4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL AGENDA REPORT
JUNE 21, 2010
9A
JERIL YN ERICKSON, FINANCE DIRECTOR
STEVE ALBRECHT, PUBLIC WORKS DIRECTOR
JERIL YN ERICKSON, FINANCE DIRECTOR
STEVE ALBRECHT, PUBLIC WORKS DIRECTOR
CONSIDER APPROVAL OF TWO RESOLUTIONS: 1) APPROVING THE
2011-2015 CAPITAL IMPROVEMENT PROGRAM (CIP); AND 2)
APPROVING THE STREET RECONSTRUCTION PLAN
Introduction
The purpose of this agenda item is for the City Council to consider two
resolutions approving the 2011-2015 CIP and the Street Reconstruction Plan.
Historv
City staff updates the CIP on an annual basis. The CIP is designed to identify
infrastructure improvements needed due to ongoing maintenance and repair and
community growth and the associated funding sources. Such projects include
City-initiated improvements, county and state road improvements and
improvements requested by developers. The 2011-2015 CIP ($25.4 million) is
similar in scope to the 2010-2014 CIP ($27.8 million). The 2011-2015 CIP only
reflects the City's share of other governmental agency projects.
A Council workshop was held on April 5, 2010 to discuss the CIP. A draft copy
of the 2011-2015 Capital Improvement Program was distributed for review in
conjunction with that workshop. The CIP included a summary of demands
versus funding sources which reflected the projected cash balances after taking
into account conservative revenue projections, CIP construction demands and
2010 construction obligations. Projects were presented by department, funding
source, and provided detail on each project.
Included with the CIP were the following long-term planning documents:
. Equipment Replacement Plan (2011-2022) - identifies the City's vehicle
and equipment needs and establishes a regular replacement schedule.
. Park Equipment Replacement Plan (2011-2036) - identifies the equipment
replacement demands for 46 neighborhood parks.
. Transportation Plan (2011-2020) - identifies the major roadway
improvements involving both new and reconstruction projects that need to be
coordinated with Scott County.
Staff provided a detailed overview of the 2011 projects and highlights for the
major projects scheduled for 2012-2015 previously at a city council workshop.
The impact of the bonds that would be required to support the1 O-year
R\CoLlncil\2010 Agenda Reports\06 2110\CIP Agenda.docR:\Council\201 0 Agenda Reports\06 21 1 O\CIP Agenda.doc
transportation plan including street reconstruction was graphically shown from an
annual debt levy perspective as well.
On April 12, 2010 the Prior Lake Planning Commission reviewed the 2011-2015
Capital Improvement Program (CIP). The Commission found that the CIP was
consistent with the goals and objectives of the City of Prior Lake Comprehensive
Plan.
On June 7, 2010 the City Council held a public hearing for the CIP and Street
Reconstruction Plan. No public comments were received at the hearing and the
City Council directed staff to prepare resolutions to be considered at the June
21st City Council meeting.
Current Circumstances
It is important for the Council to recognize that the CIP is a flexible planning tool
that is affected by the actions of a number of governmental agencies (State,
County and Shakopee Mdewakanton Sioux Community). The projects that are
reflected in year 2011 of the 2011-2015 CIP will be incorporated into the 2011
budget.
The improvements that are funded in full or partially by tax levies have a direct
impact on the level of property taxes payable in future years. Bond proceeds are
utilized to cashflow the project and debt levies are adopted to repay the debt
service.
Actions by the school district and the county will also influence the level of taxes
through their annual levies and periodic referenda and bond issues.
A copy of the final proposed CIP has been included with this agenda report. It
reflects the deletion of two projects that were noted in the June 7, 2010 agenda
report: 1) GIS Data and 2) construction of Stonebriar Park play equipment in
2011.
Conclusion
The City Council should approve the 2011-2015 CIP and Street Reconstruction
Plan as proposed.
ISSUES:
Following Council approval of the Capital Improvement Program, Engineering
staff will prepare a feasibility report for those projects identified for next year.
Adequate lead time is important for surveying, right-of-way acquisition and
engineering to obtain the best possible bids, which has generally occurred when
the City is able to put projects out for bid early in the year.
Subsequent years in the CIP are important from a planning perspective. Our
objective in preparing the CIP has been to balance the tax impacts from year to
year while addressing infrastructure needs.
By approving the Street Reconstruction Plan as part of the Transportation Plan
the City will be able to issue Street Reconstruction bonds for these projects. It
should be noted that if within 30 days of the Public Hearing a petition signed by
at least 5% of the votes cast in the last municipal election is received the City
may only issue Street Reconstruction Bonds after approval of a referendum in
accordance with State Statute. This does not affect the issuance of 429 Bonds
for reconstruction projects.
R:\Collncil\2010 Agenda Reports\06 2110\CIP Agenda.doc
2
FISCAL IMPACT: In reviewing the final proposed 2011-2015 Capital Improvement Program, the
Council should consider the annual tax impact of the scheduled projects. While
state levy limits have been imposed through 2011, a special exception exists for
debt levies associated with capital improvement program financing.
The major projects proposed for 2011 involving a property tax levy (payable
2012) are listed below:
I Project Description
Boudins Area Street Reconstruction (Phase 1)
CR21/Arcadia Intersection - ROW & Construction
I Total
Project Levy
$ 840,000
910,000
$1,750,000
The 2011-2015 CIP includes projects that are funded by bond proceeds. Bonds
are issued for the project costs that the City is funding through tax levies as well
as the costs that are specially assessed to property owners. The CIP anticipates
$12,022,000 in bonding for projects in the Transportation Plan for 2011-2015 and
$1,500,000 for a 500,000 gallon water storage unit in 2013. The following chart
reflects all bonding requirements referenced in the CIP and Transportation Plan.
It does NOT include the bonding that may be presented to residents by
referendum for major fire equipment purchases (identified in the Equipment
Replacement Plan) and community park improvements (identified in the Park
Equipment Replacement Plan) beginning in 2018.
The following chart reflects the cumulative effect of new debt issued and the
retirement of existing debt. The top line is the resulting debt balance at the end
o..!.- the ~.ear.
$40.0
Projected Debt Balances
06.07.2010
$5.0
"""-"~'
$35.0
$30.0
............. ' , .~
$25.0
~
c
~$20.0
'E
:E$15.0
$10.0
$0.0
"C) ,," ",,'l- ,,~ "I>. ,,'=> ,,'0 ,,'\
'l-C) 'l-C) 'l-" 'l-C) 'l-C) 'l-C) 'l-C) 'l-C)
I _Existing Debt __NewCIP Debt
",,'0 ""C!! n'\''l-C)
'l-" 'l-" ~
The impact of the 2011-2015 CIP and other anticipated bond payment
adjustments on the debt service property tax levy is reflected in the following
table:
R:\CoLlncil\2010 Agenda Reports\06 2110\CIP Agenda.doc
3
Projected Change in Debt Levy Totals
I 2011 -
2011 2012 2013 2014 2015 2015
Debt:
Existing CIP (60,589) (52,438) (58,638) (109,837) (158,037) (439,539)
New CIP 109,000 210,000 154,000 240,000 240,000 953,000
EDA Lease Revenue 15,000 15,000 15,000 15,000 15,000 75,000
Market Referendum 20,463 27,162 34,325 (160,057) 41,363 (36,744)
Chan!je in Debt Levy 83,874 199,724 144,687 (14,894) 138,326 551,717
Each year, certain bond issues mature and the corresponding debt service
payments are eliminated. In the early 2000s, the level of bonding was lower due
to the capital improvement projects being much smaller in scope. Current
projects are larger due to the fact that we have accelerated the street
reconstruction plan in order to address maintenance issues in a more reasonable
time frame. Therefore, the amount of debt service dropping off each year is less
than the amount that we are adding for new CIP projects. This results in an
increase in the debt service property tax levy.
The table also reflects the debt associated with the EDA Lease Revenue bond
which funded the construction of city hall and the police station incrementally
increases each year. The debt associated with Market Referendum bonds which
funded park improvements and construction of the fire stations also incrementally
increases each year. In 2013, the bonds for fire station #1 mature which results
in a reduction in debt levy in 2014.
The debt service for 2011 is already established. Bonds were issued in 2010 for
the CR12 Phase III, CR21 Extension, CR42/McKenna Intersection Signal, and
Shady Beach, Rustic Road and Lords Street resurfacing projects. The first levy
associated with the 2010 bond issue will be in 2011.
The proposed CIP projects will impact the debt service levy beginning in 2012.
The anticipated bond payments on debt issued in conjunction with these projects
along with payment adjustments on current bonds would result in an increased
debt service levy of approximately $199,724 for 2012, $144,687 for 2013, and
$138,326 for 2015. The 2014 debt service levy would have increased but, due to
the fire station #1 bonds maturing in 2013, the overall impact is a decrease.
EauiDment ReDlacement Plan
The Equipment Replacement Plan (ERP) utilizes general tax levies to support
replacement of the City's equipment and vehicle fleet. Whereas historically, the
Police Department equipment inventory was included with the ERP for
informational purposes only, it is now included in the proposed 2011-2022 ERP
as a planned use of funds. As a result, the purchase of police squad cars will be
funded by the Revolving Equipment Replacement Fund instead of the General
Fund. The property tax levy reflects incremental annual increases over the
program's 12-year term. The ERP also has as one of its funding sources an
annual transfer from the Water & Sewer Fund. This transfer is incrementally
increased every other year because a significant portion of the equipment also
serves the Water and Sewer departments.
