Loading...
HomeMy WebLinkAbout8A - 2001 Improvement Project MEETING DATE: AGENDA #: PREP ARED BY: AGENDA ITEM: APRIL 16,2001 8A SUE MCDERMOTT, CITY ENGINEER CONSIDER APPROVAL OF A RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND AUTHORIZING ADVERTISEMENT FOR BIDS FOR STREET RECONSTRUCTION FOR 2001 IMPROVEMENT PROJECT (CITY PROJECT #01-11) DISCUSSION: History Proposed street reconstruction improvements to Evanston A venue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakota Street, Oak Street and Memorial Trail (Project #01-11) are in the approved 2001 Capital Improvement Program. Resolution 01-05 authorizing preparation of plans and specifications for the projects was approved by the City Council on January 22, 2001. Public informational meetings were held in January and March of 2001 to provide affected property owners the opportunity to discuss the projects. All of the meetings were well attended. Plans were available at the March open house for review and City staff was in attendance to answer questions from the public. Current Circumstances This project includes storm sewer, sanitary sewer, water main, concrete curb and gutter, aggregate base, bituminous surfacing, sidewalk, and appurtenant work. The engineer's construction cost estimate is $1,507,150. Indirect costs are estimated at 28%, and include engineering (17%), administration (5%), and financing (6%) for a total estimated project cost of $1,726,500. The construction of this project is proposed to be funded through assessments, tax levy, Collector Street and Trunk Reserve funds. Issues The Council held an informational meeting at the March 19th council meeting to discuss the following five issues that were raised at the public hearing: 162QQpf.oole Creek Ave. S.L, Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER TT .- I i 1 II' 1. Assessment method: unit versus front footage 2. Sidewalks 3. Tree replacement 4. Alleys 5. Memorial Trail: one-way versus two-way traffic Attached is a one-page summary addressing each of the issues raised by the neighborhood residents. A copy of this position paper was distributed to the attendees of the March 19th informational meeting. Items 2 through 5 have been incorporated in the final plans and specifications or will be addressed during the project construction. The following table is a breakdown of the project costs: PROJECT #01-11 Feasibility Current Estimate Estimate Street/Storm Sewer* $959,920.00 $1,002,900.00 Sidewalks $46,400.00 $43,200.00 Trunk Storm Sewer $176,300.00 $148,400.00 Sanitary Sewer $318,840.00 $231,800.00 Watermain $326,620.00 $300,200.00 Sewer and Water Services* $105,000.00 $105,000.00 TOT AL PROJECT $1,933,080.00 $1,831,500.00 * Include 28% indirect costs include engmeerIng (17%), administration (5%), and financing (6%). The estimated assessment rate for this project based on the Feasibility Report was $4,219.44 per unit or $52.01 per front foot. Using the current engineer's estimate and the recommendations outlined above, the estimated assessment rate is $4,408.00 per unit or $54.33 per front foot. Conclusion The staff will provide a brief summary of the plans and specifications. The staff believes it is appropriate for the City Council to approve project plans and specifications and authorize solicitation of bids for the 2001 Improvement Project #01-11, Evanston Avenue, St. Paul A venue, Jordan Avenue, Minnesota Street, Dakota Street, Oak Street, and Memorial Trail. The actual bid amounts will APPPLAN verify the estimated assessments. If the Council has concerns at that stage, they could direct appraisals to determine the degree of benefit. FINANCIAL IMPACT: The total cost of this year's projects are estimated to be $1,831,500 and will be recovered through special assessments, Collector Street and Trunk Reserve funds in addition to tax levy for bond repayment. The table below outlines the project costs based on the engineer's current estimate. Project Assessments Tax Levy Trunk Collector Total Reserve Street Project #01-11 $506,200 $601,700 $680,400 $43,200 $1,831,500 AL TERNA TIVES: The alternatives are as follows: 1. Adopt a resolution approving plans and specifications for Project #01-11, 2001 Improvement Project, including Evanston A venue, St. Paul Avenue, Jordan A venue, Minnesota Street, Dakota Street, Oak Street, and Memorial Trail and authorizing advertisement for bids. 