HomeMy WebLinkAbout9E - Thomas Ryan Concession
MEETING DATE:
AGENDA #:
. PREPARED BY:
REVIEWED BY:
AGENDA ITEM:
DISCUSSION:
CITY COUNCIL AGENDA REPORT
November 5, 2001
9E
AI Friedges, Parks Supervisor
Bud Osmundson, Public Works Director
CONSIDER APPROVAL OF A RESOLUTION APPROVING
CHANGE ORDERS TO CONTRACTS FOR THE CONSTRUCTION
OF THE THOMAS RYAN MEMORIAL PARK
RESTROOM/CONCESSION BUILDING.
History: The purpose of this agenda item is to approve a change
order to the contracts for the construction of the Thomas Ryan
Memorial Park restroom/concession building. The original
contracts were awarded on October 16, 2000. Attached is the
original approving resolution. However, theproject was held up
due to various issues related to the annexation of the property,
and permit fee matters.
Staff and City Council have discussed the issues with Spring
Lake Township representatives over the past year. Earlier this
year an agreement on annexation of the park property from the
township to the City was completed, and the State Planning
Board approved the annexation of September 14, 2001. As of
October 15, 2001, the park property is within the City limits.
Current Circumstances: To save money on the construction of
this building, we are acting as our own general contractor and
we bid the sub-contractors individually. Since the contracts were
awarded over one year ago, costs have risen for the contractors
in both labor and materials.
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
I:\COUNCIL\AGNRPTS\FORMA T.DOC
l-~TT
AN EQUAL OPPORTUNITY EMPLOYER
ISSUES:
FISCAL IMPACT:
Contracts were awarded and have been signed for the following nine
categories:
Original Change New
Catel!:ory Contractor Amount Order Total
Earthwork Mahowald Builders $16,080.00 $1,608.00 $17,688.00
Concrete Cannon Const. Co. $10,900.00 $ 425.00 $11,325.00
Masonry Greystone Const. Co. $45,520.00 $4,900.00 $50,420.00
Carpentry Cannon Const. Co. $40,695.00 $1,588.00 $42,283.00
Hardware, Doors Cannon Const. Co. $ 4,450.00 $0 $ 4,450.00
Tile Jerry R. Conley Tile $ 6,175.00 $0 $ 6,175.00
Painting Lonsdale Painting Co. $ 4,635.00 $ 463.00 $ 5,098.00
Mechanical Pumper Plumbing
& Heating $20,898.00 $1,044.00 $21,942.00
Electrical Hayes Electric $10,870.00 $ 470.00 $11,340.00
Restroom
Accessories Kully Supply Co. $ 9,425.00 $0 $ 9,425.00
Concession
Windows &
Accessories In House $ 6,400.00 $0 ...6..400.00 ~
TOTALS $176,048.00 $10,498.00 $186,546.00 ,/
Conclusion: The total increase of $10,498 reflects a 6.0% increase for
the change orders. Staff recommends that the change orders be
authorized. Should the Council authorize the change orders,
construction will start in the next two weeks. Footings and subgrade
. work is anticipated to be completed before "freeze up" and the
remainder of the building will be constructed during the winter months.
The key issue to whether the Council believes that a savings greater
than the $10,498 can be achieved by rebidding the project. A second
consideration is the likelihood that rebidding the project will likely
delay opening this park next year. The staff believes that the change
order requests are not unreasonable and will allow winter construction
to occur barring extreme weather in the near future.
The only remaining issue affecting the concession/restroom facility is
the sewer extension which is estimated to cost $45,000. We are
working on a design for this and will return to the Council as soon as
possible for final approval. This issue does not affect construction of
the concessionlrestroom facility.
Budget Impact
The total cost of the building with the proposed increases will now be
$186,546.00. Funds for this project have been reserved in the
X:\FRIEDGES\AGENDAS\1l1omas Rayn Change Order.doc
AL TERNA TIVES:
RECOMMENDED
MOTION:
REVIEWED BY:
referendum account.
-'
The alternatives are as follows:
1. Approve Change Orders to the contract for the construction of the
Thomas Ryan Memorial Park Restroom/Concession Building and
appurtenant work as set forth above and in the attached resolutions.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason.
