HomeMy WebLinkAbout5K Purchase Easement Jetting Machine O � PRlp�
ti �
V � 4646 Dakota Street SE
Prior Lake. MN 55372
�jNtvESO�
CITY COUNCIL AGENDA REPORT
MEETING DATE: April 22, 2013
AGENDA #: 5K
PREPARED BY: Katy Gehler, Public Works & Natural Resources Director
PRESENTED BY: Katy Gehler
AGENDA ITEM: Consider Approval of a Resolution Authorizing the Purchase of an
Easement Jetting Machine
DISCUSSION: Introduction
The purpose of this agenda item is to seek City Council approval for the re-
placement of the following the easement jetting machine (Unit #770).
Hi StOry
The City owns and maintains approximately 113 miles of sanitary sewer pipe
to collect and transport waste from Prior Lake. This pipe can range in age and
material from older "bell and spigot" vitrified clay pipe to more modern sealed
joint plastic pipe. Due to the material and joint type, clay or concrete pipe is
more susceptible to cracking, root intrusions, and obstructions which ultimately
impact the flow capacity and longevity of the pipe.
To maintain flow in the pipe and limit the liability for sewer backups, the city
regularly jets and televises sewers. Reduction of backups also limits the po-
tential for overflows and accidental releases of sewage both overland and into
water bodies. Jetting can also act as a visual type of inspection of the pipe
condition. Root intrusions and offsets can be felt with the jetting tip, while
wash water will show gravel bedding or soils entering the pipe through cracks
or holes. Repairs can then be completed before complete failure of the pipe
occurs causing an emergency situation and potentially added liability to the
city.
The League of Minnesota Cities completed an analysis of sewer backup
claims in 2008. The overview of the findings is below. The entire report is at-
tached.
�V81VIeW
Sewer backup claims comprise a significant portion of liability costs for the League of Min-
nesota Cities Insurance Trust (LMCIT). The average cost per claim of a sewer backup has
increased steadily since 2000. In order to better understand how cities might prevent sewer
claims, LMCIT recently conducted an analysis of sewer backup claims.
The claims data clearly indicate that the most common reason for sewer backups was an
obstruction in the sewer line. It is also evident that issues related to maintenance and in-
spection were the primary reason for city liability in sewer backup claims. In addition, we
know that some of the most costly claims, though occurring with less frequency, are those
related to lift station problems and design/consfruction issues. What the study data does not
appear to reveal is any particular claim pattern or trend on an annual basis that provides
insight into the reason for rising costs. It seems that regardless of the cause of the sewer
backup or reason for city liability, the average cost of sewer backups has increased as a
whole over the past several years.
As indicated in the �ndings below, the primary reason for the cause of sewer backups as
well as the associated liability are remarkably evident in the study results. LMCIT staff was
somewhat surprised that the claims data painted such a clear picture. But even more sur-
prising, perhaps, were the causes that did not rise to the top of the list: Weather related in-
cidents like extraordinary rainfall or lift station failure due to weather events were not a ma-
jor cause of sewer backups. And while aging infrastructure is an ongoing concern for cities
throughout the state, physical condition of the sewer line was not quite as notable a cause
of sewer backups as we anticipated.
Here are the main findings:
• By far, the most prevalent and expensive cause of sewer backups among paid
claims was an obstruction in the line.
• The second most prevalent and costly cause of sewer backups was lift station
problems.
• Backups caused by the design/construction of the system had the second larg-
esf inedian cost per claim (damages).
• Sewer backup claims with multiple claimants were a great deal more costiv than
those with a single claimant.
• Issues related to maintenance and inspection were the primary reason for city li-
abilitv in sewer backup claims.
• There was no difference in the cause of sewer backups for claims in which the city
was liable (paid claims) and for claims in which the city was NOT liable (zero-pay
claims).
Much of the 113 miles of sanitary sewer is located in the City's Right-of-way
which allows staff to readily access manholes for routine and emergency
maintenance utilizing our large jet-vac truck. The truck has a reach of approx-
imately 300' from any roadway.
However, approximately 10.3 miles lies in side yard or backyard easement ar-
eas that is not accessible with the large jetting truck. To provide some typical
examples, Portions of the Vierling property contain such lines, there is sewer
along the lakeside on the Bolger/Shepherd property and the same is true
along Northwood Road to mention a few.