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item until some date in the future. RECOMMENDED MOTION: Motion and second adopting a resolution approving plans and specifications for Project #01-11, 2001 Improvement Project, including Evanston A venue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakrt Street, Oak Street, and Memorial Trail and authorizing adverti ment for bids. I APPPLAN III I HI 3~ RESOLUTION 01~ A RESOLUTION APPROVING THE PLANS AND SPECIFICATIONS AND AUTHORIZING THE ADVERTISEMENT FOR BIDS FOR 2001 IMPROVEMENT PROJECT #01-11 FOR THE CITY OF PRIOR LAKE, MINNESOTA MOTION BY: ~t SECOND BY: ~ WHEREAS, pursuant to Resolution 01-05, adopted on January 22, 2001, the City Engineer has prepared plans and specifications for the utility improvement. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA that 1. Such plans and specifications, a copy of which is attached hereto and incorporated herein by this reference, are hereby approved. 2. The City Manager shall prepare and cause to be inserted in the official paper and in the Construction Bulletin an advertisement for bids for the making of the improvement pursuant to the attached plans and specifications. The advertisement shall be published not less than 21 days prior to bid opening, shall specify the work to be done, and shall state that the bids will be received by the City Manager until 10:00 a.m. on Friday, May 18,2001, at which time the bids will be publicly opened at City Hall at 16200 Eagle Creek Avenue SE by the City Engineer. No bids will be considered unless sealed and filed with the City Manager and accompanied by a cash deposit, cashier's check, bid bond, or certified check payable to the City of Prior Lake in the amount of five (5) percent of the amount of such bid. 3. The City reserves the right to reject any and all bids for any reason as determined solely by the City. Passed and adopted this 16th day of April, 2001. YES NO Mader Mader Ericson Ericson Gundlach Gundlach Peterson Peterson Zieska Zieska { Seal} City Manager City of Prior Lake 162(9l)\~~~~~lm~neA~ct~ke, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER ADVERTISEMENT FOR BIDS 2001 Improvement Project #01-11 Reconstruction of Evanston Avenue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakota Street, Oak Street and Memorial Trail NOTICE IS HEREBY GIVEN that sealed proposals will be received by the City Council of the City of Prior Lake, Minnesota at the Prior Lake City Hall, located at 16200 Eagle Creek Avenue S.E., Prior Lake, MN 55372 until 10:00 a.m. local time, on the 18th day of May, 2001, and will be publicly opened at said time and place by two or more designated officers or agents of the City of Prior Lake, said proposals for the furnishing of all labor and materials for the construction, complete in place of the following: APPROXIMATE MAJOR QUANTITIES PROJECT #01-11 Common Excavation Concrete Curb and Gutter Class 5 Aggregate Base Bituminous Paving Pipe Jacking Directional Drilling Storm Sewer Sodding Watermain Sanitary Sewer 12,800 10,200 9,300 3,700 190 540 3,000 12,900 5,700 3,600 CY LF TON TON LF LF LF SY LF LF Proposals arriving after the designated time will be returned unopened. The Bids must be submitted on the bid forms provided in accordance with contract documents, plans, and specifications as prepared by the City of Prior Lake Engineering Department, 16200 Eagle Creek Avenue S.E., Prior Lake, MN 55372. Contract documents, plans, and specifications may be obtained from Prior Lake Engineering Department by calling (952) 447-9830. Copies may be obfained upon deposit of Seventy five dollars ($75.00) non-refundable deposit per set. No bids will be considered unless sealed and filed with the City Manager of Prior Lake and accompanied by a cash deposit, cashier's check, bid bond, or certified check payable to the City of Prior Lake, for five (5%) percent ofthe amount bid to be forfeited as liquidated damages in the event that the bid be accepted and bidder shall fail to enter promptly into a written contract and furnish the required bond. 