Staff recommends alternative number 1.
ic Works Director
X:\FRIEDGES\AGENDAS\Thomas Rayn Change Order.doc
I r I ~
-.
"<'MIl
RESOLUTION 00-109
ION AUTHORIZING THE AWARD OF BIDS AND EXECUTION OF CITY'S
ANDARD CONTRACT FOR THE CONSTRUCTION OF THE THOMAS RYAN
MEMORIAL PARK RESTROOM/CONCESSION BUILDING.
WHEREAS,
WHEREAS,
WHEREAS,
WHEREAS,
WHEREAS,
WHEREAS,
MOTION BY: ERICSON
SECOND BY: GUNDLACH
On February 25, 1997 the citizens of Prior Lake passed a Parks and Library
Referendum which included the development of an athletic facility; and
the funding source for the restroom/concession building will be drawn from
the Parks and Library Referendum; and
the plans and specifications for the restroom/concession building have been
approved by the City Council; and
bids have been solicited and received for the restroom/concession building;
and
it appears that the following companies are the lowest responsible bidders
Mahowald Builders
Cannon Construction Co.
Greystone Construction
Jerry R. Conley Tile
Lonsdale Painting,
Hayes Electric,
Pumper Plumbing and Heating,
Kully Supply Co.;
and
the City is responsible for certain portions of the construction including
fountains, concession windows, and concession equipment that will not
exceed a cost of $6,400.00.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOT A, that bids are hereby awarded to the following companies in the following
amounts not to exceed a total of$176,048.00:
162001E~gle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
I 1 r 11
....---...
Mahowald Builders Earthwork $16,080.00 i
l_g_~~?E.:~~~~i~~].?i.g:?=::.:::'=~:~===~==~?_ncr~i~:::~........-.- ""$"i-9.:;2.Q9~~:~J
i Greystone Construction . Masonry . $45,520.00 i
[~~?~::::~?nsi~~E.9_~:~~~~:=_:'~~':~:.:=:===CaiJi~~!~:=:::~~==:~:.:.:::.-':::~~:q~~~:~:.~~L!
~je~W~~i~i~:f}~n C~~~:=_ i _",:==~~~~~11i: ~:~~=~=~~~:I~=:.~,:=~~J.1%~~~~j
['-Lonsdale Painting Co. . Painting : $4,635.00 I
[I~~EiEpiii@i~ng-~!:!~~hn~_I,'==:B~~~~~.~~C:~=:=J:'===~~?~8~?:Qq]
l_li.~ye~_~~~.~!~~._,____....._._____",__."..",_____.___~_1~_~!~~~~"..._"_,__,_,_,__,,,_1...,_.._..._..._~_!9_&?_?':Q2.J
t Kully Supply Co. _ ____,___L,__B.-~~tr?_?!? ~C?,~~~~!i~_.._....__,_____,__~,~~~~~:~Q..J
r-I;~House- -.---,--,- ,. I Concession Windows & . .
i !.
, ' Accessones
. ,
r-----..,-'-"'---'-'-------..r-----------."--."'TOTAL ;
$6,400.00 i
$176,048.00 i
and
FURTHER, that staff is authorized to expend $6,400 for in-house portion of the project; and,
FURTHER, the total expenditures for the restroom/concession building are not to exceed
$176,048; and,
FURTHER, the funds for the restroom/concession building will be drawn from the Parks and
Library Referendum; and,
FURTHER, the City Manager is hereby authorized to return bid securities submitted with the
proposals to vendors, following the execution of contracts; and,
FURTHER, the Mayor and the City Manager are authorized to execute the City's Standard
Contract on behalf of the City for each of the restroom/concession contracts.
Passed this 16th day of October 2000.
YES
Mader Absent Mader
Ericson X Ericson
Gundlach X Gundlach
Petersen X Petersen
Zieska X Zieska
NO
Absent
{ Seal}
00-109
RESOLUTION 01~ /2 f
RESOLUTION APPROVING CHANGE ORDERS TO CONTRACTS
OR THE CONSTRUCTION OF THE THOMAS RYAN MEMORIAL PARK
RESTROOM/CONCESSION BUILDING.
