CITY COUNCIL AGENDA REPORT
JUNE 21, 2010
5F
LARRY POPPLER, ASSISTANT CITY ENGINEER
LARRY POPPLER, ASSISTANT CITY ENGINEER
CONSIDER APPROVAL OF A RESOLUTION AWARDING THE CITY'S
STANDARDIZED CONSTRUCTION CONTRACT FOR STREET
CONSTRUCTION FOR THE BLUFFS OF NORTHWOOD MEADOWS
Introduction
This agenda item asks the City Council to award a contract to complete the
Developer Installed Improvements, mainly the final wear course of asphalt,
for the Bluffs of Northwood Meadows.
Historv
On September 5, 2006, the City Council approved the Development
Contact for the Bluffs of Northwood Meadows. Construction in this
development, with the exception of final paving (wear course) and
landscaping, was completed in the fall of 2006.
On April 7, 2009 the City found the developer, Manley Land Development,
in default of their Development Contract with the City. One of the remedies
of the Development Contract is to freeze building permits for the project.
The City froze the issuance of building permits at that point.
On, June 15, 2009 the City Council approved an agreement with the
Developer of the Bluffs of Northwood Meadows. Rather than freezing
building permits completely, the agreement sets out the terms and
conditions under which the City will release lots from the freeze and issue
building permits. One of the conditions was that the Developer pay
$36,000 to the City for the completion of the street improvements on Hawk
Ridge Road in exchange for the release of eight building permits. This
$36,000 fee has been received by the City and was used to pave Hawk
Ridge Road and Visionary Heights Circle in 2009. The agreement also
contains a condition where an additional $2,500 fee is collected on each
building permit above the initial eight permits. These funds are held by the
City to be used for completion of the wear course on the remaining streets
and other outstanding items of the Development Contract.
Current Circumstances
The City has collected $2,500.00 from the builder on an additional 20
building permits. The account now has sufficient dollars to complete the
wear course paving on the two remaining streets, Tahinka Place and
Tahinka Court.
R:\CoLlncil\2010 Agenda Reports\06 2110\BILlffs Northwood Meadows Paving Agenda.doc
The remaining fees collected with the building permits for this project will be
used to complete other outstanding Development Contract responsibilities
including: rain garden construction, as-built drawings, retaining wall
monitoring, legal expenses, silt fence removal, project cleanup, etc.
The City received quotes from three asphalt paving contractors as
tabulated below:
Prior Lake Blacktop $28,169.50
Bituminous Roadways $28,869.00
McNamara Contracting $31,670.00
Conclusion
The low quote was from Prior Lake Blacktop from Prior Lake, Minnesota in
the amount of $28,169.50. Prior Lake Blacktop has worked for the City and
developers on many Prior Lake projects. The most recent projects were
Brooksville Hills Phase II and CR 21 Watermain projects. As the lowest
responsible bidder, Prior Lake Blacktop is recommended by City staff to
complete the remaining street improvements for the Bluffs of Northwood
Meadows.
ISSUES:
The Developer of the Bluffs of Northwood Meadows is financially insolvent
and therefore can't enter into a contract for the remaining work. The City
has secured the dollars from builders to pay for the remaining work.
FINANCIAL
IMPACT:
There is no financial impact on the City. The funds to complete the street
improvements will come from the funds collected with the building permits.
ALTERNATIVES:
The alternatives are as follows:
1. Approve a resolution accepting bids and awarding the City's
Standardized Construction Contract for street construction to Prior
Lake Blacktop for the Bluffs of Northwood Meadows.
2. Deny this item for a specific reason and provide Staff with direction.
3. Defer this item until a specific date in the future.
RECOMMENDED j'Alternative #1
MOTION: /
.-----.
R:\CoLlncil\2010 Agenda Reports\06 2110\BILlffs Northwood Meadows Paving Agenda.doc
2
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 10-xxx
A RESOLUTION AWARDING THE CITY'S STANDARDIZED CONSTRUCTION CONTRACT
FOR STREET CONSTRUCTION FOR THE BLUFFS OF NORTHWOOD MEADOWS
Motion By:
Second By:
WHEREAS, The Developer of the Bluffs of Northwood Meadows has failed to complete the
Developer installed improvements required of it in the Development Contract; and
WHEREAS, The Developer Installed Improvements that remain incomplete include bituminous
pavement and appurtenant work; and
WHEREAS, To assure the improvements are completed and the property owners who
purchased homes in the subdivision are protected, the City has been charging a
builders fee to pay to have the work at the Bluffs completed based on an
agreement dated June 15, 2009 between the Developer and the City; and
WHEREAS, City staff has solicited bids for the work and received three quotes; and
WHEREAS, Prior Lake Blacktop of Prior Lake, MN submitted the lowest quote and is a
responsible bidder; and
WHEREAS, The City desires to assure the final wear course of bituminous is completed before
the winter to prevent undue degeneration of the streets.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The bituminous work remaining in the Bluffs of Northwood Meadows was competitively
quoted and Prior Lake Blacktop of Prior Lake, Minnesota is the lowest responsible bidder.
3. The Mayor and City Manager are hereby authorized to enter into the City's Standard
Construction Contract with Prior Lake Blacktop of Prior Lake, Minnesota in the amount of
$28,169.50 to complete the work in the Bluffs of Northwood Meadows.
4. Construction costs for the work in the Bluffs of Northwood Meadows will be paid from funds
collected from the builders pursuant to the June 15, 2009 agreement between the Developer
and the City.
5. Construction costs will be recorded in the Developers Agreement Fund, Account #260-
60112-501.
PASSED AND ADOPTED THIS 21st DAY OF JUNE, 2010.
YES
NO
I Myser
I Erickson
I Hedberg
I Keeney
I Millar
Myser
Erickson
Hedberg
Keeney
Millar
Frank Boyles, City Manager
R\Collncil\2010 Agenda Reports\06 2110\BILlffs Northwood Meadows Paving ResolLltion.doc