HomeMy WebLinkAbout5E - CR 21 Watermain Replacement Project o~ PRIO/f tO~ 4646 Dakota Street S,E. U ~ Prior Lake, MN 55372-1714 t'2y ~INNESO~~ CITY COUNCIL AGENDA REPORT MEETING DATE: AGENDA #: PREPARED BY: AGENDA ITEM: DISCUSSION: MAY 3,2010 5E CRAIG ELDRED, STREET AND UTILITIES SUPERVISOR CONSIDER APPROVAL OF A RESOLUTION ACCEPTING QUOTES AND AUTHORIZING FUNDS FOR RESTORATION AND FINAL COMPLETION OF THE CR 21 WATERMAIN REPLACEMENT PROJECT Introduction The purpose of this agenda item is to seek approval from the City Council to authorize funds for restoration and final completion of the CR 21 Watermain Reconstruction Project. Historv During the winter of 2008-2009, the City experienced several breaks in the CR 21 watermain between Eau Claire Trail and Quincey Street. The City Council ordered a Feasibility Report to examine the condition of the watermain and options for its repair or replacement. The Feasibility Report was presented to the City Council on June 15, 2009, Based on the condition of the watermain described and depicted in the Feasibility Study, it was determined that breaks would most likely continue if the watermain was not replaced. On June 15, 2009, the City Council authorized SRF to negotiate easements on the City's behalf for construction of the watermain on the northern boulevard of CR 21. The proposed project impacted three parcels. On August 17, 2009, the City Council approved the plans and authorized advertisement for bids for the project. On September 8,2009, the City Council approved a resolution accepting bids and awarding the City's standardized construction contract for the CR 21 watermain improvements. The watermain was put into service on November 18, 2009 and experienced an initial failure which was repaired February 2010, The watermain has been in full service since February 8, 2010, Current Circumstances Restoration of the CR 21 right-of-way and private properties has already been specified as part of the permits and agreements approved for the project. Because the watermain construction was completed in fall and winter the final restoration could not be completed concurrently. City staff obtained quotes according to the City Purchasing Policy to complete the remaining restoration throughout the entire project area. The following are the lowest quoted alternatives: www.cityofpriorlake.com Phone , 952,447 ,9800 I Fax 952.447.4245 I VENDOR EJM Prior Lake Blacktop Quirinq Excavatinq Jirik Sod Farms Ti-Zak Concrete I City Staff I Total WORK COMPLETED Sand fill 24" watermain Bituminous Restoration Watermain work Sod, Hvdro-Seedinq Curb/Sidewalk Repair RestorationlTraffic Control COST I $19,500 I $16,000 I $14,000 I $5,200 I $9,000 I $36,500 I $100,200.00 I The City portion of the work to be completed above includes the traffic control rental, abandonment of disconnected water infrastructure and restoration of easement areas including tree replacement. Based on the quotes received, City Staff recommends that a total of $100,200.00 be authorized to complete the required final restoration for the CR 21 Watermain Replacement Project. These purchases will be completed in accordance with the City's Purchasing Policy. ISSUES: Final restoration is required as part of the easement agreements and permits the City obtained for construction of the watermain. In order to minimize erosion and complete the requirements of those agreements, the City should proceed with restoration as soon as possible. Because this project involves several specialty services and includes the City's primary easUwest water system connection and an important transportation corridor the City has acted as the general contractor coordinating subcontractors and overall construction. FINANCIAL IMPACT: The required funding is available in the Water Utility fund for the reconstruction of the CR 21 Watermain. To date the project has the following expenditures: ALTERNATIVES: I ITEM I Initial EmerQencv Repair Costs I Construction Costs I Final Repair/Restoration Costs (pendinq) I Proiect Costs I 1, AMOUNT I $61,710.02 I $5'10,512.19 I $100,200.00 I $173,450.00 I Total Costs $845,872.21 I Approve a resolution accepting quotes and authorizing funds for restoration and final completion of the CR 21 Watermain Reconstruction Project. 2. Table this Resolution and provide alternative direction to staff. 3, Deny the resolution. RECOMMENDED Alternative # 1 MOTION: ReView~;~ Frank Boyles, cpa~ o~ PRI01> t ~ ~ 4646 Dakota Street S,E. U ~ ~ Prior Lake, MN 55372-1714 ~INNESO~~ RESOLUTION 10-XXX RESOLUTION ACCEPTING QUOTES AND AUTHORIZING FUNDS FOR THE RESTROATION AND FINAL COMPLETION OF THE CR 21 WATERMAIN PROJECT WHEREAS, WHEREAS, WHEREAS, WHEREAS, WHEREAS, WHEREAS, WHEREAS, WHEREAS, Motion By: Second By: The CR 21 watermain between Eau Claire Trail and Quincy Street is a major connection piece of the City's water infrastructure; and Breaks that occurred during the 2008-2009 winter season revealed damage that if left unrepaired would most likely continue to fail annually resulting in considerable cost to the City; and On June 15, 2009 the City Council accepted a Feasibility Study for the repair and reconstruction of the CR 21 watermain and authorized Staff to pursue relocation of the watermain to the northern boulevard of CR 21 utilizing directional drilling; and SRF was authorized to proceed with easement acquisition on the City's behalf; and On August 17, 2009 the City Council approved the plans and specification and authorized the advertisement for bids; and On September 8, 2009 the City Council accepted bids and awarded contracts for the construction of the County Road 21 water main; and City staff obtained the following quotes according to the City Purchase Policy: I VENDOR I EJM I Prior Lake Blacktop I Quiring Excavating I Jirik Sod Farms I Ti-Zak Concrete I City Staff I Total WORK COMPLETED Sand fill 24" water main Bituminous Restoration Water main work Sod, Hydro-Seeding Curb/Sidewalk Repair Restoration Supplies/Traffic Control COST I $19,500 I $16,000 I $14,000 I $5,200 I $9,000 I $36,500 I $100,200.00 I ; and The funding source is from the Water Utility Fund and the project expenditures to date are provided in the table below: I ITEM I Initial Emergency Repair Costs I Construction Costs I Final Repair/Restoration Costs I Proiect Costs I Total Costs AMOUNT $61,710.02 $510,512.19 $100,200.00 $173.450.00 $845,872.21 and; www.cityofpriorlake.com c,Bbon~\r9Ei2,;r44 'UilSOO;/ cFaK952.44 7.4245 WHEREAS, City staff recommends authorization of the funds for completion of the County Road 21 water main improvements. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. The City Council authorizes City staff to expend an amount not to exceed of $100,200,00 in accordance with the Purchasing Policy for completion of the repairs and restoration for the County Road 21 water main improvement project 3. Watermain reconstruction costs will be recorded in the Water & Sewer Fund (#601-49400-530), PASSED AND ADOPTED THIS 3rd DAY OF MAY 2010. YES NO Myser Erickson Hedberg Keeney Millar Myser Erickson Hedberg Keeney Millar Frank Boyles, City Manager R:\Council\2010 Agenda Reports\05 03 10\CR 21 Watermain Bid Resolution.doc: