HomeMy WebLinkAbout99-69
RESOLUTION 99-69
RESOLUTION AUTHORIZING THE AWARD OF BID
AND EXECUTION OF CITY'S STANDARD CONTRACT
FOR THE PURCHASE AND INSTALLATION OF MILLWORK
FOR THE LIBRARY/RESOURCE CENTER
MOTION BY: Schenck
SECOND BY: Wuellner
WHEREAS,
On May 17, 1999 the City Council approved the plans and specifications for the purchase and
installation of millwork for the Library/Resource Center and authorized the solicitation of bids,
and,
WHEREAS,
the bid opening was conducted on Tuesday June 15, 1999 and the following is the bid tabulation:
Contractor
Fulco Construction Inc.
Ron's Cabinets
Millcraft
J.S. Cates
Bid Amount
$91,900.00
$117,322.00
$125,685.00
$178,000.00
and,
WHEREAS,
the apparent lowest responsible bidder is Fulco Construction Inc. , and,
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, as follows:
1. The bid for the purchase and installation of millwork for the Library/Resource Center is hereby awarded to
Fulco Construction Inc. for a total cost not to exceed $91,900.
2. The funds for such improvements will be drawn from the Parks and Library Referendum Funds ($36,700) and
the remainder from interest earnings which have not been programmed.
3. The City Manager is hereby authorized to return bid securities submitted with the proposals to the vendors
following the execution of contracts.
4. The Mayor and City Manager are authorized to execute the City's standard contract on behalf of the City.
Passed and adopted this 19th dpy of July, 1999.
YES
NO
Mader X Mader
Kedrowski X Kedrowski
Schenck X Schenck
Petersen X Petersen
Wuellner X Wuellner
{Seal}
~g~Q Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 1 Ph. (612) 447-4230 1 Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER