RE
~INNESO~~ RESOLUTION AWARDING BID FOR THE
NSTRUCTION OF A SALT/SAND STORAGE BUILDING
MOTION BY:
Kedrowski
SECOND BY: Schenck
WHEREAS, the need for a storage facility to store salt and sand is essential to
the street snow and ice maintenance efforts of the public works
department, and
WHEREAS, an indoor salt/sand storage facility facilitates more cost effective
snow and ice control, and
WHEREAS, an indoor structure better protects the environment from the
destructive effects of salt, and
WHEREAS, a precast salt and sand storage building with a 2,500 ton capacity
is recommended, and
WHEREAS, bids have been solicited and received for the construction of a
Salt/Sand storage building as follows:
CONTRACTOR
Hunnerburg Construction
J.S. Cates Construction
CM Construction
Northfield Construction
Merrimac Construction
Morcon Construction
FNC Construction
BID AMOUNT
$174,975.00
$180,000.00
$180,000.00
$180,650.00
$187,998.00
$210,000.00
No Bid
NOW THEREFORE, BE IT RESOLVED by the Mayor and City Council of the
City of Prior Lake that it should and hereby does award bid for the construction of a
Salt/Sand Storage Building be awarded to Hunnerburg Construction at a cost not to
exceed $174,975.00. Said funds for this project will be allocated from the following:
1. $100,000.00 from the original budget.
2. $11,914.00 remaining from the original budget due to cost savings.
3. $37,394.00 from additional interest earnings.
4. $34,947.00 from the Sewer and Water Fund balance.
For a total of $184,255.00
AND FURTHER, the Mayor and City Manager are authorized to execute a
contract of the construction of this building.
16200 E~~~OO~ S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
Passed and adopted this 5th day of August , 1996.