R\CoLlncil\2010 Agenda Reports\06 2110\CIP Agenda.doc
4
Park EauiDment ReDlacement Plan
The Park Equipment Replacement Plan (PERP) utilizes general tax levies to
support the ongoing repairs and maintenance reflected in the General Fund
Parks Department budget. The PERP reflects a decrease in 2011 and
incremental increases between $15,000 and $50,000 for years 2012 through
2015 based on the current equipment replacement philosophy. Staff, along with
the Parks Advisory Committee, will be evaluating this philosophy over the next
12-24 months to determine if it should be adjusted to meet changing
demographics in the community.
In 2009, the Revolving Park Equipment Fund was established with a $100,000
transfer from the General Fund to fund future park maintenance expenditures.
The 2010 budget included a $100,000 transfer. Beginning in 2011, staff
recommends that the transfer be reduced to $50,000. This reduced level of
funding is sufficient to meet the maintenance needs currently projected by city
park staff.
Other Lona-Term Plans
Three other long-term plans were briefly discussed during the April 5, 2010
workshop: the Water Plan, the Sanitary Sewer Plan, and the Water Quality Plan.
These plans will be presented to the City Council later this year and incorporated
into the Capital Improvement Program at that time.
Approval of the CIP does not constitute final project approval. All of the projects
included in the CIP will come before the City Council several times prior to final
approval. All future bonding decisions are approved by the City Council, as well.
ALTERNATIVES: The following alternatives are available to the City Council:
1. Approve a resolution approving the 2011-2015 CIP.
2. Approve a resolution approving the Street Reconstruction Plan.
3. Table the Resolution(s) for a specific reason.
4. Deny the Resolution(s) and provide staff with additional direction.
Alternatives #1 and #2.
~ C1I,I( ~g~/I~~!ty Manager
R\CoLlncil\2010 Agenda Reports\06 2110\CIP Agenda.doc
5
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 10-xxx
A RESOLUTION APPROVING THE 2011-2015 CAPITAL IMPROVEMENT PROGRAM
Motion By:
Second By:
WHEREAS, The purpose of the Capital Improvement Program (CIP) is to protect the infrastructure of
the City of Prior Lake by establishing a replacement plan for existing infrastructure and by
identifying those improvements necessary to accommodate the growth of the community;
and
WHEREAS, The CIP is a flexible planning document that attempts to balance the financial resources
of the City with its needs; and
WHEREAS, It is intended for the CIP to be established for a period of five (5) years and to be updated
annually; and
WHEREAS, On June 7, 2010, the City Council of Prior Lake conducted a Public Hearing on the 2011-
2015 CIP and offered opportunity for public testimony on the capital spending priorities of
the City Council; and
WHEREAS, The City reasonably expects to reimburse the expenditures made for certain costs of the
projects included in the CIP from the proceeds of bonds.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City has determined to make a declaration of official intent ("Declaration") to reimburse certain
estimated costs for projects included in the CIP from proceeds of bonds in accordance with the
Internal Revenue Service Reimbursement Regulations (Treasury Reg. 1.150-2).
3. The 2011-2015 Capital Improvement Program is hereby approved.
4. The City may declare other separate statements of reimbursement intent in connection with
specific public improvements projects as they are initiated under Minnesota Statutes Chapters 429
and 444, or for other capital projects, with the understanding that such additional declarations of
reimbursement intent will supplement this resolution. All reimbursed expenditures will be capital
expenditures, costs of issuance of the bonds, or other expenditures eligible for reimbursement
under Section 1.150-2( d)(3) of the Reimbursement Regulations.
5. This Declaration has been made no later than 60 days after payment of any original expenditure to
be subject to a reimbursement allocation with respect to the proceeds of bonds, except for the
following expenditures:
R:\CoLlncil\2010 Agenda Reports\06 2110\CIP Final ResolLltion.doc
a. costs of issuance of bonds;
b. costs in an amount not in excess of $100,000 or five percent of the proceeds of an issue;
or
c. "preliminary expenditures" up to an amount not in excess of 20 percent of the aggregate
issue price of the issue or issues that are reasonably expected by the City to finance the
project for which the preliminary expenditures were incurred. The term "preliminary
expenditures" includes architectural, engineering, surveying, bond issuance, and similar
costs that are incurred prior to commencement of acquisition, construction or rehabilitation
of a project other than land acquisition, site preparation, and similar costs incident to the
commencement of construction.
6. This Declaration is an expression of the reasonable expectations of the City based on the facts and
circumstances known to the City as the date hereof. The anticipated original expenditures for the
Projects and the principal amount of the bonds are consistent with the City's budgetary and
financial circumstances. No sources other than proceeds of bonds to be issued by the City are, or
are reasonably expected to be reserved, allocated on a long term basis, or otherwise set aside
pursuant to the City's budget or financial policies to pay such Project expenditures.
7. This Declaration is intended to constitute a Declaration of the Official Intent for the purposes of the
Reimbursement Regulations.
PASSED AND ADOPTED THIS 21st DAY OF JUNE, 2010.
YES
NO
I Myser
I Erickson
I Hedberg
I Keeney
I Millar
Myser
Erickson
Hedberg
Keeney
Millar
Frank Boyles, City Manager
R:\COll nci 1\20 1 0 Agenda Reports\06 2110\CIP final Resollltion.doc
2
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 1 a-xxx
A RESOLUTION ADOPTING THE STREET RECONSTRUCTION PLAN AND THE INTENT TO ISSUE
GENERAL OBLIGATION STREET RECONSTRUCTION BONDS
Motion By:
Second By:
WHEREAS, The following table identifies the Street Reconstruction Plan financing elements:
Year Improvement Total City Estimated Estimated
Cost Reconstruction Total Bonding
Bonds
2011 Boudins/Rut~ers Area Phase 1 $1,950,000 $0 $1,400,000 1
2011 CR 21/Arcadia Intersection $2,675,000 $910,000 $910,000
I 2012 Industrial Park $900,000 $0 $800,000
I 2012 Boudins/RutQers Area Phase 2 $2,180,000 $0 $1,630,000
I 2012 CR21/Fountain Hills Signal $300,000 $100,000 $100,000
I 2013 Main Ave/Ridgemont $1,875,000 $1,100,000 $1,100,000
I 2013 Martindale/Carriage Hills Resurf. $350,000 $300,000 $300,000
I 2013 Mushtown/Panama/Maple $1,475,000 $0 $1,300,000
I 2014 Franklin Trail Resurfacin~ $400,000 $300,000 $300,000 1
2014 Eau Claire /Highland/ $3,320,000 $0 $2,670,000
Marsh/Skyline
I 2015 CR 21/Main/Pleasant $3,000,000 $1,455,000 $1,455,000 1
2015 CR 83 CooP AQreement $57,000 $57,000 $57,000 I
Total $18,482,000 $4,222,000 $12,022,000 ]
;and
WHEREAS, Issuing general obligation bonds is one mechanism to fund street reconstruction projects.
Adopting a Street Reconstruction Plan with the intent to issue general obligation street
reconstruction bonds does not require the City to utilize this mechanism; and
WHEREAS, The total estimated general obligation street reconstruction bonds for the 5-year program
is $4,222,000; and
WHEREAS, Street reconstruction is necessary to provide residents the opportunity of safe travel while
commuting throughout the City.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
R:\CoLlncil\2010 Agenda Reports\06 2110\CIP Street Recon ResolLltion.doc
1. The recitals set forth above are incorporated herein.
2. The City Council authorizes the adoption of the Street Reconstruction Plan with the intent to issue
general obligation street reconstruction bonds
PASSED AND ADOPTED THIS 21st DAY OF JUNE, 2010.
YES
NO
I Mvser
I Erickson
I Hed ber!j
I Keeney
I Millar
Myser
Erickson
Hedber!j
Keeney
Millar
Frank Boyles, City Manager
R:\CoLlncil\2010 Agenda Reports\06 21 10\CIP Street Recon ResolLltion.doc
2
4646 Dakota Street SE
Prior Lake. MN 55372
Date:
June 21, 2010
To:
Mayor Myser, Council Members and Residents of Prior Lake
Frank Boyles, City Mmager U, c.1..
2011-2015 Capital Improvement pr-:a.l · -
From:
Subject:
One of the most fundamental responsibilities of local government is the construction and maintenance of
infrastructure including streets, trails, sewer, water, parks and public buildings. Our 2030 Vision and Strategic Plan
acknowledges this fact.
Prior Lake's five-year Capital Improvement Program is directly responsive to the City's 2030 Vision and Strategic
Plan. The Strategic Plan serves as our vision and our "things to do" list. How that list is prioritized, funded and
converted into City projects is determined largely through the five-year Capital Improvement Program (often
referred to as the CIP).
Each year, forecasts for projects that will be needed, estimated costs and possible funding sources are programmed
into the CIP for the next five years. The CIP is updated, evaluated and approved each year by the City Council as
projects are completed and priorities change. The purpose of the CIP is to assure that funds are available when
projects are contemplated. More importantly, the CIP helps the City Council and staff gauge when funding sources
are sufficient to build the infrastructure our community needs.
Every year, enhancements are made to the CIP. This year, a debt anal)Csis section was added to provide the user
with information regarding the impact on the amount of debt the City will have and the corresponding impact on
the property tax levy for debt service.
The attached 2011-2015 CIP contains new and continued projects critical to the development of our community
and achievement of our 2030 Vision and Strategic Plan goals. It reflects an aggressive approach to upgrading the
conditions of our streets and infrastructure in direct response to citizens' feedback.
All-in-all, the 2030 Vision and Strategic Plan establishes the vision for our community.. . and the Capital
Improvement Program allows us to achieve it!
