CITY COUNCIL AGENDA REPORT
:6ril17,2000 "2!i
PAUL HOKENESS, PARKS AND RECREATION DIRECTOR
CONSIDER APPROVAL OF RESOLUTION OO-V/AUTHORIZING THE
PREPARATION OF PLANS AND SPECIFICATibNS FOR TRAILS AND
PLAYGROUND EQUIPMENT AS IDENTIFIED IN THE 1999 AND 2000
CAPITAL IMPROVEMENT PROGRAM
History:
This item originally appeared on the February 22, 2000 agenda but was
deferred until the Referendum Status Report was provided to the City
Council (See Agenda Item 88).
Each year the City Council adopts the Capital Improvement Program
which involves funding for various park improvement projects. To assure
that the Council is aware of and supportive of our major park
improvement efforts, we are seeking approval to prepare plans and
specifications for park projects programmed for 1999 and 2000.
The 1999 and 2000 Capital Improvement Programs contains a total of
$287,750.00 in park improvement projects. Of this, $212,750.00 is for
playground equipment and trail projects. The remainder, $75,000.00 is
for miscellaneous improvements and capital park appurtenant equipment.
This agenda item will focus on the playground equipment and trail
projects. Agenda item 90 addresses the miscellaneous improvements
and capital appurtenant equipment expenditures.
The 1999 Capital Improvement Program identified two parks which were
slated for new playground equipment as well as trails at Knob Hill park
and Crest Avenue. The two parks which were to receive playground
equipment in 1999 were Oakland Beach and Sand Point. The storm of
1998 destroyed the playground equipment at Oakland Beach. In 1998
we ordered new equipment for the park at the Wild's but since this park
wasn't ready for development the Council authorized the installation of
the equipment at Oakland Beach. Having new equipment at Oakland
Beach left us with only Sand Point for 1999 equipment installation. We
have discussed the park development of the Wild's with the developer
but have not been successful in finalizing the plans, so we will be
proposing that the Wild's playground equipment be included in the 2001
C.I.P.
1626~1~'@'\~~M~9fJ€?~f~cPrior Lake, Minnesota 55372-1714 / Ph, (612) 447-4230 / Fax~tffZ) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
<-'-<-."--<-'<.'~.<-'7--"-
T
Due to the schedule of the park maintenance crews who were busy with
the new Library/Resource Center and Lakefront Park we were unable to
provide the labor necessary for the playground and trails. Typically park
maintenance crews do all of the grading and prep work for the
playgrounds including, hauling of sand, base work for the curbing, and
finish landscaping and sodding. With the trails we do the grubbing,
grading, and base work
Park maintenance crews completed all of the landscaping at the
Library/Resource Center and graded and based many of the trails in
Lakefront park, They also did all of the seeding and tree planting in
Lakefront park as well as built the two hockey rinks and hauled the sand
and fiber for the playgrounds.
Current Circumstances:
The Capital Improvement program includes funds to install playgrounds
at Sand Point, Fish Point, Knob Hill, Raspberry Ridge, and Sunset parks.
The C.I.P. also includes funds to develop trails at Glynwater.
The following is a breakdown of the cost estimates contained in the
Capital Improvement Program for the 1999 and 2000 playground
equipment and trails:
PLAYGROUND EQUIPMENT
1999 Sand Point
2000 Fish Point.
2000 Knob Hill
2000 Raspberry Ridge
2000 Sunset
$25,750.001
$25,750.00
$25,750.00
$25,750.00
$25.750.00
$128,750.00
The 1999 C.I.P. included $44,000 for two parks. The Wilds park is to be
rescheduled for 2001 therefore only $25,750.00 will be used this year.
The increase in cost per park is due to council direction that resilient
surfaces be done at the same time new play equipment is installed.
This total includes the cost of the concrete curbing, resilient surfacing,
and sand. The cost estimate for the equipment alone is $20,000.00,
installation included.
