HomeMy WebLinkAbout98-73RESOLUTION 98-73
AUTHORIZING TIlE AWARD OF llID FOR TIlE CONgTRUCTION
OF ROAD, TRAIL, AND PARKING LOT IMPROVEMENTS IDENTIFIED IN THE
1998 PARKS CAPITAL IMPROVEMENT PROGRAM.
MOTION BY:
KEDROWSKI
SECOND BY:
PETERSEN
WHEREAS,
the following road, trails, and parking lot projects are scheduled for completion
in the 1998 Capital Improvement Program:
The Ponds Athletic Complex road, parking lot and trails
Memorial Park parking lot and trail
WHEREAS,
the City of Prior lake is committed to providing Trails, Parking Lots, and other
park amenities in accordance with the Comprehensive Park and Trail Plan, and
WHEREAS,
trails provide our residents the opportunity to enjoy our City Parks, and
WHEREAS,
trails are an essential link between neighborhoods and business areas, and
parks, and
WHEREAS,
parking lots provide off street parking for park users and reduce congestion on
City streets, and
WHEREAS,
the City's Capital Improvement Program scheduled this construction in 1998
and allocates funds therefore, and
WHEREAS,
pursuant to the call for bids for concrete curb and gutter and bituminous for
these projects, the following bids were solicited, received, and tabulated as
follows:
Concrete Curb & Gutter
VENDOR
Jim Clausen Constr.
McNamara Contractors
Expert Asphalt
Barber Construction
BID AMOUNT
38,768.00
42,760.60
45,635.00
84,565.00
Bituminous
Valley Paving
McNamara Contractors
Vi-Con Inc.
Prior Lake Blacktop
Expert Asphalt
Barber Construction
84,399.60
87,854.25
99,795.00
107,670.55
139,166.25
181,275.00 and,
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
WHEREAS,
After analyzing the bids, the apparent lowest responsible bidder is Jim Clausen
Construction for concrete curb and gutter work in the amount of $38,768.00
and Valley Paving for bituminous work in the amount of $84,399.66
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
Minnesota, that award of bids for Road, Trails, and Parking Lot Improvement projects be
approved as set forth above.
FURTHER,
The City Manager is hereby authorized to return bid securities submitted with
the proposals to the vendors following the execution of contract; and,
FURTHER,
The Mayor and city Manager are authorized to execute the contract on behalf
of the City.
Passed and adopted this 15th day of June, 1998.
{ Seal }
YES NO
Mader X Mader
Kedrowski X Kedrowski
Schenck X Schenck
Petersen X Petersen
Wuellner X Wuellner
~City of Pri~q/ *
rs98cip2.doc