DISCUSSION: Introduction
This agenda report is intended to be the basis for discussion at the March 21
work session and City Council meeting.
The purpose of this agenda item is to propose a process which will encourage
complete and comprehensive City Council discussion of all salient issues
associated with preparing the 2012 Budgets and Capital Improvement
Program.
Hi story
Last year's budget process began on February 1, 2010. It contemplated 12
work sessions on budget - related issues. My records do not confirm whether all
scheduled sessions actually took place. The important point is that at the
conclusion of the budget process not everyone was satisfied with the process.
Therefore, the Finance Director and I have reviewed the process and propose
revisions in an attempt to address all Council concerns.
Current Circumstances
At our February 22, 2011 work session, the City Council discussed the 2012
budget process. Since that meeting, various issues have arisen which suggest
that further refinement of the process is needed so there is Council consensus
before we undertake this effort.
The process proposed for Council consider is the third page of this report. To
integrate this narrative with the proposed process, we have numbered each
step of both documents.
In an effort to tie various aspects of the budget consideration process together,
we propose the following: consolidate session topics, reduce the overall
number of work sessions and, in various cases, lengthened work sessions. By
providing for longer sessions it is our hope that the Council will be able to fully
discuss and deliberate on each critical issue before moving on to the next.
Consolidation of topics is intended to avoid some of the conceptual
fragmentation that may have occurred last year as well.
We also added some budget steps. Most notable is the identification of when
financial information is available to staff and when it should be available to the
City Council. (Step 1) This schedule would become an annual part of the
process. This work session will also facilitate a discussion of circumstances
that could have led or may lead to a surplus or deficit condition. (Step 1)
Included in Steps 3 and 4 is the opportunity to factor in any amendments that
were made to the 2030 Vision and Strategic Plan into the CIP and budget.
A discussion of benchmarks is also provided at the same time the Council
discusses the amended budget and again with the preliminary budget for the
coming year. (Steps 4 and 7)
Perhaps the single most important new step is the annual amendment of the
current year's budget at about mid -year taking into account changes in the
economy, revenues and expenditures to the extent possible. (Step 4) We
believe that this step will provide a better "launching pad" for the coming year's
budgeting process and help to mitigate against variances.
ISSUES: There are two alternative approaches to the budget / CIP adoption process.
The first approach is to schedule City Council review of each individual
element of the budget and CIP first so that the component parts of each
document could be considered one by one, much like building blocks. The
other approach is to focus on the big picture first, i.e. levy and use of reserves
to support the coming year's budget and CIP.
We are recommending the second approach as it became clear that we would
be unable to have elements such as the Facilities Management Plan,
Technology Plan, Personnel Plan, and Parks Study done in time to provide for
an orderly process using the first approach. This may be the approach the
Council wishes to consider for the 2013 budget, however.
It is expected that the 2030 Vision and Strategic Plan will be updated by June
6. These activities will be scheduled on non -City Council nights but an
additional workshop may need to be added to completely integrate this
process with the financial process if we are unable to complete this process by
June 6.
In terms of length of work sessions, the Council should weigh in on the
proposed four 2- and -a- half -hour work sessions. If conducted as we have done
in the past, this will mean that the Council meeting following these four
meetings will begin at 7 p.m. rather than 6 p.m. There is also a four -hour
consolidated workshop proposed on July 5. 1 do not anticipate that there would
be a Council meeting that evening.
FISCAL IMPACT: Collectively, the expenditures and revenues reflected in the budget and CIP
constitute the greatest financial impact upon our residents. Therefore, the
proposed process is to assure that adequate time is provided to the City
Council to thoroughly deliberate both the budget and CIP so the final products
reflect input by fully informed City Council members.
ALTERNATIVES: 1. Review the proposed process and discuss the changes at the work
session.
2. Provide staff direction regarding desired changes at the City Council
meeting.
RECOMMENDED Alternatives 1 and 2.
MOTION:
2
2012 Budget Dates and Topics Discussion
March 21, 2011
Step
Date
Hours
Discussion Topics
Adoption
1
Mon,
2.5
Comprehensive Financial Management Policy
Apr 18
Apr 4
-
Reserve Balances for:
• General Fund
• Water Fund
• Sewer Fund
Availability of Financial Information
n/a
2
Mon,
1.5
Long Range Financial Planning
n/a
Apr 18
Use of Reserves
• Maximum Levy
3
Mon,
2.5
Draft CIP:
Aug 15
Jun 6
Transportation Plan
• Water Operating Plan
• Sewer Operating Plan
• Equipment Replacement Plan
• Park Equipment Replacement Plan
• 2030 Vision and Strategic Plan
Does NOT include Facilities Management
Plan or Technology Plan
4
Mon,
2.5
Benchmark Discussion
n/a
Jun 20
Amended 2011 Budget
Jul 5
• 2030 Vision and Strategic Plan
5
Tues,
4
Facilities Management Plan
Aug 15
Jul 5 **
Technology Plan
Aug 15
Personnel Services Plan
Aug 15
** No City Council meeting this evening.
6
Mon
2.5
Park Analysis
Aug 15
Aug 1
7
Mon
1.5
Preliminary 2012 Budget with additional
Sept 6
Aug 15
benchmark presentation