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245 G:\PROJECTS\200111IFROGIBIDADV.DOC AN EQUAL OPPORTUNITY EMPLOYER III 11 , r I' No bids may be withdrawn for a period of sixty (60) days from the date of opening of bids. The City of Prior Lake reserves the right to reject any or all bids DATED: April 16, 2001 Frank Boyles City Manager City of Prior Lake, Minnesota To be published in the Prior Lake American on April 21, 2001 and April 28, 2001. To be published in the Construction Bulletin on April 20, 2001 and April 27, 2001. G:\PROJECTS\200 1 \11 FROG\BlDADV .DOC 2001 Public Improvement Project - Resident Concerns March 19, 2001 1. Method of Assessment: Residents who attended the Public Hearing expressed concern about of the front footage methodology. On the other side, persons with smaller lots believe they overpay with the unit method. The recommendation of the special assessment committee is to retain the front footage method for the following reasons: . 45 of the 78 single-family residential units (nearly 60%) have front footages of 80 feet or less, with 31 of these lots having frontages of 60 feet or less. . The front footage method is the application that is most familiar to the residents as a result of the informational meetings and the public hearing. . The front footage application is the most equitable because the cost is directly proportional for the most part to the size of the lot. 2. Sidewalks: There are no special assessments for sidewalks. All sidewalks are paid for from other sources. Sidewalks are to be constrl,lcted beginning at CSA!-i 44 down Jordan Avenue to Minnesota Street to Evanston Avenue to CSAH 21. The sidewalk will connect the County Road, the Park and the School. A sidewalk cannot be constructed economically on the east side of St. Paul Avenue because of lot grades and setbacks. A sidewalk is also proposed along Memorial Trail in the park and will be located so as not to disturb existing trees. 3. Tree Replacement: As with any City reconstruction project, tree removal will be kept to a minimum. By decreasing the width of Memorial Trail to 20 feet, only two pines on park property will have to be relocated with a tree spade and the oaks will remain undisturbed. As many as five trees on private property may be removed depending on storm sewer and watermain final design. Several trees will be removed within the right of way including an area along the north side of Oak Street. Three of the trees are approximately 20" in diameter. Staff will continue to work with property owners to locate sewer and water services so that tree removal is minimized. Trees on private property (not right-of-way or public property) that die within twelve months of project completion, will be replaced with 2-3 caliper-inch trees from the City's nursery stock if the City determines that the tree loss was related to the project. 4. Alley: The City will discuss installation of curb cuts or vacation of the alley with affected residents. 5. Memorial Trail (east/west only): Memorial Trail will be built to a 20-foot width in accordance with the City's past practice considering the State Uniform Fire Code. As previously mentioned, narrowing the width of the street results in saving trees. The street can be striped and signed for two-way or one-way traffic. IH . r Tl PRELIMINARY REPORT FOR THE CITY OF PRIOR LAKE 2001 PUBLIC IMPROVEMENT PROJECT INCLUDING UTILITY IMPROVEMENTS, STORM SEWER, GRADING, CONCRETE CURBING, STREET PAVING, SURFACE IMPROVEMENTS, AND APPURTENANT WORK December 18, 2000 I hereby certify that this Feasibility Report was prepared by me or under my direct supervision and that I am a duly registered Professional Engineer under the laws of the State of Minnesota. J~ 41-A.c;[)~--tf Susan J. McDermott, P.E. Reg. No. 21715 1;1 /18/00 Date G:\PROJECTS\2000\ 18-00 Feasibil ity Report\FEASREPOR T .DOC 2 III ~ . 1 I ! II INTRODUCTION On June 19, 2000, the Prior Lake City Council adopted Resolution 00-53, which ordered the preparation of a feasibility report for Project 01-11 that includes street and utility improvements to Evanston A venue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakota Street, Oak Street and Memorial Trail located within Sections 1 & 2, Township 114, Range 22, Scott County, Minnesota. SCOPE This report evaluates the feasibility of reconstructing the streets and replacing utilities in the project area. All existing infrastructure elements (streets, sanitary sewer, water main, etc.) were evaluated, improvements recommended, cost estimates of the proposed improvements prepared and funding strategies developed in this report. DESCRIPTION OF PROJECT The project area is known as Frogtown and includes Evanston Avenue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakota Street, Memorial Trail and Oak Street. Exhibit 1 shows the project area. Evanston Avenue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakota Street, and Memorial Trail have failing bituminous surfaces, bituminous curb and segments of concrete curb. A portion of Evanston Avenue and Oak Street has gravel surfaces. The existing road widths vary from 26 feet to 39 feet with the exception of Memorial Trail. Memorial Trail is currently a one-way street with a 12-foot wide surface. There are some existing reinforced concrete storm sewers and culverts that carry storm water runoff to an existing ditch system and ultimately to the DNR pond located adjacent to Lakefront Park. The majority of these streets were originally paved in 1963. The streets no longer meet minimum design standards and it is not cost effective to continue to patch the streets. The water main system was installed in 1939 and 1953 and consists of 6-inch cast iron pipe and some ductile iron pipe. A major portion of the water main within the project area was installed in 1939. The sanitary sewer system was installed between 1960 and 1963 and consists of 8-inch vitrified clay pipe. A 12-inch reinforced concrete trunk sewer main replaced the 8-inch main on Evanston in 1973. The sanitary sewer within the project area was televised in September 2000. The televising report indicated numerous cracked joints, cracked pipes, sags in the pipe, and roots. Residents in the area have reported numerous backups and have had to continually hire "Roto-Rooter" to clean their services. In addition, the City has had to repair and replace segments of the sewer due to failure, two in the past two months. G:\PROJECTS\2000\18-00 Feasibility Report\FEASREPORT.DOC 3 111 ~ ] J m Proposed improvements include 7-ton design street reconstruction with storm sewer, concrete curb and gutter, driveway restoration, and bituminous surfacing. Street widths for Evanston Avenue, St. Paul Avenue, Jordan Avenue, Memorial Trail, Minnesota Street, Dakota Street, Oak Street, and Credit River Road are proposed to be 32 feet. Memorial Trail is proposed to be 24' wide. The typical street section is shown on Exhibit 2. Sidewalks are proposed along one side of Jordan Avenue, Minnesota Street, and Evanston Avenue to connect the existing trail systems on CSAH 44 and CSAH 21 (see Exhibit 1). Street lights are proposed to be re-installed in existing locations at all intersections. Sanitary sewer will be replaced to correct the failing system. A new sanitary sewer main will be installed on Oak Street to eliminate existing long service lines. The water main will be replaced with 8" mains and additional fire hydrants will be added to the project, as the existing hydrant spacing is not in conformance with City requirements. New water main pipe will be installed on a portion of Evanston Avenue, Oak Street, and Memorial Trail to loop the system and eliminate long services. See Exhibits 3 and 4 for proposed sanitary sewer and water main locations. The costs outlined in this report also include an option for residents to have their sewer and water services replaced from the right-of-way line to the house. Residents who opt to do this would be required to sign an agreement waiving the right to appeal with that portion of the assessment that is associated with the service costs. For the purposes of this report, 30 sewer and water service replacements were estimated. The existing right-of-way is 66 feet wide on all of the streets except Jordan where it is 60 feet wide. Temporary construction easements or right-of-entry agreements will be necessary for driveway restoration due to the topography of the area. Acquisition of additional easements will be pursued where the existing roadways lie outside of the existing right-of- way. The storm sewer system improvements will include a new outlet pipe beneath T.H. 13 to carry storm water runoff from the project area to the DNR pond, which is adjacent to Lakefront Park. The DNR pond (#159P) located south of Kop Parkway is a landlocked basin. In 1996 and 1997, the water elevation of this pond was at an elevation that resulted in flood damage to the property at 16100 Evanston Avenue. This pond is in need of an outlet to not only protect property owners from future flooding, but to accommodate future downtown redevelopment as well. A lift station is being proposed at the southwest corner of the pond that will discharge into the pond located near City Hall and through the storm sewer system to Prior Lake. The existing 24-inch culvert under T.H. 13 has settled over time creating a back slope. A parallel 24-inch outlet pipe is being proposed under T.H. 13. This will provide the necessary capacity to pass storm flows from the east side of T.H. 13 to the west side. Proposed storm sewer improvements are shown on Exhibits 5 and 6. The benefiting property owners will be assessed for street, storm sewer and utility service construction. The property tax levy will be used to finance the City's portion of the street reconstruction costs. The Trunk Reserve Fund will be used to finance the water, sanitary sewer and trunk storm sewer improvements. The Collector Street Fund will be used to fund sidewalk improvements. G:\PROJECTS\2000\ 18-00 Feasibility Report\FEASREPORT.DOC 4 Ilf 'If 1 In FEASIBILITY From an engineering standpoint, this project IS feasible, and can be accomplished as proposed. ESTIMATED COST The following costs were prepared based upon an Engineer's Estimate and are subject to change, depending on the final design of the project, required easements and/or right of way, soil conditions, bids received, and actual work performed. The following table shows the cost to rehabilitate or restore streets to a seven ton design standard and includes reconstruction of Evanston Avenue, St. Paul A venue, Jordan A venue, Minnesota Street, Dakota Street, Oak Street, and Memorial Trail: ITEM Street/Storm Sewer* Sidewalks Trunk Storm Sewer Water Main Sanitary Sewer Sewer and Water Services* COST $959,920 $46,400 $176,300 $326,620 $318,840 $105,000 TOTAL PROJECT COST $1,933,080 *lncludes 28% Indirect Costs detailed as follows: Engineering (17%) Administration (5%) Financing (6%) FUNDING The area proposed to be assessed is every lot, piece, and parcel within the City limits benefiting from said improvement, whether abutting or not, within the following described areas: Evanston Avenue, St. Paul Avenue, Jordan Avenue, Minnesota Street, Dakota Street, Oak Street, and Memorial Trail Specific property descriptions included in the above-described area, but not inclusive, are as follows: Borgerding Addition Costello's Addition Schmokel's Addition Original Townsite Prior Lake G:\PROJECTS\2000\18-00 Feasibility Report\FEASREPORT.DOC 5 111 I -~- ESTIMATED ASSESSMENTS The improvement cost can be assessed on a unit basis or an adjusted front footage basis to the benefiting properties as per the Assessment Policy adopted by the City Council on February 21, 1989, and as amended. Both methods are shown for the project. The following breaks out estimates at 60% City cost and 40% assessment for streets and lateral storm sewer. Total Street & Storm Sewer Project Cost $959,920 Project Levy (60%) $575,950 Project Assessment (40%) $383,970 Front Footage Method Estimated Assessable Front Footage 7227/FF Estimated Assessment Rate $53.13/FF Unit Method Assessable Units Estimated Unit Assessment 78 Units $4,173.57/Unit Optional Water & Sewer Service Costs Estimated Assessable Units Estimated Unit Assessment $105,000 30 Units $3,500/Unit Funding for the remainder of the project is summarized in the following table: COST ESTIMATE AND FUNDING SOURCES FUNDING SOURCE ITEM COST ASSESSMENTS TAX LEVY TRUNK COLLECTOR WATER ESTIMATE RESERVE STREET QUALITY FUND FUND FUND Street/Storm $959,920* $383,970 $575,950 Sewer Sidewalk $46,400 $46,400 Trunk Storm $176,300 $136,300 $40,000 Sewer Sanitary Sewer $318,840 $318,840 Water Main $326,620 $326,620 S/W Services $105,000* $105,000 TOTAL $1,933,080 $488,970 $575,950 $781,760 $46,400 $40,000 G:\PROJECTS\2000\ 18-00 Feasibility Report\FEASREPORT.DOC 6 III I ! I *Includes 28% indirect costs; 17% Engineering 5% Administration 6% Financing With a total estimated project cost of $1,993,080, an estimated bond issue of $1,075,000, the