Motion By:
JP
Second By:
M~
WHEREAS, as part of the amenities for Thomas Ryan Memorial Park, a concession/restroom facility is
to be constructed; and
WHEREAS, the City is to act as general contractor for this project; and
WHEREAS, bids were solicited and contracts awarded for this project on October 16, 2000; and
WHEREAS, project construction was delayed for one year by the annexation process and contractors
were bound to maintain their bid amount for 45 days; and
WHEREAS, each contractor has committed to complete their contractual obligations provided
requested change orders are approved; and
WHEREAS, the City Council believes it most prudent to revise the contracts by change order since the
increase in cost is reasonable, re-bidding the project would further delay project
completion without assuring better prices, and the opening of the park would be further
delayed if this work is not initiated this year.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA
that:
1. The recitals set forth above are incorporated herein.
2. Change orders in the following amounts are hereby approved:
r-' '--'-----.-----'-'-.---T.'---......'..----'-'----...-'........-.-...............-...,--......----...-.~
i Category 1 Contractor ! Original Amount i Change Order I New Total I
i Earthwork ! Mahowald Builders I $16,080.00 ! $1,608.00 I $17,688.00 !
,.....,.....-' i ' ..----------'---,--.--...-.- , ----..............----'-1
! Concrete i Cannon Const. Co.! $10,900.00 i $425.00 I $11,325.00 i
,-,-,--------~ ---.--~------..,___l,---.--,-.._...._...____,__,_'..____,___...__._........._..__........_.,_,.........,
L~....9so!!!)'_.._----! GreY..sto~e Con_~!:...~o 1_,__ $45,5?Cl:Q_Q___......._!..____...~~~..Q0. QQ.....__-..J_..J?g!,~,~Q.oq______..j
f_..garpentrY..____,_... i Cannon 9..Q~~!:....g_9...:.,_+-____ $49.!.69!5.0Q____...l___...._..._~~,~?00 _.._,...! _~~~~~:QfL___.j
! Hardware & Doors i Cannon Const. Co. i $4,450.00 ! $0 ! $4,450.00 !
[Tile ~...___ -'--rSeS!LQ..9..!l~y'TiL~.._ ' " $6, fI?oQ___-==-_-[~=_~~=:~~9...___= i--'l6.J~?~.OO--'~~J
L,E~l,Q!!!!9._____,_._,_l..Lo~~!!..~E?-i,r.:!!!!!g--...J.-~~,635.QQ"----1--,..,,--!4..~3.J>_Q_..._..._..._,_j,.__,_~!Q~~:~Q...__J
! Mechanical I Pumper Plumbing & i ' 1 i
L-.--....---...------J He~!!Q,9..._,__......_.._L.,--Jl,Q!~~~.OO-,-,...J..1LQ..~,~Q..Q-,---....L.._......l~..1!~~?:,9._Q.,.,"'_.......J
L~!~~!d~~1 _..._JJiayes ElecJ!Lc__,_._,..J.____J1Q!~Q:9..Q__ ..-......_...14?Q:Q~____..._..._J,___~..1.1_!~~Q~..Q..Q..,_._.J
!__~~!room Accessorie~_LKu!!y' SuP-2!y,-~Q:....__l--...-~~!.~~-~:..Q.Q-..,--4-"--.-....,...,l9.....---,-_.L---...J~,!1~~j)SL..,_....l
i Concession Windows Iln House i ! I i
I & Accessories I i $6,400.00 I $0 I $6,400.00 I
i TOTALS I I $176,048.00 $10,498.00' $186,546,00 '
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (952) 447-4230 / Fax (952) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
I I
3. Funding for the additional $10,498.00 will be drawn from the Park Referendum balance in the Park
Dedication account.
4. The Mayor and City Manager are hereby authorized to execute documents prerequisite to
effectuate these change orders.
PASSED AND ADOPTED THIS 5TH DAY OF NOVEMBER, 2001.
YES
NO
Mader Mader
Ericson Ericson
Gundlach Gundlach
Petersen Petersen
Zieska Zieska
City Manager, City of Prior Lake