RESOLUTION 03-171
CONSIDER APPROVAL OF A RESOLUTION
APPROVING CHANGE ORDER NO. 2 FOR A MATERIAL CHANGE
AND ADDITIONAL WORK IF NEEDED
FOR RECONDITIONING OF THE CREST AVENUE WATER TOWER,
CITY PROJECT NO. 03-01
MOTION BY: LEMAIR SECONDBY: BLOMBERG
WHEREAS, Due to the drought-like conditions Prior Lake faced this summer, the Crest Avenue water
tower reconditioning project was delayed to meet the City's water demands. This delay may
result in a spring completion date; and
WHEREAS, Due to this delay, Champion Coatings, Inc. submitted a change order bid of $19,980.00 for
additional cost if spring work is necessary for the Crest Avenue Tower; and
WHEREAS, According to the CIP, there are sufficient funds in the Water and Sewer Fund for the
additional work requested.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
1. The recitals set forth above are incorporated as if fully set forth herein.
2. The City Council authorizes the expenditures from the Water and Sewer Utility Fund for additional costs for the
Crest Avenue water tower in an amount not to exceed $19,980.00.
Passed and adopted this 6t~, day of October 2003.
YES NO
Haugen X Haugen
Blomberg X Blomberg
LeMair X LeMair
Petersen X Pelersen
Zieska X Zieska
{Seal} Frank Boyles, Ci~an~ger
www.cityofpriorlake .cora
Phone 952.447.4230 / Fax 952.447.4245