CITY COUNCIL AGENDA REPORT
JUNE 7, 2010
10C
ROSS BINTNER, WATER RESOUCES ENGINEER
CONSIDER APPROVAL OF TWO RESOLUTIONS: 1) ACCEPTING
PROPOSALS AND AUTHORIZING WSB TO PROVIDE SURVEYING
AND WETLAND DELINEATION SERVICES; AND, 2) ACCEPTING
PROPOSALS AND AUTHORIZING NTS TO PROVIDE TESTING
SERVICES FOR THE 2011 WATER QUALITY MAINTENANCE AND
RETROFIT PROJECT.
Introduction
The purpose of this agenda item is to accept the proposals for professional
services related to design, construction surveying, wetland delineation and
pond sediment testing for the 2011 Water Quality Maintenance and Retrofit
Project #11-012.
Historv
The City of Prior Lake owns the majority of the stormwater conveyance and
treatment system (ponds, swales, culverts) that provides flood protection
and water quality treatment of rainwater runoff. To keep the system in
good working order, and maintain the mandated average designed level of
service; periodic maintenance must be undertaken. The city council
recently approved such maintenance for 2009 which is presently underway.
This agenda item is for work to be undertaken in 2011.
The City of Prior Lake inspects its entire stormwater system on a 3-5 year
rotating basis. The result of these inspections triggers minor maintenance
work that is completed annually by City staff. Inspections also lead to large
full pond dredging projects and efficiency and capacity retrofit which occur
biennially (currently every odd year). Water quality maintenance and
retrofit projects are prioritized and completed based on the following
criteria: cost efficiency, current level of service, and rights of access.
City staff solicited proposals for surveying and testing services needed to
collect information to assist in the process of prioritizing these ponds, and
creating maintenance cost estimates and plans.
Current Circumstances
The 2011 Water Quality Maintenance Project includes five water quality
areas. These five areas show signs of underperforming their design level
of service and are in need of repair or modification. In order to determine
the parameters needed to prepare the plans and specifications for this
project the City needs to complete survey/wetland delineation work and
testing. The results of the surveying and testing will allow City Staff to
produce maintenance plans and cost estimates for full maintenance to be
completed from January 1, 2011 through October 31, 2011.
R\CounCii201O Agenda Reports\06 07 1CJJOOGCJ7 IGENDA !\ccept Ouotes Survey arid Testing docx
Surveying and Wetland Services
Staff has requested proposals from the three firms from our consultant pool
for surveying services. They include: Bolton and Menk Inc., WSB and
Associates, and MFRA. Each of these firms has a positive history of
construction staking and wetland delineation services for the City of Prior
Lake. The bids received by these firms are tabulated below. Note that
MFRA did not respond to the RFP:
I Firm Name
I MFRA
I WSB
I BMI
, Base Price
Nonresponsive
$4,980.00
$10,700.00
The proposals received were analyzed and City staff is recommending that
WSB perform the surveying and wetland delineation services for this
project. WSB has performed the construction staking and wetland
delineations for City utilities in the past. The quoted represent a "Base Bid"
that was based on assumptions about the amount of ponds to be
maintained. Final determination on the amount of survey work required will
depend on the final design estimated costs and any contamination detected
during testing. These factors will determine whether the City will complete
maintenance on less than or more than five areas based on budget
constraints.
Soil Testing Services
Staff has requested proposals from the three qualified testing firms. They
include: NTS, Braun Intertec, and Pace Analytical. Each of these firms has
the unique ability to provide the State-mandated soil tests:
I Firm Name
I NTS
I Braun Intertec
I Pace Analytical
. Base Price
$4,532.00
$5,225.00
$6,420.50
The proposals received were each analyzed and City staff is
recommending NTS to perform the soil testing services for the 2011 Water
Quality Maintenance and Retrofit project. NTS performed similar services
for the 2009 pond maintenance project and met the timelines and testing
requirements. Each firm provided a "Base Bid" based on assumptions of
numbers of tests required. The testing protocol requires a varying level of
effort based on the sample content and a predefined decision matrix. The
actual cost will vary depending on the soil sample content.
ISSUES:
Surveying, wetland delineation, and soil chemical tests must be done by or
under the supervision of a registered land surveyor, or certified testing
laboratory and thus qualifies as a professional service. The City of Prior
Lake is not equipped or licensed to perform surveying and testing for these
projects.
FINANCIAL
IMPACT:
The surveying and testing for this project will be funded through the City
Water Quality utility, capital outlay budget item #49420-530.