TRAILS
1999 Crest Avenue
1999 Knob Hill
2000 Glynwater
$44,000.00
$18,000.00
$22.000.00
$84,000.00
The 1999 CIP included $44,000 for two parks. The Wilds park is to be rescheduled for 2001. Therefore,
only $25,750.00 will be used this year. The increase in cost per park is due to Council direction that
resilient surfaces be done at the same time new play equipment is installed,
k:\paul\agden,rep\cipexpen,doc
Page 2
The trail at Crest Avenue is a reconstruction of the existing trail. The trail
is approximately 20 years old and in very poor condition. The trail is 6
feet wide and we would replace this trail section with a standard 8 foot
trail. This reconstruction would be from County Road 42 to Shore Lane.
The trail at Knob Hill Park is a new trail which will meander through the
new park and connect Carriage Hills Parkway with Hummingbird Trail.
The trail at Glynwater is also an internal park trail which will provide
access to the park within the development as well as provide a
connection to Island View Park. These trail sections are identified in the
Comprehensive Plan (attached).
The Issues:
The bidding of the trails is typically not complicated as it is easy to
quantify the length of the trails and the quantities needed for their
construction. The specifications for bituminous and base materials is not
very complicated and the mix is typically the same regardless of which
paving contractor is used.
As we know from past experience the bidding of playground equipment is
more complicated as the various manufacturers have different
specifications for each part of their equipment Le. pipes, clamps, decks,
slides, swings, coatings, etc.. The warranties vary and the installation of
the equipment differs from one vendor to the next.
The intention would be to use the input received from the City Council at
the February 10, 2000 workshop to guide us in the preparation of
specifications, analysis and award.
Conclusion:
Staff is requesting that the Council approve the attached resolution so
that we may prepare the plans and specifications for the playground
equipment and the trails for Council approval. The plans and
specifications will be presented to the City Council for approval prior to
bidding.
Design and plans for these projects will be done in-house as a
cooperative effort between the Parks and Engineering Departments. By
doing so, the City will save on design costs and allow a full commitment
of the funding to construction costs. The design scope of these projects
is small and the work can be done efficiently in-house. Most of the rough
grading and back filling will be performed by Parks Maintenance staff. In
addition, the construction management and field work will be done in-
house as well.
FISCAL IMPACT: Budget Impact:
The funds for these projects will be drawn from the Parks portion of the
Capital Improvement Program. The project cost estimates for the
k: \paul\agden,rep\cipexpen,doc
Page 3
. -., -
T
ALTERNATIVES:
RECOMMENDED
MOTION:
REVIEWED BY:
k:\paul\agden,rep\cipexpen,doc
playground and trails is $212,750.00. The Park Capital Program
currently has a balance of $549,057.00.
1. Approve Resolution DO-XX authorizing the preparation of plans and
specifications for playground equipment and trails.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason.
Motion and second to approve Resolution DO-XX authorizing the City
Manager to prepare plans and specifications for playground equipment
at Sand Point, Fish Point, Knob Hill, Raspberry Ridge, and Sunset Parks
and trails at Crest enue, Knob Hill, and Glynwater Parks.
Page 4
zj
RESOLUTION OO~
RESOLUTION AUTHORIZING THE PREPARATION OF PLANS AND SPECIFICATIONS
FOR TRAILS AND PLAYGROUND EQUIPMENT AS IDENTIFIED
IN THE 1999 AND 2000 CAPITAL IMPROVEMENT PROGRAM
WHEREAS,
WHEREAS,
WHEREAS,
WHEREAS,
MOTION BY:
SECOND BY:
the following neighborhood parks are scheduled to receive new playground
equipment as listed in the 1999 and 2000 Capital Improvement Program
Sand Point
Fish Point
Knob Hill
Raspberry Ridge
Sunset, and
the following trails are scheduled for construction as identified in the 1999 and
2000 Capital Improvement Program
Crest Avenue
Knob Hill
Glynwater
the City of Prior Lake is committed to providing recreational activities for people of
all ages, and
playgrounds and trails provide for physical and mental stimulation and are
considered a high priority in the development of the Prior Lake park system.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA,
that staff is authorized to proceed with the preparation of plans and specifications for the parks and
trails identified herein.
Passed and adopted this 17th day of April, 2000.
YES
NO
Mader Mader
Ericson Ericson
Gundlach Gundlach
Petersen Petersen
Schenck Schenck
{Seal} City Manager, City of Prior Lake