2011- 2015 CAPITAL IMPROVEMENT PROGRAM
Adopted June 21, 2010
by the
PRIOR LAKE CITY COUNCIL
Mayor
Councilmember
Councilmember
Councilmember
Councilmem ber
Mike Myser
Warren Erickson
Ken Hedberg
Rick Keeney
Steve Millar
Term EXDires
December 31, 2012
December 31, 2012
December 31, 2010
December 31, 2012
December 31, 2010
CITY MANAGER
Frank Boyles
FINANCE DIRECTOR
Jerilyn Erickson
PUBLIC WORKS DIRECTOR / CITY ENGINEER
Steve Albrecht
2011 - 2015 CAPITAL IMPROVEMENT PROGRAM
"COMMUNITY CAPITAL ASSETS - Quality infrastructure (municipal utilities, parks,
buildings, roadways, etc.) is the essential capital cornerstone of a great and vibrant community.
Such infrastructure must be completed in a timely manner using specifications which
emphasize longevity and cost effectiveness. Once installed, the City must maintain these assets
to maximize product life. . The interconnection of infrastructure with neighbors is desirable to
protect against system failures and improve cost effectiveness." - 2030 Vision and Strategic
Plan
"Community Capital Assets," one of the ten vision elements of the 2030 Vision and Strategic
Plan (2030 VSP), represents an area of strategic importance that must be addressed to make the
2030 VSP a reality.
The Prior Lake Capital Improvement Program (CIP) addresses this vision element by focusing on
long-term planning for the. expansion, replacement and/or maintenance of capital assets. Capital
assets refer to infrastructure (water, sewer, storm water, streets and transit), vehicles and
equipment, and park equipment.
The CIP is reviewed on an annual basis to identify the need for expansion, replacement and/or
maintenance; the timeframe to complete the project; and the appropriate funding source. The
final document reflects the specific goals, policies and priorities of the City Council and the 2030
Vision and Strategic Plan. It is important to note that the CIP is a planning document and
contains estimates for the project and equipment costs. Prior to the implementation of any
individual improvement project, staff must prepare a feasibility study, conduct a public hearing,
request bids for the construction costs, and obtain approval for all phases of the project from the
City Council.
The CIP also includes the following long-term plans: Transportation Plan, Equipment
Replacement Plan, and a Park Equipment Replacement Plan.
A ten (10) year Transportation Plan has been developed in an effort to coordinate city and county
improvements that require a cooperative funding agreement between our two jurisdictions.
The Equipment Replacement Plan serves to identify the City's equipment needs on a long-term
basis and to provide a regular replacement schedule. The equipment purchases for the Fire, Police
and Public Works departments are processed through a revolving equipment fund. Equipment
purchases that are typically less than $5,000 are incorporated into the annual operating budgets
for the specific departments.
A Park Equipment Replacement Plan identifies the equipment needs for each neighborhood and
community park over the next twenty-six (26) years.
TABLE OF CONTENTS
1. Demands versus Funding Sources
· This table shows the impact of the improvements identified in the CIP on
each of the funding sources.
2. Projects by Department
· This table categorizes each of the projects by department. The associated
funding source for each project is also shown.
3. Projects by Funding Source
· This table categorizes each of the projects by funding source.
4. Project Detail
· This table provides a detailed description, purpose, and cost/benefit impact
statement for each of the projects.
5. 2011 - 2020 Transportation Plan
.
This table provides a ten-year summary of street improvement projects.
6. 2011 - 2022 Equipment Replacement Plan
.
A table and chart provide a summary of the uses and sources of funds.
Detailed equipment schedules are included for the following departments:
o Fire Department
o Police Department
o Public Works Department
.
7. 2011- 2036 Park Equipment Replacement Plan
.
This summary provides a summary of uses and sources of funds.
This summary also identifies future community park referendum needs.
.
8. Debt Analysis
9. Future Information
CAPITAL IMPROVEMENT PROGRAM
Demands vs. Funding Sources
1/1/10 Cash Six-Year Revenue CIP Construction 2010 Construction 1/1/16 Projected
Funding Source Balances Projection (Net) Demands Encumbrances Cash Balances
Water Fund 3,844,800 (1,447,559) 3,040,000 330,000 (972,759)
Sewer Fund 2,545,200 (2,120,792) 1,731,000 - (1,306,592)
Water Quality Fund 657,000 941,338 1,711,701 122,000 (235,363)
Capital Park Fund 144,000 705,000 255,000 76,000 518,000
Trunk Reserve Fund 1,094,000 1,866,250 130,000 85,000 2,745,250
Street Oversize Fund 513,000 615,000 100,000 20,000 1,008,000
Water Storage Fund 96,000 1,800,000 1,800,000 - 96,000
Transit Fund 1,708,000 (1,979,176) 153,000 40,000 (464,176)
Municipal State Aid - 2,600,000 2,135,000 - 465,000
Project Tax Levy - 8,542,000 8,542,000
Special Assessments - 3,480,000 3,480,000
Intergovernmental - 2,315,000 2,315,000
TOTALS $
10,602,000 $
17,317,061 $
25,392,701 $
673,000 $
1,853,360
CITY OF PRIOR LAKE PROJECTS BY DEPARTMENT
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Project Reference 2011 2012 2013 2014 2015 Total
All City Departments
Fiber Optic Network Connection CIP1 200,000 200,000
Water Storage Fund 200,000 200,000
All City Departments Total - - 200,000 - - 200,000
Public Works (Parks)
Field Backstops CIP2 5,000 5,000 10,000
Capital Park Fund 5,000 5,000 10,000
Basketball Courts CIP3 10,000 10,000 20,000
Capital Park Fund 10,000 10,000 20,000
Park Appurtenant Equipment CIP4 10,000 10,000 20,000
Capital Park Fund 10,000 10,000 20,000
Tree Planting CIP5 10,000 10,000 10,000 10,000 40,000
Capital Park Fund 10,000 10,000 10,000 10,000 40,000
Park Signs CIP6 20,000 5,000 25,000
Capital Park Fund 20,000 5,000 25,000
Picnic Shelter CIP7 25,000 25,000 50,000
Capital Park Fund 25,000 25,000 50,000
Play Structures CIP8 45,000 45,000 90,000
Capital Park Fund 45,000 45,000 90,000
Neighborhood Park Replacement CIP9 110,000 150,000 175,000 190,000 240,000 865,000
General Fund-Park Operating 110,000 150,000 175,000 190,000 240,000 865,000
Public Works (Parks) Total 110,000 275,000 285,000 200,000 250,000 1,120,000
Page 1 of 4
CITY OF PRIOR LAKE PROJECTS BY DEPARTMENT
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Project Reference 2011 2012 2013 2014 2015 Total
Public Works (Streets I Utilities)
Test Wells CIP10 55,000 55,000
Water Quality Fund 10,000 10,000
Water Fund 45,000 45,000
Meter Replacement Program CIP11 120,000 120,000 120,000 175,000 175,000 710,000
Water Fund 80,000 80,000 80,000 120,000 120,000 480,000
Sewer Fund 40,000 40,000 40,000 55,000 55,000 230,000
Well No. 10 CIP12 600,000 600,000
Water Fund 600,000 600,000
Street Reconstruction (Co. Rd.) CIP13 2,675,000 300,000 1,875,000 - 3,057,000 7,907,000
Project Levy 910,000 100,000 1,100,000 1,512,000 3,622,000
State - 200,000 200,000
County 750,000 - 500,000 1,250,000
City MSA Funds 715,000 200,000 425,000 795,000 2,135,000
Street Oversize Funds 100,000 - - 100,000
Water Quality Fund 100,000 50,000 150,000 300,000
Water Fund 100,000 100,000 100,000 300,000
Sanitary Improvement CIP14 150,000 150,000
Sewer Fund 150,000 150,000
Watermain Improvements CIP15 200,000 340,000 540,000
Water Fund 200,000 340,000 540,000
Water System CIP16 100,000 100,000
Water Storage Fund 100,000 100,000
Inflow !Infiltration Prevention CIP17 150,000 150,000 251,000 551,000
Sewer Fund 150,000 150,000 251,000 551,000
Page 2 of 4
CITY OF PRIOR LAKE PROJECTS BY DEPARTMENT
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Project Reference 2011 2012 2013 2014 2015 Total
Street Improvements (City) CIP18 1,950,000 3,080,000 1,825,000 3,720,000 - 10,575,000
Project Levy 840,000 1,180,000 900,000 2,000,000 4,920,000
SpedalAssessmenffi 560,000 1,250,000 700,000 970,000 3,480,000
Trunk Reserve Funds 50,000 50,000
Water Quality Fund 50,000 100,000 50,000 50,000 250,000
Water Fund 250,000 250,000 125,000 450,000 1,075,000
Sewer Fund 250,000 250,000 50,000 250,000 800,000
Pressure Reducing Valves CIP19 80,000 80,000
Trunk Reserve Fund 80,000 80,000
Water Storage CIP20 1,500,000 1,500,000
Water Storage Fund 1,500,000 1,500,000
Public Works (Streets I Utilities) Total 5,750,000 3,750,000 5,550,000 3,895,000 3,823,000 22,768,000
Public Works (Water Resources)
WQ System Maintenance and Retrofits CIP21 350,000 25,000 300,000 40,090 315,000 1,030,000
Water Quality Fund 350,000 25,000 300,000 40,000 315,000 1,030,000
Prior Lake Outlet Channel JPAlMOA CIP22 - 32,500 32,500 38,188 18,513 121,701
Water Quality Fund 32,500 32,500 38,188 18,513 121,701
Public Works (Water Resources) Total 350,000 57,500 332,500 78,188 333,513 1,151,701
Transit
CMAO Grant Bus Purchase (City Share) CIP23 153,000 153,000
Transit Fund 153,000 153,000
Transit Total - - 153,000 - - 153,000
GRAND TOTALS 6,210,000 4,082,500 6,520,500 4,173,188 4,406,513 25,392,701
Page 3 of 4
CITY OF PRIOR LAKE PROJECTS BY DEPARTMENT
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Project Reference 2011 2012 2013 2014 2015 Total
TOTALS BY FUNDING SOURCES
Project Levy 1,750,000 1,280,000 2,000,000 2,000,000 1,512,000 8,542,000
Special Assessments 560,000 1,250,000 700,000 970,000 - 3,480,000
State 200,000 - - 200,000
County 750,000 - 500,000 1,250,000
City MSA Funds 715,000 200,000 425,000 - 795,000 2,135,000
Capital Park Fund 125,000 110,000 10,000 10,000 255,000
Street Oversize Fund 100,000 - - 100,000
Trunk Reserve Funds 50,000 80,000 - 130,000
Water Quality Fund 510,000 157,500 432,500 128,188 483,513 1,711,701
Water Fund 1,275,000 330,000 305,000 570,600 560,000 3,040,000
Sewer Fund 440,000 440,000 240,000 305,000 306,000 1,731,000
Water Storage Fund 100,000 1,700,000 - 1,800,000
Transit Fund - 153,000 - 153,000
General Fund-Park Operating 110,000 150,000 175,000 190,000 240,000 865,000
6,210,000 4,082,500 6,520,500 4,173,188 4,406,513 25,392,701
Page 4 of 4
Page 1 of 3
CITY OF PRIOR LAKE PROJECTS BY FUNDING SOURCE
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Project Reference 2011 2012 2013 2014 2015 Total
Street Oversize Fund
Street Reconstruction (Co. Rd.) CIP13 100,000 - - - - 100,000
100,000 - - - - 100,000
Trunk Reserve Fund
Street Improvements (City) C1P18 - 50,000 - - - 50,000
Pressure Reducing Valves CIP19 - - 80,000 - - 80,000
50,000 80,000 - - 130,000
Water Quality Fund
Test Wells CIP10 10,000 - - - - 10,000
Street Reconstruction (Co. Rd.) CIP13 100,000 - 50,000 - 150,000 300,000
Street Improvements (City) CIP18 50,000 100,000 50,000 50,000 - 250,000
WQ System Maintenance & Repair CIP21 350,000 25,000 300,000 40,000 315,000 1,030,000
Prior Lake Outlet Channel Repair CIP22 - 32,500 32,500 38,188 18,513 121,701
510,000 157,500 432,500 128,188 483,513 1,711,701
Water Fund
Test Wells CIP10 45,000 - - - - 45,000
Meter Replacement Program CIP11 80,000 80,000 80,000 120,000 120,000 480,000
Well No. 10 CIP12 600,000 - - - - 600,000
Street Reconstruction (Co. Rd.) CIP13 100,000 - 100,000 - 100,000 300,000
Watermain Improvements CIP15 200,000 - - - 340,000 540,000
Street Improvements (City) CIP18 250,000 250,000 125,000 450,000 - 1,075,000
1,275,000 330,000 305,000 570,000 560,000 3,040,000
Sewer Fund
Meter Replacement Program CIP11 40,000 40,000 40,000 55,000 55,000 230,000
Sanitary Improvement CIP14 150,000 - - - - 150,000
Inflow I Infiltration Prevention CIP17 - 150,000 150,000 - 251,000 551,000
Street Improvements (City) CIP18 250,000 250,000 50,000 250,000 - 800,000
440,000 440,000 240,000 305,000 306,000 1,731,000
Page 2 of 3
CITY OF PRIOR LAKE PROJECTS BY FUNDING SOURCE
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Project Reference 2011 2012 2013 2014 2015 Total
Water Storage Fund
Fiber Optic Network Connection CIP1 - - 200,000 - - 200,000
Water System CIP16 - 100,000 - - - 100,000
Water Storage CIP20 - - 1,500,000 - - 1,500,000
100,000 1,700,000 - - 1,800,000
Transit Fund
CMAO Grant - 3 Buses (City Share) CIP23 - - 153,000 - - 153,000
153,000 - - 153,000
General Fund-Park Operating
Park Equipment Replacement CIP9 110,000 150,000 175,000 190,000 240,000 865,000
110,000 150,000 175,000 190,000 240,000 865,000
6,210,000 4,082,500 6,520,500 4,173,188 4,406,513 25,392,701
Page 3 of 3
Proiect
CITY OF PRIOR LAKE
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
All City Departments
Fiber Optic Network Connection
Public Works (Parks)
Field Backstops
Basketball Courts
Park Appurtenant Equipment
Tree Planting
Park Signs
Picnic Shelter
Play Structures
Park Equipment Replacement
CIP1
CIP2
CIP3
CIP4
CIP5
CIP6
CIP7
CIP8
CIP9
CIP
Reference
Description
Fiber Optic Network Connection between City
Hall, Maintenance Center, Water Treatment
Facility and Fire Station No.1
Backstops / Aglime:
2012 - Northwoods Meadows
2013 - Enclave at Cleary Lake
Basketball Courts:
2012 - Northwood Meadows
2013 - Enclave at Cleary Lake
Numerous park benches, grills, drinking
fountains, player benches, pcnic tables, play
equipment etc. need to be replaced or additional
equipment added each year.
Tree planting and replacement in parks and
parkways
Park Entrance Signs:
2012 - Stonebriar, Northwood Meadows and Spring Lake (2)
2013 - Enclave at Cleary Lake
Picnic Shelters:
2012 - Northwood Meadows
2013 - Enclave at Cleary Lake
Play Structures:
2012 - Northwood Meadows
2013 - Enclave at Cleary Lake
Park equipment replacement
Page 10'3
Purpose
Connect WTF and MC to fiber optic network to
increase communications abilities and reliability
PROJECT DETAIL
Cost I Benefit
Impact Statement
Will provide reliable connection from City Hall &
maintenance center to WTF for SCADA control
and information systems
Backstops keep balls in the field of play. Aglime Backstops protect spectators and park users
is the safety surface materials used on the from equipment used on fields. Aglime is a safe,
infields. maintainable material.
Basketball hard court surface areas are very
popular among neighborhood children and
adults.
These items are essential elements to each of
the parks in the community.
An annual Tree Planting and Replacement
Program is needed to replace dead trees and
enhance other areas.
The signs will be constructed of natural,
maintenance-free materials and provide park
identification.
These courts benefit both the youth and adults of
the neighborhood.
By purchasing these items for our park system in
a timely manner, the City is serving its residents
efficiently.
Trees add value to parks, neighborhoods and the
City, as well as providing benefits to wildlife and
the environment.
The park signs provide identification for residents
and visitors of Prior Lake.
Picnic shelters provide shelter from the elements These shelters provide shelter and protection
for picnics, gatherings, and summer playground from the elements.
recreation activities for children.
Each year, selected neighborhood and
community parks being developed will have
modular play structures installed providing safe
accessible activities for children.
Replace and Renovate park facilities and
equipment
Play equipment provides active play areas and
provides social activities for children.
Renovations necessary to maintain City park
system
CITY OF PRIOR LAKE
CAPITAL IMPROVEMENT PROGRAM
2011 - 2015
CIP
Reference
Proiect
Public Works (Streets I Utilities)
Test Wells
CIP10
Meter Replacement Program
CIP11
Well No. 10
CIP12
Street Reconstruction (Co. Rd.)
CIP13
Sanitary Improvement
CIP14
Watermain Improvements
CIP15
Water System
CIP16
Inflow /Infiltration Prevention
CIP17
Description
Purpose
Drill Test Wells:
Cardinal Ridge Park
Monitor stormwater and water quality for City
well field
PROJECT DETAIL
Cost I Benefit
Impact Statement
Protect City's wellhead
Water Meter Replacement Program:
SR II meters (1,441)
Invensys meters (455)
Water meters deteriorate with age, resulting in Implementation of a meter replacement program
inaccurate readings. American Water Works will show a decrease in apparent loss and in
replacement guidelines estimate a 15-year life on increase in revenue.
residential meters.
Municipal Well NO.1 0 in Wilderness Ponds Park Construct Well NO.1 0 to provide adequate
water supply in case of well failure
These are Scott County reconstruction projects.
City will participate in storm sewer and other
improvements on a cost sharing basis through a
2011 - CR21/Arcadia intersection cooperative agreement.
2012 - CR21/Fountain Hills Signal
2013 - CR44/Main1TH13 intersection
2015 - CR 21/Main Ave/Pleasant, CR 83 Payment
Sanitary Sewer improvement project
Duluth Avenue easement
Improve sanitary sewer main line which services
Commercial area, reduce infiltration issues and
improve flow
Replace CIP watermain along TH 13 from Rustic Replace old watermain
Road to Boudins Street
Well and water tower control upgrades
Improvements will allow staff to coordinate flow
to the elevated tanks and make well pump
improvements to match the water treatment
facility pressure.
Sanitary Sewer Lining
Reduce water infiltration into collection system
Page 2 of 3
Well is needed to provide City firm pumping
capacity and to utilize Water Treatment Facility
at full capacity
These County Highway Improvement Projects
will restore the driving surface and improve storm
drainage in these respective areas.
Reduction of infiltration and settlements in
sanitary sewer which could be cause for sanitary
back-ups and impede flow design of mllin line
pipe
Currently, this watermain experiences periodic
breaks
Altitude valves and well pump modifications will
allow staff greater control of the water system.
Reduction of lift station pumping and treatment
flow costs to Blue Lake from Met Council .
CITY OF PRIOR LAKE
CAPITAL IMPROVEMENT PROGRAM
2011-2015
Project
Street Improvements (City)
Pressure Reducing Valves
Water Storage
Public Works (Water Resources)
WQ System Maintenance and Retrofit
Prior Lake Outlet Channel JPAlMOA
Transit
CMAO Grant Bus Purchase
CIP
Reference
CIP18
CIP19
CIP20
CIP21
CIP22
CIP23
Description
2011 - Boudins,Timothy,Denise,Lois,Natalie
2012 - Industrial Park,
RutgersfWatersedge/Grayling
2013 - Martindale/Carriage Hills Resurfacing,
Mushtown/Maple/Panama
2014 - Franklin Trail Resurfacing, Eau
Claire/Highland/Marsh/Skyline
Pressure Reducing Valves:
2013 - Carriage Hills
Water Storage:
500,000 gallons ground storage
Maintaining existing structural stormwater
practices and adding new treatment. (locations
vary)
Prior Lake Outlet Channel maintenance /
improvements
Purpose
To resurface streets to extend usuable life or
reconstruct streets to a 7 -ton or 9-ton standard.
Reduce pressure in lower service areas of the
Prior Lake community.
Increase water storage on west side of lake.
Maintenance, retrofit and creation of storm water
ponds to restore and enhance overall system
treatment efficiency. Maintenance, retrofit and
creation of other structural practices such as;
sump manholes, bioretention, infiltration and
filtration.
To provide maintenance repairs and upgrades
for the Prior Lake Outlet Channel. This project is
a cooperative effort between the SMSC,
PLSLWD, Prior Lake andShakopee.
Purchase of 3 additional coach buses for transit Expansion of BlueXpress service to provide
purposes. more frequent runs and more routes.
Page 3 of 3
PROJECT DETAIL
Cost I Benefit
Impact Statement
Improved streets will reduce maintenance for the
streets and for vehicles.
Reducing pressure in the distribution system will
assist in water conservation and water loss.
Increase water storage to provide adequate
supply for high usage periods, fire protection and
system pressure. Provides better water quality
by increasing ability to circulate system.
Using a targeted maintenance and retrofit
program to continually renew and improve the
overall water quality system effectivness and
cost efficiency.
Outlet channel repairs will prevent erosion and
restore channel capacity.
Additional transit capacity will help reduce
congestion on regional roads and will help to
improve air quality.
City of Prior Lake
2011-2020 Transportation Plan
! Year !
Improvement
MSA
Street
Oversizina
Tax
Lew
Bond Assessments
Tvoe
Utility
Fund
Water
Qualitv
Trunk
Fund
County/
State/Other
Total City
Cost
2011 BoudinslTimothy/Denise/Lois/Natalie $ $ - $ 840,000 429 $ 560,000 $ 500,000 $ 50,000 $ $ $ 1,950,000
2011 CR 21/Arcadia Intersection 715,000 100.000 910.000 Recon - 100.000 100.000 - 750.000 2.675.000
1IIIIIIr~1l![ m!lmt:~_~ !~I]r~ dllaml
2012 Industrial Park (Rural Street Restoration)
2012 RutgerslWatersedge/Grayling
2012 CR21/Fountain Hills SiQnal
$
$
$
200,000
980,000
429
429
$
600,000 $
650,000
$
50,000 $
50,000
50,000 $
$
900,000
2,180,000
300,000
500,000
200.000
2013 Main Ave/TH 13/Ridgemont $ 425,000 $ $ 1,100,000 Recon $ $ 100,000 $ 50,000 $ $ 200,000 $ 1,875,000
2013 Martindale/Carriage Hills Resurfacing - - 300,000 Recon - 50,000 - - - 350,000
2013 Mushtown/Maple/Panama - 600.000 429 700,000 125.000 50.000 1.475.000
r ........... ~ 1!!lr~_,_, "Illll&l......~-i1 I!Ullllllil.DI_I_iE_ ~!. tJIl~ +,.~___
2014 Franklin Trail Resurfacing
44 to Summer) $
$
$
300,000 Recon $
$
100,000 $
600,000
$
$
$
400,000
50,000
2015 CR 21/Main Ave/Pleasant $ 795,000 $ - $ 1,455,000 Recon $ - $ 100,000 $ 150,000 $ - $ 500,000 $ 3,000,000
2015 CR 83 CooP AQreement Pa~ment - 57,000 Recon 57.000
lIlY lIIIiI!laRlIIIifl&illm'*'l" .......,""";""~- ~ll_IT!IiI I"". ~~. fa :Jjj -"!WI_I. .~l u;- ~'-- '..1IIlI ~
2016 City Street Reconstruction $ $ - $ 1,300,000 429 $ 740,000 $ 550,000 $ 55,000 $ - $ $ 2,645,000
2016 CR 12 Phase IV 300,000 - 350,000 429 360,000 500,000 30,000 - - 1,540,000
2016 TH 13/150th Street 500,000 150.000 1.000.000 Recon 150,000 55.000 1.855,000
_~,~""",~!llli liIIIIIIIIIlI"" l~ ~UlIlBI;__:! .- ~~JIID"I~~~ -.. 1-. ~...
2017 CR 42/TH 13
$
200,000 $
$
1,000,000 Recon $
1.000.000 429
$
100,000 $
350.000
55,000 $
55.000
$
$
1,355,000
600.000
2018 City Street Reconstruction $ $ - $ 1,000,000 429 $ 500,000 $ 350,000 $ 55,000 $ - $ - $ 1,905,000
2018 City Street Reconstruction - 750,000 729 500.000 350.000 55.000 1.655.000
I~-'-...Iliiii.. A -':,~,,~ ~ J-1 ~"~"__I~IIII1I1""!I-II.~~~"'-' "'-IIiJ! 1111 .. l!lJllt_
2019 City Street Reconstruction
2019 Resurfa~inQ ProQram (50% State Aid SO
$
$ - $ 1,200,000 429 $ 680,000 $ 400,000 $ 55,000 $ - $ $ 2,335,000
400.000 400.000 Recon - 100.000 - - - 900.000
ro'l1llltD:lli, "II Ilh..O.'~JIliDlr'_\l~~,~~_!JJ~J U.j.II):~llr :~
1$
$
2,100.000 429 $ 840.000 $ 900.000 $ 120.000 $ - $ - $ 3.960.000
:jr)_.:B~ .......~__ rtllw.pi I i~ -. r .....
Street Reconstruction
1$
III
1$
3,535,000 $ 250,000 $ 18,642,000
$ 7,700,000 $ 5,925,000 $ 1,085,000 $
50,000 $ 1,450,000 $ 38,637,000
CITY OF PRIOR LAKE
2011 - 2022 EQUIPMENT REPLACEMENT PLAN
2011 - 2022
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Totals
Use of Funds:
Fire Dept Total 90,000 44,885 28,646 - - 35,940 73,617 1,000,000 36,681 - 550,000 - 1,859,768
Police DeptTotal 73,500 75,000 76,500 78,000 109,500 106,000 82,500 84,000 103,500 87,000 88,500 90,000 1,054,000
Public Works Dept Total 530.256 277.321 168.723 434,044 686,901 571.294 710.943 624.104 151.119 565,540 370.421 238,387 5,329,055
Total Use of Funds 693,756 397,206 273,869 512,044 796,401 713,234 867,060 1,708,104 291,300 652,540 1,008,921 328,387 8,242,822
Source of Funds:
Interest Earnings (2%) 26,348 20,400 20,464 23,396 22,223 16,139 12,197 5,500 2,048 7,263 5,557 7,890 169,423
Annual Equipment Levy 270,000 280,000 290,000 320,000 350,000 380,000 390,000 400,000 410,000 420,000 430,000 440,000 4,380,000
Enterprise Fund Contribution 100,000 100,000 110,000 110,000 120,000 120,000 130,000 130,000 140,000 140,000 140,000 140,000 1,480,000
Bond Proceeds - Referendum - - - - - - - 1,000.000 - - 550,000 - 1,550,000
Total Source of Funds 396,348 400,400 420,464 453,396 492,223 516,139 532,197 1,535,500 552,048 567,263 1,125,557 587,890 7,579,423
Change in Fund Balance (297,408) 3,194 146,595 (58,648) (304,179) (197,095) (334,863) (172,604) 260,748 (85,277) 116,636 259,503 (663,399)
Beginning Fund Balance 1,317,398 1,019,990 1,023,184 1,169,778 1 ,111 ,130 806,951 609,857 274,994 102,390 363,137 277,860 394,496
Ending Fund Balance 1,019,990 1,023,184 1,169,778 1,111,130 806,951 609,857 274,994 102,390 363,137 277,860 394,496 653,999
Page 10f7
$1.000,000
$900,000
$800,000
$700,000 -
$600,000
$500,000 -
$400,000
$300,000
$200,000
$100,000 -
Equipment Replacement Plan
$0
2011
_20J2
20J3_2_0~2_Q~5_2_0.16_2_0~2_0.18_20_19_2020 2021
. Firn O'ptT ola' . P,bli' Wo~, O'pl To'" · por;oo O'ptTo'" l
2022
Page 2 of 7
FIRE DEPARTMENT
2011 - 2022 EQUIPMENT INVENTORY
Life Current
Equipment Description EouiD # YEAR SERIAL # COST Mil E1HR Exot. Value 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Zodiak Rescue Boat 9290 1991 XDC2453F $ 16,000 15 $ 36,700 $ 90,000 $ $ $ $ $ $ $ $ $ $ $
-Peterbilt Pumper 9220 1993 1XPBHA8X1PD332698 244,000 51,107 25 320,000 550,000
-Peterbilt Rescue 9215 1993 1XPBH78XXPD332699 218,000 41,470 25 300,000 450,000
-Peterbilt Pumper 9221 1996 1XPGHA8X7TN412503 204,085 25,374 25 320,000 550,000
Scotty Trailer-Smoke House N/A 1997 1 SSTT1PT2V11SS246 24,780 20 30,900 38,003
Ford F-350 Crew Cab 9270 2000 1 FTSW31 S3YEE27499 41,076 18,603 12 42,308 44,885
Polaris 500 6x6/ATV 9275 2000 4XALL50A2YD418369 8,000 48 15 25,000
Peterbilt Tanker 9260 2001 2NPNHZ8XX1 M498712 145,000 7,526 25 156,817
Ford F-350 9271 2001 1 FTSX31 S71 ED79752 25,452 33,662 12 26,215 28,646
Ford Expedition 9200 2003 1 FMPU16L83LB71121 25,390 102,842 12 26,151
Ford F-150 Super Cab 9201 2004 1 FTPW14544KD62092 29,223 59,331 12 30,099 35,940
Ford F-350 Super Cab 9202 2005 1 FTPW14595KE56227 28,957 44,767 12 28,957 35,613