What is similar about these sewer lines is they are most often located on
grades and have limited access through easements on private property. Very
few are served by bituminous trails or other access roads which is important
considering the weight of the jet-vac truck. These lines also tend to be the old-
er clay or concrete pipe that is more susceptible to cracking and offsets mak-
ing ideal conditions for root growth and infiltration from the surrounding high
ground water levels. The attached map shows the easement sewer locations.
n
To complete maintenance of these sewers, the city acquired an easement jet-
ting machine in 1992. The machine attaches to the jetting truck and extends
the reach of the lines 600'. In addition it is sized to access these narrow, land-
scaped areas that are not accessible with a full size vehicle.
Current Circumstances
The Equipment Replacement Plan is a tool which provides funds which are
likely to be needed for vehicle and equipment acquisitions and refurbishing.
Annually the plan is reviewed and updated based on the current condition of
the City's fleet and approved as part of the CIP and budgeting process. As
per state statute, all purchases over $20,000 are brought to the Council for
final purchase authorization.
For 2013 there are four pieces of equipment that are scheduled to be replaced
that require council approval:
1. 1999 Ford F350 w/ Plow (Unit #457) Authorized April 8, 2013
2. 1999 Ford F350 w/ Plow (Unit #543) Authorized April 8, 2013
3. 1999 Ford F350 w/ Plow (Unit #545) Authorized April 8, 2013
4. 1990 Serco Extend-a-Jet (Unit#770)
Prior to the recommendation for replacement or addition of vehicles and
equipment, the following criteria are analyzed to determine whether a vehi-
cle/equipment should be replaced, how and with what type:
1. Vehicle and Equipment Refurbishing
2. Lease, Rental and Borrowing Options
3. Equipment Zero Value Operations
4. Alternative Fuels
5. Vehicle and Equipment Scheduling Procedures
6. Equipment Partnerships
7. Investigation of Used vs. New
8. Alternative Annual Cost Analysis
Our analysis is attached. Based upon our analysis, the council is being asked
to authorize replacement of the easement jetting machine.
Conclusion
Based on the City's detailed vehicle and equipment needs and financial analy-
sis, staff is recommending the purchase of the following:
1. 2011 JAJ-600WH Easement Jetting Machine (Unit #770)
ISSUES: The attached analysis considers each piece of equipment in the following cat-
egories:
1. Refurbishing
2. Lease/RentalOptions
3. Zero Value Operations
4. Alternative Fuel Analysis
5. Equipment Utilization
6. Equipment Partnerships
7. Used Equipment Options
8. Alternative Annual Cost Analysis
FINANCIAL The Equipment Replacement Plan programmed and the Revolving Equipment
IMPACT: Fund Budgeted $49,862 for the replacement of the easement machine. The
replacement cost for the proposed vehicles is $48,996.84 which is $865.16
less than budgeted.
ALTERNATIVES: 1. Approve a resolution authorizing the purchase of the proposed equipment
and trade in the existing equipment as detailed in this report.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direc-
tion.
RECOMMENDED Alternative No. 1
MOTION:
�
O � PRIp�
ti �
4646 Dakota Street SE
`�tNx�so'� Prior Lake, MN 55372
RESOLUTION 13-xxx
A RESOLUTION AUTHORIZING TRADE IN AND REPLACEMENT OF 1990 SRECO EXTEND-A-JET
EMSP-6 (UNIT 770) AND PURCHASE OF ONE 2011 JAJ-600WH EASEMENT MACHINE FROM
MACQUEEN EQUIPMENT
Motion By: Second By:
WHEREAS, Each year the City Council adopts �an Equipment Replacement Plan as part of the Capital
Improvement Program (CIP); and
WHEREAS, The 2013 Equipment Replacement Plan contemplates the replacement of Unit #770, the
1990 Sreco EMSP-6; and
WHEREAS, The 2013 Equipment Replacement Plan programmed $49,862 for the replacement of this
equipment; and
WHEREAS, A detailed needs and financial analysis has been completed and was included in the
agenda report; and
WHEREAS, Quotes were received through the State Purchasing Program and from local vendors.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. Staff is authorized to trade-in the 1990 Sreco EMSP-6 (Unit #770)
3. Staff is authorized to purchase one 2011 JAJ-600WH Easement Machine from Mac Queen for a cost
not to exceed $48,996.84
4. Funds will be drawn from the Revolving Equipment Funtl account # 410-49450-580
PASSED AND ADOPTED THIS 22�d DAY OF April 2013.