R\Council\2010 Agenda Reports\06 07 10,1001307 A.GE~~D," Accept Que,tes Survey and Test!ngdo~x
2
ALTERNATIVES: The alternatives are as follows:
1. Approve a resolution accepting proposals and authorizing the Mayor
and City Manager to execute the City's Standardized Contract for
Professional Services with WSB for Surveying and Wetland Delineation
Services for the 2011 Water Quality Maintenance and Retrofit project.
2. Approve a resolution accepting proposals and authorizing the Mayor
and City Manager to execute the City's Standardized Contract for
Professional Services with NTS for Soil Testing Services for the 2011
Water Quality Maintenance and Retrofit project.
3. Table the Resolution for a specific reason.
4. Deny the Resolution.
RECO.. MMEN.DED. A7t rnatives # 1 and #2
MOTION:
Revit~ j~:' ,1 ~\ _"~'-_"_______
Frank BOYI.e , C. it ty1< Inager
.J
i
R.\Council\2010 A.geilda Reports\O(j 07 10,100\)07 AGEr~DA Accepi OUI)ies SUrVSy and
3
4646 Dakota Street SE
Prior Lake_ MN 55372
RESOLUTION 10-xxx
A RESOLUTION AUTHORIZING WSB TO PROVIDE SURVEY, STAKING AND WETLAND
DELINEATION SERVICES FOR THE 2011 MAINTENANCE AND RETROFIT PROJECT
Motion By:
WHEREAS,
WHEREAS,
WHEREAS,
Second By:
Design survey, wetland delineations and construction staking are necessary to properly
design, install and maintain City infrastructure; and,
Survey, staking and wetland delineation is needed for the following project: 2011 Water
Quality Maintenance and Retrofit Project #11-012; and,
The City does not have the in-house expertise to complete these services; and,
The City solicited quotes from three firms and evaluated quotes from two firms qualified
firms to provide surveying staking and wetland delineations services for the 2011 Water
Quality Maintenance and Retrofit Project #11-012.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
WHEREAS,
1. The recitals set forth above are incorporated herein.
2. WSB is hereby selected to provide Surveying Services for the 2011 Water Quality Maintenance and
Retrofit Project for a base price in the amount of $4,980.00.
3. The Mayor and City Manager are authorized to execute the City's Standardized Professional Services
Agreement with WSB on behalf of the City.
4. Funding for these services will be drawn from the Water Quality Fund #49420-530.
PASSED AND ADOPTED THIS 7th DAY OF JUNE 2010.
I Myser
I Erickson
Hedber!l
Keenev
Millar
YES
NO
Myser
Erickson
Hedberg
Keeney
Millar
Frank Boyles, City Manager
R\Counclt\2010 Agenda Reports\06 07 10\100607 RESOLUTION Accept Survey.docxR:\Council\20 1 0 Agenda
Reports\06 0710\100607 RESOLUTION Accept Survey.docx
4646 Dakota Street SE
Prior Lake. MN 55372
RESOLUTION 1 Q-xxx
RESOLUTION AUTHORIZING NTS TO PROVIDE SOIL TESTING
SERVICES FOR THE 2011 WATER QUALITY MAINTENANCE AND RETROFIT PROJECT
Motion By:
WHEREAS,
WHEREAS,
WHEREAS,
Second By:
The State requires soil testing of pond sediment prior to pond maintenance projects; and
Soil testing is needed for the following projects: 2011 Water Quality Maintenance and
Retrofit Project #11-012; and
The City does not have the equipment J expertise or required licensure to provide these
services; and
The City solicited and evaluated quotes from three qualified firms to provide soil testing for
the 2011 Water Quality Maintenance and Retrofit Project #11-012.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
WHEREAS,
1. The recitals set forth above are incorporated herein.
2. NTS is hereby selected to provide soil testing services for the 2011 Water Quality Maintenance and
Retrofit Project for a base price in the amount of $4,532.00 and the unit pricing rates shown in the
proposal and attached to the City's Standard Professional Services Contract will be applied.
3. The Mayor and City Manager are authorized to execute the City's Standard Professional Services
Agreement on behalf of the City.
4. Funding for these services will be drawn from the Water Quality Fund #49420-530.
PASSED AND ADOPTED THIS 7th DAY OF JUNE 2010.
Myser
Erickson
Hedberg
Keeney
Millar
YES
NO
Myser
Erickson
Hedberg
Keenev
Millar
Frank Boyles, City Manager
RICouncii\2010 Agenda Reports\06 07 10\100607 RESOLUTION Accept Testing.docxR:\Council\20JO Agenda
Reports\06 07 10\100607 RESOLUTION Accept Testing .docx