Peterbuilt Pumper 9222 2007 2NPLHZ8X37M682390 319,890 13,255 25 319,890
Ford F-350 Super Cab 9272 2007 1 FTWX31Y28EB35023 23,074 10,981 12 28,113 36,681
E-One 100' Aerial 9280 2007 925,500 5,556 25 925,500
Peterbilt Heavy Rescue 9216 2009 2NPRHN8XXAM794324 424,366 3,125 25 424,366
NEW EQUIPMENT:
Rescue Truck (Station #2)
Totals $ 90,000 $ 44,885 $ 28,646 $ $ $ 35,940 $ 73,617 $ 1,000,000 $ 36,681 $ $ 550,000 $
*** Referendum Total 2011 - 2022 $ 1,859,768
9220 ; $550,000 (2018)
9215; $450,000 (2018)
9221 ; $550,000 (2021)
Research refurbishing options
in 2010
Page 3 of7
POLICE DEPARTMENT
2011-2022 EQUIPMENT INVENTORY
Equipment Description Equip # YEAR SERIAL # COST Mileaqe 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Ford Crown Victoria 209 2009 2FAHP71V79X131710 24,058 25,000
Ford Crown Victoria 309 2009 2FAHP71V09X131709 18,578
Ford Crown Victoria (M-Squad) 408 2008 2FAHP71V28X161342 76,935 24,500
Ford Crown Victoria (M-Squad) 607 2007 2FAHP71W77X156290 76,422
Ford Crown Victoria (M-Squad)' 706 2006 2FAHP71WX6S145993 92,197
Ford Crown Victoria (M-Squad) 708 2008 2FAHP71V08X161341 49,835 25,000
Ford Crown Victoria (M-Squad) 806 2006 2FAHP71W86X145992 71,282 24,500
Dodge Charger (M-Squad) 808 2008 2BAKA43H98H271257 25,650 25,000
Dodge Charger (M-Squad) 906 2006 2B3LA43H26H406967 80,011
Ford Crown Victoria (M-Squad) 1005 2005 2FAHP71W35X176453 46,240 24,500
, New engine in 2007
TOTAL SQUAD CARS $ 73,500 $ 75,000 $ 76,500 $ 78,000 $ 79,500 $ 81,000 $ 82,500 $ 84,000 $ 85,500 $ 87,000 $ 88,500 $ 90,000
Dodge Sprinter (TCTT) 1108 2008 WDOPF445285312689 $48,000 1,964 $ - $ $ $ $ $ $ $ $ $ $ $
GMC Denali 1202 2002 1 GKEK63U 12J280904 88,764
Ford Ranger 1292 1992 1 FTCR1 OU5NUA67382 51,475
Nissan Murano 1407 2007 JN8AZ08W07W652082 16,796 - 30,000
Dodge Magnum (DARE) 2106 2006 2086V47V86H438151 7,496 25,000
Harley Davidson Motorcycle 2009 $16,000 0 - - 18,000
Speed Sign Trailer 1293 2000 Speed Sign Trailer
PD Generator (Cummins-D) 9911 2006 D040627729
TOTAL MISC VEHICLES ( FORFEITURE & OTHER FUNDING)' $ - $ - $ - $ - $ 30,000 $ 25,000 $ - $ - $ 18,000 $ - $ - $
Totals $ 73,500 $ 75,000 $ 76,500 $ 78,000 $109,500 $106,000 $ 82,500 $ 84,000 $103,500 $ 87,000 $ 88,500 $ 90,000
Total 2011 - 2022 $ 1,054,000
, Donations or contributions may defray or pay for replacements in this category.
Page 4 of 7
PUBLIC WORKS DEPARTMENT
2011 . 2022 EQUIPMENT INVENTORY
2010 Life Current
Equipment Description Eaulp # YEAR SERiAL # Mileaae/Hrs ExDl. Value 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
DUMP TRUCKS Miles
Ste~ing Dump (P,W,S) L8511 466 2000 2FZHDJBB5YAB04744 67,643 15 200,000 225,102
Ste~ing Dump (P,W,S) L8511 467 2000 2FZHDJBB7YAB04745 65,170 15 200,000 231,855
Ste~ing Dump (P,W,S) L8511 468 2001 2FZAAWAKX1AF83306 58,704 15 200,000 245,975
Ste~ing Dump (P,W,S) L8511 469 2001 2FZAAWAK11AF83307 57,437 15 200,000 238,810
Ste~ing Dump (P,W,S) L8511 518 2002 2FZAAWAK92AK06805 65,678 15 200,000 245,975
International Dump (P,W,S)(tandem) 465 2003 IHTWXAXT14J083646 61,236 15 207,400 278,728
Ste~ing Dump (P.w.S)(tandem) 519 2008 2FZHAZDE49AAE8498 13,368 15 207,400
PICK UPSNAN
Chev. C1500 (112T) 540 1996 1 GCEC14M7TE246454 80,839 12 25,000 26,523 35,644
F350 Ford 4x4 (H) w/Plow' 457 1999 1 FTSF31 F6XED33327 101,093 12 57,000 66,079
F350 Ford 4x4 (H) Utility (crane) 756 1999 1 FDWF37F9XED33326 119,320 10 79,000 81,370 106,169
F350 Ford 4x4 (H)w/plow 543 1999 1FTSF31 FXXEC10484 93,548 12 34,500 38,830
F350 Ford 4x4 (H)w/plow 544 1999 1 FTSF31 F3XEC26476 118,084 12 34,500 36,601
F350 Ford 4x4 (H)w/dump 545 1999 1 FDWF37F4XEE98166 72,653 12 59,000 66,405
F350 Ford 4x4 (H)w/dump/plow' 546 1999 1 FDWF37F9XEE98163 75,391 12 59,000 70,449
F350 Ford 4x4 (H) Utility 750 2000 1 FDWF37S5YEE27427 94,900 10 76,700 106,171
3500 Dodge 4x4 w/dump/plow' 547 2001 BB6MF36W81 M575169 64,350 12 59,000 68,397
F350 Ford 4x4 w/plow' 451 2001 1 FTSF31S51 ED79753 85,795 10 59,800 61,594 82,777
F-550 Bucket truck 549 2002 1 FDAF56F22ED28193 26,013 20 91,200 130,029
F-350 Ford (H) w/piow 548 2003 1 FTSF31 F83EA38823 77,506 12 34,500 45,015
Chev 4x4 1/2 T 758 2004 1 GCEK19T94Z315464 66,152 10 25,000 28,982
F-550 w/plow 452 2005 1 FDAF57975ED-26435 36,090 12 57,000 70,103
Ford Ranger 508 2005 1 FTZR45E55-PA97395 47,468 10 18,500 21,447
Chev 4x4 1/2 T 541 2006 1 GCEK19Z16Z265893 32,965 10 25,000 31,669
F550 Ford 4x4 w/plow 459 2008 1 FDAF57R18EE 18372 13,233 12 57,000 76,603
F3504x4 (club cab)w/plow 453 2009 1 FTWW31 R69EA63787 9,056 12 42,400 58,692
F350 4x4 (4 door) 494 2009 1 FTWX31 R39EA63789 8,930 12 33,200 45,957
F350 4x4 utility w/plow 762 2009 1 FTWF31 R89EA63788 5,216 10 59,800 78,025
, Replaced with F550 w/plow
2 New engine _ body refurbished
, New engine - body refurbished
'Replaced w/utility box
UTILITY EQUIPMENT
Serco Extend-A-Jet 770 1990 EMSP-6.91101 455 20 57,900 63,269
Ford L8000 Tanker 521 1991 1 FDYK82A3MV A35699 45,950 15 144,400 172,421
Jet-Vac 784 2002 2FZHA T AK62AK46319 49,027 20 260,000
Portable 10" pump DNR 27977-078 30 21,300
Valve Exerciser 763 2007 21984 20 56,775
JLG Electric Lift 551 2007 200152825 20 15,000
EMERGENCY POWER
Cat D80-6 Towable 742 2007 D4B00613 72 15 39,000 55,605
Cat 80KW Towable 747 2006 D4P00357 358 15 39,000 53,985
Cat 200KW Towable (Booster station) 777 1996 085Z13104 130 20 94,000
Cat 80KW Towable 776 1996 2021765 3,706 15 39,000 40,170
Cat 75KW Estate 778 2002 NPF01467 220 30 94,000
Cal40KW Lime 749 2004 E4724B1/001 105 30 27,000
Cat 40KW Franklin T~ 748 2004 F5283A 1/001 100 30 27,000
Cal300KW (Wells 8 & 9) 746 2006 KPS01979 0 30 72,400
Cat 100KW Main!. Ctr 745 2006 N4E00311 16 30 36,000
Waler Treatment Facility 744 2009 SXC02940 0 30 325,000
Onan 100EN FS #1 9211 1996 G940549015 346 30 35,000
FS #2 Cal Gen 9212 2008 N6D00424 17 30 35,000
PD Gen 9911 2007 46385148 639 60 35,000
City Hall Gen 9913 2008 N3C00696 70 30 28,000
Pag& 5 0'7
PUBLIC WORKS DEPARTMENT
2011 - 2022 EQUIPMENT INVENTORY
2010 Life Current
Equipment Description Equip # YEAR SERIAL # Mileage/Hrs Expt. Value 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
TRAILERS
Homemade Trailer 530 1986 DPSMN960962 12 7,219 9,145
Homemade Trailer 480 1988 12 7,300
Towmaster Trailer 479 1999 4KNUT2020XL 161258 12 10,500 10,815
JAA 22' Trailer 533 2000 00082264ROB 12 7,300 7,745
Towmasler Tandem Trailer 482 2004 4KNFZ19244L 163143 12 7,900 9,433
Feathe~ile Trailer 761 2006 4U01ST9256A028847 12 5,980 7,575
Haulin Trailer 554 2006 5NHVHA0156W045768 12 4,000 5,067
Towmasler Trailer 531 2008 4KNUC18218L 162564 12 7,000 9,407
Towmaster Trailer 532 2007 4KNUC18288L 162562 12 7,000 9,407
LOADERS/SKID STEERS
JCB Traclor Backhoes 785 1995 SLPZ14TCSE0436049 4,084 13 115,000 118,450
Melroe Bobcat S 185 w/broom 781 2004 525015713 2,717 6 55,000 58,350 69,672
Melroe Bobcat S250 w/blower 501 2006 530912105 2,686 6 60,000 60,000 73,792
Case Loader 721 E w/plow & wing 488 2007 N7F200557 1,049 14 127,403
Cal Loader 938G w/plow & wing 789 2001 00938GJGW502904 4,140 14 156,000 170,465
Cat 257B 502 2008 CAT0257BVSCK07556 1,127 6 35,315 39,747 47,460
S Will be replaced w/used backhoe
~ Hammer Hoe (new)
~ Plate compactor (new)
STREETS/SIDEWALKS
Tymco Sweeper" 471 2007 1 HTMPAFN07H433838 14,143 15 158,500
Elgin Sweeper 472 2003 S9112D 3,082 14 147,000 180,791
Holder Sidewalk Plow 506 2009 4DB070947 251 14 80,000 101,342
40" Bituminous Mill 664 2000 231611255 12 25,000 26,523
Erskine Fronl Blower 665 2002 207600168 10 9,400 9,972 11,908
Direclional Safety Sign 664 2003 1A9A5465522228069 20 28,800
Pavement router 454 2003 3112109081 500 20 25,800
Crack Seal Equip 473 2003 03-110-119 426 20 7,000
Stone AP41 00 Roller 474 2009 72009191 15 23,400
Message Board for Utility Truck 128006 20 10,000
Box Broom 664 1996 714400101 15 6,200 6,386
S Research resloration ~ptions
ANTI-ICING EQUIPMENT
Brine Production 2004 SB600 6 9,800
Critical Spol Sprayer 492 2004 15 6,320 8,246
Single Axle Slide-In 493 2007 15 12,000 17,109
Storage Tanks 2007 10 22,000 27,057
Slide-in Sander 455 2003 13839 10 11,900 13,003
Slide-in Sander 490 2006 123148 10 11,900 14,209
Liquid Anli-Ice Unil 495 2009 10 17,200 22,442
TURF CARE
JR Turf Truckster Striper 535 1998 98002740 1,646 20 18,000 22,802
Cushman Field Groom w/atch 537 2003 LM21013 1,467 10 18,900 21,272
Cushman Truckster 538 2005 2300977 1,513 10 18,000 20,667
Kubota 539 2007 KRTV110071011057 581 10 20,000 24,597
T oro 580D 504 2001 210000239 4,967 10 77,200 79,516
72" 328D Toro Diesel w/blower 523 2003 230000114 2,348 8 32,500 34,479 42,405
Case CX100 Traclor 507 2000 C100AS4JJE1014819 3,193 11 48,000 52,451
Seed-A-Valor 665 2000 4 8 10,600 12,657
Aerator AE80 665 1998 445 10 9,700 9,991
Goosen Rake-N-Vac 665 1992 RVT#I-12000 15 17,500 19,696
Sovema Tiller 665 1993 15 7,200
MilIcreek Top Dresser 665 1995 21934 10 7,100 7,991
Dilch Mower 665 2006 RBF-1295 15 16,500 22,840
T oro 5700D Sprayer 536 2004 24000016 1,182 10 25,500 32,303
Jacobson HR 9016 503 2008 705291855 810 10 68,400 66,647
Jacobson Turf Cat 524 2008 628-DT 870 8 27,900 33,314
Toro 325D 525 2009 290000139 503 8 27,900 34,313
Taro 325D 526 2009 280000303 435 8 27,900 34,313
John Deere 5525 Tractor 505 2009 L V5525H456371 631 11 28,100 37,764
Page 6 of7
PUBLIC WORKS DEPARTMENT
2011 - 2022 EQUIPMENT INVENTORY
2010 Life Current
Equipment Description EauiD # YEAR SERIAL # Mileaae/Hrs EXDt. Value 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
TREE CARE
Vermeer 1250A Chipper 510 1999 1VRN1416XW1007408 1,820 13 28,400 30,130
Rayco Stump Grinder 550 2007 1R91209127M210026 75 15 17,000
Tree Spade 509 2008 NOVAK 20 39,700
Aerovator Seeder 512 2008 29 15 6,500
BUILDING DEPARTMENT
Ford Crown Victoria7 205 2005 2FAHP71W95X166042 69,676 15 12,000
Ford Focus 398 2009 1 F AHP34N09W259206 5,964 10 15,000
ENGINEERING DEPARTMENT
Suburban' 399 1999 1 GNFK16R6XJ351846 46,036 15 38,000 25,000
Ford Crown Victoria" 405 2005 2FAHP71W75X166041 96,077 10 12,000
REFURBISHING 10,000 15,000 15,000 15,000 20,000 20,000 20,000
FUTURE ADDITIONS
Used 112 Ton Pick Up (Parks) 10 20,000
Stainless slide-in sander 10 11,900 13,795
Hot patch unit (cost share w/SMSC)
trade in exlsling unit 10 26,000 26,780
Slide in anti-deice liquid slide in (1850 gal) 10 12,800 13,184
Totals $ 530,256 $ 277,321 $168,723 $ 434,044 $ 686,901 $ 571,294 $ 710.943 $ 624,104 $ 151,119 $ 565,540 $ 370,421 $ 238,387
7 Will be replaced wilh used economy car
, Will be replaced with a 1/2 Ion pickup Total 2011 - 2022 $ 5,329,055
" Will be replaced with used economy car
Page 70t7
CITY OF PRIOR LAKE
2011 - 2036 PARK EQUIPMENT REPLACEMENT PLAN
2011
2012
2013
2014
2015
2016
General Fund - Parks Department
Use of Funds:
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2011 - 2036
TOTAL
Parks DeptTotal(l) $ 101,709 $ 148,653 $ 169,331 $ 182,536 $ 238,171 $ 223,318 $ 337,954 $ 256,466 $ 439,475 $ 1,444,108 $ 370,004 $ 1,021,454 $ 602,736 $1,067,726 $ 1,144,646 $ 453,392 $ 378,853 $ 606,199 $ 560,538 $ 1,898,928 $ 539,301 $ 473,803 $ 749,365 $ 677,628 $ 369,746 $ 836,518 $ 15,292,559
Sources of Funds:
Tax Levyl') 110,000
Referendum or Privale Fundingl')
Revolving Park Equip Fund Contribution
Total Source of Funds 110,000
175,000
190,000
240,000
150,000
250,000
150,000
175,000
190,000
240,000
250,000
Change in Fund Balance $ 8,291 $ 1,347 $ 5,669 $ 7,464 $ 1,829 $ 26,682 $
Revolving Park Equipment Fund
Use of Funds:
Transfer to General Fund $
Tolal Use of Funds
$
$
$
$
$
$ 182,954 $ 91,466 $ 264.475 $
182,954 91,466 264,475
199,108 $ 175,004 $ 116.454 $ 147,736 $ (107,f74) $
199,108 175,004 116,454 147,736 (107,274)
Sources of Funds:
Interesl Earnings (2%)
General Fund Contribution
Tax Levy
Total Source of Funds
7,348
50,000
4,040
50,000
5,121
50,000
6,223
50,000
8,495
50,000
9,665
50,000
54,040
55,121
56,223
57,348
58,495
59,665
Change In Fund Balance $ 54,040 $ 55,121 $ 56,223 $ 57.348 $ 58,495 $ 59,665 $ (72,097) $ 22,950 $1144,600) $ (77.125) $ (49,564) $ 12,996 $ (13,027) $ 246.722 $ (130,264) $ (56,615) $ 31.793 $ 50,082 $ (118,255) $ (29,010) $ (69,964) $ 9.135 $(251,244) $(169,532) $ 149,960 $ (298,813) $
155,000
182.~54
337,954
100,000
110,858
10,858
165,000
91.466
256,466
$
105.000
114,416
9,416
175,000
264.475
439,475
$
110,900
119,875
185,000
1,060,000
199.108
1,444,108
$
9,875
6,983
195,000
175.004
370,004
$
120.000
125,440
205,000
700,000
116.454
1,021,454
$
5,440
125.000
129,449
215,000
240,000
147,736
602,736
$
4,449
130.000
134,709
225,000
950,000
(107,P41
1,067,726
$
4,709
4,448
115.000
121,983
13~,000
139,448
Beginning Fund Balance $ 202,000 $ 256,040 $ 311,161 $ 367,384 $ 424,732 $ 483,226 $ 542,891 $ 470,794 $ 493,744 $ 349,144 $ 272,019 $ 222,455 $ 235,451 $ 222,424 $
Ending Fund Balance $ 256,040 $ 311,161 $ 367,384 $ 424,732 $ 483,226 $ 542,891 $ 470,794 $ 493,744 $ 349,144 $ 272,019 $ 222,455 $ 235,451 $ 222,424 $ 469,146 $
Interest Rate
Total Funding from Tax Levies:
General Fund - Operating Budget
General Fund - Contribution 10 RPEF
Park Equipment Revolving Fund
Debt Levy - Referendum
$ 110,000 $ 150,000 $ 175,000 $ 190,000 $ 240,000 $ 250,000 $ 155,000 $ 165,000 $ 175,000 $
$ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ $ $ $
100,000 105,000 110,000
185,000 $ 195,000 $ 205,000
$ . .$
115,000 120,000 125,000
1.060.000 700,000
$ 1,360,000 $ 315,000 $ 1,030,000
Total $ 160,000 $ 200,000 $ 225,000 $ 240,000 $ 290,000 $ 300.000 $ 255,000 $ 270,000 $ 285.000
$ 215,000
$
130,000
240.000
$ 585,000
$ 225,000 $
$ $
135,000
950,000
$ 1,310,000 $
235,000
630,000
279,646
1,144,646
$
245,000
208,392
453,392
$
255,000
123.853
378,853
$
265,000
230,000
111.199
606,199
$
275,000
285,538
560,538
$
279,646 $ 208,392 $ 123,853 $ 111,199 $ 285,538 $
279,646 208,392 123,853 111,199 285,538
.9,363
140,()QO
149,383
145,000
151,778
6,778
150,000
155,645
5,645
6,281
160,000
167,283
7,283
469,'146 $ 338,882 $ 282,268 $ 314,060 $ 364,143 $
338,882 $ 282,268 $ 314,060 $ 364,143 $ 245,887 $
155,000
161,281
235,000 $ 245,000 $ 255,000 $ 265,000 $ 275,000 $
$ $ $ $ $
140,000 145,000 150,000 155,000 160,000
630,pOO 230.()QO
1,005,000 $ 3~0,000 $ 405,000 $ 650,000 $
(1) Includes costs for communily parks as noted in "Community Park Referendum Needs."
(2) Includes planned incremental increases per council discussion but at a lower amount due to lower projected needs.
(3) Consider referendum or privale funding for these improvemenls.
2011
2012
2013
2014
2015
2016
LAKEFRONT
. Play Structure
- Hockey Rinks
- Parking / Roadway
MEMORIAL
- Parking
. - Pla~ Structure
THE PONDS
- Play Structure
- Parking / Roadway
SAND PT. BEACH
- Concession
. - Parking / Roadwa~
THOMAS RYAN MEMORIAL
- Ballfield Renovation
- Play Structure
- Parking
WATZL'S BEACH
- Concession
$
$
$
$
$
$
Total Annual Costs $
$
$
$
$
$
$
2017
$
$
2018
$
$
$
$
2019
2020
$ $
545,000
515,000
$ 1,060.000 $
COMMUNITY PARK REFERENDUM NEEDS
2021
2022
2023
2024
2025
$ $ $ $ $
375,000
700,000
240,000
85,000
720,000
145,000
255.000
$ 700,000 $ 240,000 $ 950,000 $ 630,000 $
2026
2027
$
$
2028
$ $
230,000
$ 230cOOO $
285,000
1,415,000
198.928
1,898,928
$
295,000
244.301
539,301
$
305,000
168.803
473,803
$
315,000
434..365
749,365
$
325,000
352.628
677,628
$
335,000
34.746
369,746
$
345,000
491,518
836,518
$
198,928 $ 244,301 $ 168,803 $ 434.365 $ 352,628 $ 34.746 $ 491,,518 $
198,928 244,301 168,803 434,365 352,628 34,746 491,518
165.000
169,918
4,918
170.000
174,338
4,338
175.000
177,938
2,936
180,000
183,121
3,121
185,000
183,096
(1,904)
(5,295)
195,000
192,705
245,887 $ 216,878 $ 146,914 $ 156,049 $ (95,195) $(264,727) $ (114,767)
216,878 $ 146,914 $ 156,049 $ (95,195) $(264,727) $(114,767) $ (413,580)
190,pOO
164,705
285,000 $ 295,000 $ 305,000 $ 315,000 $ 325,000 $ 335,000 $
$ $ $ $ $ $
170,000 175,000 180,000 185,000 190,000
165,000
1.~15.oo0
435,000 $ 1,865pOO $ 465,000 $ 480,000 $ 495,000 $ 510,000 $ 525,000 $
2029
2030
$ $
875,000
540,000
$ 1,415,000 $
2031
2032
$
$
2033
$
$
2034
$
$
2035
$
345,000 $
195,000
540,000 $
(2,295)
6,115,000
5,225,000
4,003,!I40
15,343,840
$
51,282
4,003,!I4O
4,003,840
138,260
300,000
2,950,000 ,
3,388,260
1615,580).
6,115,000
300,000
2,950,000
5,225.!,00 .
14,590,000
2036
$
$
TOTAL
$
375,000
875,000
85,000
255.000
240,000
720,000
545,000
145,000
515,000
230,000
540,000
700,000
$
5,225,000
DEBT ANALYSIS
In reviewing the 2011-2015 Capital Improvement Program, the City Council has considered the annual
tax impact of the scheduled projects. While state levy limits have been imposed through year 2011, a
special exception exists for debt levies associated with capital improvement program financing.
Major projects scheduled for 2011 which involve a property tax levy (payable 2012) are listed below:
I Pro.iect Description
Boudins Area Street Reconstruction (Phase 1)
CR21/Arcadia Intersection - ROW & Construction
I Total
Pro.iect Levy I
$ 840,000
910,000
$1,750,000 I
The 2011-2015 CIP includes projects that are funded by bond proceeds. Bonds are issued for the project
costs that the City is funding through tax levies as well as the costs that are specially assessed to property
owners, The CIP anticipates $12,022,000 in bonding for projects in the Transportation Plan for 2011-
2015 and $1,500,000 for a 500,000 gallon water storage unit in 2013. The following chart reflects all
bonding requirements referenced in the CIP and Transportation Plan. It does NOT include the bonding
that may be presented to residents by referendum for major fire equipment purchases (identified in the
Equipment Replacement Plan) and community park improvements (identified in the Park Equipment
Replacement Plan) beginning in 2018.
As of 12/31/2009, the City of Prior Lake had $37,520,000 in debt. The following chart reflects the type
of debt that comprises the $37M:
I Debt Type
G.O. Special Assessment
Bonds
G,O, Tax Increment
G.O, Bonds (MY)
Amount Purpose
$ 7,265,000 Street Improvement Projects
G.O, Bonds
Revenue Bonds
G.O. Revenue Bonds
325,000 Tax Increment Project (EDA)
9,170,000 Referendum Projects (Park & Fire
Stations)
1,165,000 I Street Reconstruction Project
9,465,000 I City Hall & Police Station (EDA)
9,100,000 Maintenance Facility & Water
Treatment Facility
1,030,000 Scott County Cooperative Agreement
G.O. Capital Improvement
Bonds
I Total
$ 37,520,000 I
In May, 2010, the City issued $1,235,000 in General Obligation Special Assessment Bonds.
Page 1 of 3
The following chart reflects the cumulative effect of new debt issued and the retirement of existing debt.
The top line is the resulting debt balance at the end of the year.
Projected Debt Balances
06.21.2010
$40,0
$35,0
-~.
----oiL\, '" , .
----,
~l""
,.........
-,,,.
.~
$5.0
$30.0
$25.0
,-.,
CJ)
c
~ $20.0
E
c
v$15.0
$10.0
$0.0
~\'J ~'\ '" '\')" '" '\'"
'),,\'J '),,\'J '),," '),,"
~~ ",,\':>
'),,\'J '),,"
~fo
'),,\'J
~'\
'),,\'J
\'J,\'t:> \'J'\C)
'V 'V
\'J
'),,\'J'V
~ Existing Oebt~New CIP Oebt......Projected OebG
The impact ofthe 2011-2015 crp and other anticipated bond payment adjustments on the debt service
propeliy tax levy are reflected in the following table:
Projected Chanee in Debt Levy Totals
2011 2012 2013 2014 2015 2011 - 2015
Deht:
Existing CIP (60,589) (52,438) (58,638) (I 09,837) (l58,037) (439,539)
New C[P 109,000 210,000 154,000 240,000 240,000 953,000
EDA Lease Revenue [5,000 15,000 15,000 15,000 15,000 75,000
Market Referendum 20,463 27,162 34,325 ( 160,057) 41,363 (36,744)
Change in Debt Levy 83,874 199,724 144,687 (14,894) 138,326 551,717 I
Each year, cel1ain bond issues mature and the corresponding debt service payments are eliminated. In the
early 2000s, the level of bonding was lower due to the capital improvement projects being much smaller
in scope. Current projects are larger due to the fact that we have accelerated the street reconstruction plan
in order to address maintenance issues in a more reasonable time frame. Therefore, the amount of debt
service dropping off each year is less than the amount that we are adding for new elP projects, This
results in an increase in the debt service property tax levy.
Page 2 of 3
The table also reflects the debt associated with the EDA Lease Revenue bond which funded the
construction of city hall and the police station incrementally increases each year. The debt associated
with Market Referendum bonds which funded park improvements and construction of the ftre stations
also incrementally increases each year. ill 2013, the bonds for ftre station #1 mature which results in a
reduction in debt levy in 2014.
The debt service for 2011 is already established. Bonds were issued in 2010 for the CR12 Phase III,
CR21 Extension, CR42/McKenna illtersection Signal, and Shady Beach, Rustic Road and Lords Street
resurfacing projects. The ftrst levy associated with the 2010 bond issue will be in 2011.
The CIP projects will impact the debt service levy beginning in 2012. The anticipated bond payments on
debt issued in conjunction with these projects along with payment adjustments on current bonds will
result in an increased debt service levy of approximately $199,724 for 2012, $144,687 for 2013, and
$138,326 for 2015. The 2014 debt service levy would have increased but, due to the ftre station #1 bonds
maturing in 2013, the overall impact is a decrease.
Page 3 of 3