurfacing is not meant to be a long-
term repair and the useable life for this type of activity is about 10 years. One
of the issues with this method is that within a year or two of the resurfacing,
cracks will begin to appear in the new surface where subgrade issues current-
www.cityofpriorlake.com
R\Council\2010 Agenda Reports\04 05 10BbQfl5tr~J1~.4-~.~Q~'ocFax 952.447.4245
Iy exist. Any cracks that appear will be sealed by the City as part of our an-
nual crack sealing program to ensure the resurfaced area remains safe and
useable for the 1 O-year design life.
In addition to the streets identified for the resurfacing program, staff is recom-
mending that Crossandra Street and Fremont Avenue be included as they
have been identified for resurfacing as part of the annual street maintenance
overlay program.
At the February 16, 2010 meeting, the City Council adopted a resolution ap-
proving the plans and specifications and authorized the advertisement for bids
for this project.
Current Circumstances
Advertisements for bids were published in both the Prior Lake American and
Construction Bulletin with bids due and opened March 15, 2010, at 1 :30 p.m.
The City received twelve (12) bids for this project, which are listed in the chart
below.
I Company
I McNamara Contracting
I Prior Lake Blacktop ...
Northwest Asphalt
Astech
I Valley Paving
I Knife River Corporation
I Wm Mueller & Sons
I GMH Asphalt
I Chard Tiling
I Hardrives
I Bituminous Roadways, Inc.
I Midwest Asphalt Corporation
Address
Rosemount, MN 55068
Prior Lake, MN 55372
Shakopee, MN 55379
St. Cloud, MN 56302
Shakopee, MN 55379
Sauk Rapids, MN 56379
Hamburg, MN 55339
Chaska, MN 55318
Belle Plaine, MN 56011
Rogers, MN 55374
Shakopee, MN 55379
Minnetonka, MN 55435
Total I
$682,126.33 I
$721,298.87 I
$723,659.18 I
$734,272.21 I
$740,396.75 1
$751,493.26 I
$752,434.46 I
$754,445.90 I
$769,079.14 I
$781,184.79\
$787,490.95 I
$841,659.15 I
In addition to the above bids for the project the City solicited proposals for
construction materials testing from the Professional Services Pool. It is very
important to test the bituminous materials used for construction to ensure
maximum performance of the overlay. The City does not have staff trained or
equipped to provide testing services. The quotes are as follows:
I Company
I Braun Intertec
I American Engineering
I Stork Twin City Testing
Address
Lakeville, MN 55044
St. Paul, MN 55114
St. Paul, MN 55114
Total
$7,227.00
$9,630.00
$10,522.00 \
Conclusion
Staff recommends awarding the construction contract to the lowest bidder,
McNamara Contracting, in the amount of $682,126.33. Previously McNamara
Contracting successfully completed the City's 2008 Overlay Project and 2002
Street Reconstruction Project.
Staff is recommending awarding the construction testing to Braun Intertec.
R\Counci112010 Agenda Reportsl04 05 1012010 street overlay agenda,doc
ISSUES:
Existina Street Condition
Existing streets in the Martinson Island (Lords/Edgewater), Shady Beach Trail
and Rustic Road neighborhoods are over 30 years old and failing. These
streets have significant degradation that affects the safety of and usability by
the public. Based on the current transportation plan and available funding,
these streets are not scheduled for full reconstruction until after 2019.
The plans and bidding of this project were based on roadway conditions prior
to the 2009/2010 winter. Because this project involves rehabilitation of exist-
ing roadways there has been additional degradation that occurred over the
winter but could not be quantified until snow melt this spring. For that reason
Staff anticipates some additional pavement removal which will require contin-
gency funding for the project.
Existina Utilities
The utilities in these streets have been evaluated and staff believes that with
replacement of valves, hydrants and minor sanitary and storm sewer repairs,
the useable life of the utility infrastructure can be extended until the streets are
reconstructed.
FINANCIAL
IMPACT:
The total proposed CIP project budget is $900,000 ($700,000 tax levy,
$100,000 Street Budget, $100,000 utility fund). The project cost is:
Construction Cost
Construction Contingency*
Engineering/Bonding (11 %)
Total Estimated Project Cost
$682,126.33
$35,000.00
$79,000.00
$796,126.33
Due to the mileage and the condition of streets being resurfaced staff believes
it is prudent to include a $35,000 construction contingency for unforeseen
construction issues. Typical issues on these types of projects include addi-
tional drainage work and utility repair.
Based on the bids received the proposed funding sources are:
Reconstruction Bonds
Street Department
Water Utility
Total Estimated Project Cost
$583,066.33
$100,000.00
$113,060.00
$796,126.33
The project is approximately $104,000 less than estimated through the CIP
process. The project savings will result in a reduction in the estimated tax levy
funding utilizing reconstruction bonds in the amount of $116,933.67.
Construction costs for the Fremont Avenue and Crossandra improvements will
be recorded in the General Fund Street Department budget, account #101-
43100-412. Construction costs for the Lords neighborhood, Rustic neighbor-
hood, and Shady Beach neighborhood will be recorded in the Construction
Fund, account #501-48370-501. Bond proceeds will be recorded in the Con-
struction Fund. Funding for the utility repair areas will be transferred from the
Water Utility to the Construction Fund.
R\Council\2010 Agenda Reports\04 05 10\2010 street overlay agenda,doc
ALTERNATIVES: 1. Approve a resolution accepting the bids and authorizing the Mayor and City
Manager to execute the City's Standardized Construction Contract with
McNamara Contracting for the 2010 Street Resurfacing Project #10-012
and accepting the quotes and authorizing the Mayor and City Manager to
execute the City's Standard Professional Services Contract with Braun In-
tertec for the 2010 Street Resurfacing Project #10-012.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direction.
RECOMMENDED Alternatives #1.
MOTION:
Rev~~ ~
Frank Boyles City'Ma ager
-
R:\Council\2010 Agenda Reports\04 05 10\2010 street overlay
O~ PR104>
~ ("
F-.. ';P
U ~
I't1
I\rlNNESO~~
4646 Dakota Street S.E.
Prior Lake, MN 55372-1714
RESOLUTION 10-xx
A RESOLUTION ACCEPTING BIDS AND AUTHORIZING THE MAYOR AND CITY MANAGER TO
EXECUTE THE CITY'S STANDARDIZED CONTRACTS FOR THE 2010 STREET RESURFACING
PROJECT #10-012
Motion By:
Second By:
WHEREAS, The following streets are scheduled for resurfacing in 2010:
1. Fremont Avenue
2. Crossandra from Franklin Trail to Bounty Street
3. Lords Street Neighborhood (Lords Street, Quaker Trail, Fairbanks Trail, and
Edgewater Circle)
4. Rustic Road Neighborhood (Rustic Road, Maple Trail, Glendale Avenue, Oakland
Beach Avenue, Kneafseys Street, Seven Acres Street, and Cove Avenue)
5. Shady Beach Neighborhood (Shady Beach Trail and Bayview Circle); and
WHEREAS, The City of Prior Lake is committed to street maintenance by improving the streets
within the City therefore reducing the need of costly reconstruction in the near future;
and
WHEREAS, A total of twelve (12) bids (provided in the chart below) were received for the identified
improvements, with the low bid from McNamara Contracting at a cost of $682,126.33.
I Company
I McNamara Contractinq
I Prior Lake Blacktop
I Northwest Asphalt
I Astech
I Valley Pavinq
I Knife River Corporation
Wm Mueller & Sons
GMH Asphalt
I Chard Tilinq
Hardrives
Bituminous Roadways, Inc.
I Midwest Asphalt Corporation
; and
Address
Rosemount, MN 55068
Prior Lake, MN 55372
Shakopee. MN 55379
St. Cloud, MN 56302
Shakopee, MN 55379
Sauk Rapids, MN 56379
Hamburq, MN 55339
Chaska, MN 55318
Belle Plaine, MN 56011
Roqers, MN 55374
Shakopee, MN 55379
Minnetonka, MN 55435
Total I
$682.126.33 I
$721,298.87 I
$723,659.18 1
$734,272.21 I
$740,396.75 I
$751,493.26 1
$752,434.46 1
$754,445.90 1
$769,079.14
$781,184.79
$787,490.95
$841,659.15
WHEREAS, City Staff recommends award of a contract to McNamara Contracting for the 2010
Resurfacing Project #10-012; and
WHEREAS, Materials testing is required to ensure performance of the materials for this project and
the City does not have in-house testing capabilities and the following quotes were
solicited for those services:
I Company Address Total
I Braun Intertec Lakeville, MN 55044 $7,227,00
American Enqineerinq St. Paul, MN 55114 $9,630.00
Stork Twin City Testinq St. Paul, MN 55114 $10,522.00 I
with Braun providing the low quote; and
R:\Council\2010 Agenda Reports\04 05 10\2010 street o~ .~W!r8trSyr8rPa~~ . com
Phone 952.447.9800 / Fax 952.447.4245
WHEREAS, Funds allocated, for the resurfacing of the Lords neighborhood, Rustic neighborhood,
and Shady Beach neighborhood will be obtained from bond sales; and
WHEREAS, The total project costs are as follows:
I Construction Cost
I Construction ContinQency
I EnQineerinQ/BondinQ (11 %)*
I Total Project Cost
*Includes Materials Testing
$682,126.33 I
$35,000.00 I
$79,000.00 I
$796,126.33 I
;and
WHEREAS, The 2010 Street Resurfacing costs shares are allocated as follows:
I Funding Source
I Street Recon Bonds
, Street Department
Watermain Repair Work
I Total
Cost I
$583,066.33 I
$100,000.00 I
$113,060.00 I
$796,126.33 I
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City's Standardized
Construction Contract for the identified street overlays with McNamara Contracting for a cost not to
exceed $682,126.33.
3. The Mayor and City Manager are authorized to execute the City's Standardized Professional
Services Contract with Braun Intertec for a not-to-exceed cost of $7,227.00 for materials testing.
4. Construction costs will be recorded in the Construction Fund (#501-48370-501) for the Lord Street,
Rustic Road and Shady Beach improvements.
5. Construction costs will be recorded in the General Fund (#101-43100-412) for the Fremont Avenue
and Crossandra improvements
6. City Staff is authorized to transfer the following amounts to the Construction Fund #501-39203:
. Enterprise Fund Water Utility ($113,060.00) # 601-49303
7. Proceeds from the bond sale will be deposited in the Construction Fund.
PASSED AND ADOPTED THIS 5TH DAY OF APRIL 2010.
YES
NO
I Myser
I Erickson
I Hedberg
I Keeney
I Millar
Myser
Erickson
Hedberg
Keeney
Millar
Frank Boyles, City Manager
R\Council\2010 Agenda Reports\04 05 10\2010 street overlay project reso.DOC