HomeMy WebLinkAbout12-116 Boudins Phase II Change Order 1
4646 Dakota Street SE
Prior Lake, MN 55372
R ESOLUTION 1 2 - 116
A RESOLUTION APPROVING A CHANGE ORDER FOR THE BOUDINS PHASE II IMPROVEMENT
PROJECT (CITY PROJECT #12 - 01 1)
Motion By: Hedberg Second By: Hedberg
WHEREAS, Pursuant to the City’s standard construction contract with Northwest Asphalt f or the
Boudins Phase II Improvement Project (City Project #12 - 01 1) which includes sanitary
sewer, water main, storm sewer, aggregate base, concrete curb and gutter, bituminous
pavement, turf restoration and appurtenant work; and
WHEREAS, The lowest bid w as above the engi neer’s estimate ; and
WHEREAS, City staff was directed to move forward with the use of reclaimed aggregate base as a
cost saving measure. The use of reclaimed onsite material will save $36,500.70 ; and
WHEREAS, The City Engineer recomm ends acceptance of the change order and reduction of the
construction contract amount with Northwest Asphalt to $2,250,695.28.
NOW THEREFORE , BE IT HEREBY RESOLVE D BY THE CITY COUNCI L OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. Change order #1 with a reduction of $36,500.70 from the construction contract is approved.
3. The construction contract with Northwest Asphalt is revised from $2,287,195.98 to $2,250,695. 28.
4. The unit price for aggregate base reclamation and placement is agreed t o be $5.90/SY .
PASSED AND ADOPTED THIS 23rd DAY OF JULY 201 2 .
YES NO
Myser X Myser
Erickson A Erickson A
Hedberg X Hedberg
Keeney X Keeney
Soukup A Soukup A
______________________________
Frank Boyles, City Manager