assessed amount of $488,970 would be equivalent to 45% of the total bond issue. Minnesota Statutes Chapter 429 Special Assessment Bond issue requires that a minimum of 20% of the total bond issue amount be recovered through special assessments. PROJECT SCHEDULE The following project schedule outlines an approach to complete the assessable projects in 2001: Accept Feasibility Study/Call for Public Hearing 12/18/00 Hold Informational Meeting 1/09/01 Conduct Public Hearing/Accept Project/Order Plans and Specifications 1/22/01 Hold Informational Meeting 3/01 Approve Plans and Specifications/Order Advertisements for Bids 4/16/01 Open Bids 5/18/01 Accept Bids/Award Contract 6/4/01 Begin Construction 6/18/01 Authorize Amount to be Assessed/Schedule Assessment Hearing for 9/00 9/01 Conduct Assessment Hearing/Adopt Assessment Roll 1 % 1 Complete Base Course of Bituminous 1 % 1 CONCLUSION The proposed improvement is necessary, cost effective, is feasible from an engineering standpoint and should be made as proposed. The total estimated cost of the recommended improvements is $1,933,080. A portion of this project is proposed to be assessed to the benefiting property owners and the remainder through other funding sources. G:\PROJECTS\2000\18-00 Feasibility Report\FEASREPORT.DOC 7 III - Ii I rr () ~ [J 0 Q 0 0 [?OO con I ~ 160TH ST. S.E. G:iJO oClCJ ....I 0 /! ODD ~ ~d' 0 0 0:: 0 ~ 0 ::s Q o 0 0 0 MEMORIAL. TRL $=1<:) <;5 0 ') n 0 D ROAD WI CONC. CURB & GUTTER - SIDEWALK o PROJECT AREA MAP 2001 FEASIBILITY REPORT EXHIBIT 1 III T -,-- I a R.O.W. ~ ROADWAY 33'* R.O.W. ARIE~ 5' CONC. SIDEWALK I VARIES 16' 861 8 CONC. CURB&GUTTER 1.5" 2331 TYPE 41A BITUMINOUS WEAR COURSE 2.5" 2331 TYPE 31 B BITUMINOUS BASE COURSE 8" CLASS 5 AGGREGATE BASE .. SELECT GRANULAR * JORDAN AVE RIGHT OF WAY IS 60' NOTE: ALL ROADS TO BE CONSTRUCTED TO A MIN. OF 7 TON DESIGN ALL STREETS EXCEPT MEMORIAL TRAIL PROPERTY LINE Cf. ROADWAY PARK 23' l' 12' 12'~ B618 CONC. CURB&GUTTER 2% - ~' CONC. SIDEWALK . . .... .. "."" .. r- . "'.. .......:;- .. 1.5" 2331 TYPE 41A BITUMINOUS WEAR COURSE 2.5" 2331 TYPE 31 B BITUMINOUS BASE COURSE 8" CLASS 5 AGGREGATE BASE 8" SELECT GRANULAR NOTE: ALL ROADS TO BE CONSTRUCTED TO A MIN. OF 7 TON DESIGN MEMORIAL TRAil PROPOSED STREET SECTION 2001 FEASIBiliTY REPORT EXHIBIT 2 III T I --~_._--_.._-------~ I r II ~ Q 0 0 un () o 160TH ST. S.E. o ~ i 0 odJ oU 1) o ,CU I ~P'i? [] o Q 0 v QVa JJ rJ~r. QJ 0 4::J [1....~ en Uz <I: D~ v 00 0 ~O ~ES~ST~ ( -, EXISTING SANITARY SEWER MAINS ---'> PROPOSED 8" PVC SEWER MAINS . PROPOSED SANITARY SEWER 2001 FEASIBILITY REPORT III t --r-- .------------T ~ [fOO, CJ I D ~DoDCJ ~ o 0 0 ;ii! o < ~ DDrJoD ~ o 0 0 o $=1,> ') MEMORIAl TRL o n o TO BE ABANDONED EXHIBIT 3 I H () ~ CJ 0 Q 0 0 ~ un [?OO I 160TH ST. S.E. 0 oU D G=:lJ(J. oDCJ ii! o 8 c::u o 0 0 ~ 0 a:: 0 Dc" 0 0 [fi Q ::IE 0 00 o 0 0 d/lI( s.,- 0 $=I,> ~ MEMORiAl TRL t;:b. 0 ') CJ U 0 0 - PROPOSED 8" D.I.P. WATERMAlN . HYDRANT ~ VALVE o PROPOSED WATERMAIN 2001 FEASIBILITY REPORT EXHIBIT 4 III I, I I II 0 c=:J CJ Q c 0 G (? 0 0 c::::J c:::::J 'U c::::J ~ 160TI-I ST. S.E. D DodJ D G=iJGODq ~ o 1J o 0 0 ~ o 5 OD od' 0 0 ~ 0 ~ og o 0 0 o c9 MEMORIAL TRL r() C8 G ') [h D~ 0 o 0% 0 dDrQ I ~EsQE _ PROPOSED R.C.P, STORM sEWER . CATCH aASlN . FLAREO END sECTION . MANHOLE EXH\B\1' 5 . PROPOSED STORM SEWER 2001 FEASIBILITY REPORT _------.---.".----~- --,----r-, - ~.... -" . ------ -....---. , . \ I "'=== C! ~ I "= iF I ~G {J ~. @] [ tf) E Gill [h [ \) g] IT Br Lift Station BfJ Exhibit 6 [b o () t!f;;; D {J 4!Jv Ii! If <\t> ~ 0 ~ <<> ... <t> ~ ~ <Ii Ii <0 ~ <0~ cPGZJ <0 0 D o 0::: I- ...J <( 0::: o :E w :E D Lf=a 181 0 u G\) o 0 0 [ill o B cPo o \) a fZJ ~ DO ~-------, / / ( /c5 \------,/ ? LAKE FRONT J?ARK (- ) '", I (~// , J \ ,,( J -) """ //-j ~------- --./' ,~/ " , ~ "" ), J ( liP (~', / \ " ,\ ) ~)) fJJ "~,- / ((~ ffJJJ &........................ -,-,~ ~ ~-'-". t!J{] I!ifiJ e -,) ,,) tiJ!:J tzJC:fo !J2:; \) /'----------- / ) / I L (-~ I~ u o QITld 00 qo L0J1 CJ @ O. CJ [3J CITJ [BJ EJ [!;Do [] 0 CJ 00 CJ CJ 0 o CJ o .~ D [].. [] o lli1 ITJ LJ EJ Lb LJ 0 JD L4JL8UU[JEJ 00 00 0 0 CJ !]j LJDctJC1J 0 o CJ DO IT EPJ ' [] ;' I [] D I Pl............ \ ( L...I '-- \ ,...,..... ~,--------) I>j ~--/ o \8 /I : 0 I E2[J ~%9.: ~. 47 f1f}j E@fEIJlfSpcP1!19 't8P' D ~ o 3D 00 o o CS DO ~OOD CI