YES NO
Hedber Hedber
Keene Keene
McGuire McGuire
Morton Morton
Souku Souku
Frank Boyles, City Manager
o�
j,EAGUE oF CONNECTING & INNOVATING
MINNESOTA SINCE 1913
CITIES
Risk Management Information
SEWER BACKUP CLAIMS ANALYSIS: 2003 to 2006
Overview
Sewer backup claims comprise a significant portion of liability costs for the League of Minnesota
Cities Insurance Trust (LMCIT). The average cost per claim of a sewer backup has increased
steadily since 2000. In order to better understand how cities might prevent sewer claims, LMCIT
recently conducted an analysis of sewer backup claims.
The claims data clearly indicate that the most common reason for sewer backups was an
obstruction in the sewer line. It is also evident that issues related to maintenance and inspection
were the primary reason for city liability in sewer backup claims. In addition, we know that some
of the most costly claims, though occurring with less frequency, are those related to lift station
problems and design/construction issues. What the study data does not appear to reveal is any
particular claim pattern or trend on an annual basis that provides insight into the reason for rising
costs. It seems that regardless of the cause of the sewer backup or reason for city liability, the
average cost of sewer backups has increased as a whole over the past several years.
As indicated in the findings below, the primary reason for the cause of sewer backups as well as
the associated liability are remarkably evident in the study results. LMCIT staff was somewhat
surprised that the claims data painted such a clear picture. But even more surprising, perhaps,
were the causes that did not rise to the top of the list: Weather related incidents like extraordinary
rainfall or lift station failure due to weather events were not a major cause of sewer backups. And
while aging infrastructure is an ongoing concern for cities throughout the state, physical condition
of the sewer line was not yuite as notable a cause of sewer backups as we anticipated.
Here are the main findings:
■ By far, the most prevalent and expensive cause of sewer backups among paid claims was
an obstruction in the line.
■ The second most prevalent and costly cause of sewer backups was lift station problems.
■ Backups caused by the design/construction of the system had the second largest median
cost per claim (damages).
■ Sewer backup claims with multiple claimants were a great deal more costiv than those
with a single claimant.
■ Issues related to maintenance and inspection were the primary reason for city liabilitv in
sewer backup claims.
' The median is the middle of a distribution: half the scores are above the median and half are below the median. The
median is less sensitive to extreme scores than the mean and this makes it a better measure than the mean for highly
skewed distributions.
Sewer Toolkit
Other Resources - 27
■ There was no difference in the cause of sewer backups for claims in which the city was
liable (paid claims) and for claims in which the city was NOT liable (zero-pay claims).
Background
The Property/Casualty (P/C) projected ultimate losses for the years 2000 to 2005 are estimated to
be $22 million a year on average. From 2000 to 2005, liability comprised nearly half of P/C loss
costs—approximately 48 percent.
Among liability claims, there
Percent of Claimants and Incurred Loss Costs are six categories that
by Type of Liability: 2000 to 2006
comprise a majority (80 to 85
ss.o�� ---- — - percent) of loss costs. These
30 °°�° types of claims include sewers,
�s�o� � � land use, employment, police
��
zo.o� - -- - liability, administrative errors
,so� --- ----- & omissions, and streets &
, o o,� _—_ __ _ sidewalks. Incurred loss costs
s.o � —_ ___ _ include the expenses (e.g.,
o.o�ro legal) and damages that are
Sewer BU & Land Use Employment Police All Other Ar�min E& O sveets paid or reserved for the claim.
NF (All)
■ Percent of Loss Costs 0 Percent of Claimants
Average Cost Per Claim for Sewer BU Claims:
2000to 200� Approximately 13 percent of
LMCIT's total liability loss
bi2.000 - - costs are attributed to sewer
s�o.000 backup claims. With the
$s,000 �_- �" exception of 2005, loss costs
: ,�,��.-----'"" � since 2000 have been $1,600
as,000 "" per claimant, on average.
$a.000 __ - �� Average claim costs in 2005
�z,000 � were higher as a result of
several multi-claimant claims
b with large dollar losses.
00 '01 '02 '03 '04 'OS '06 'D7
Avg Cost Per Cleim °-°-- Trond Lin•
Sewer Toolkit
Other Resources - 28
Costs associated with sewer
Number of Claims by Accident Year and Claim Status: baCkUp C�11ri1S h1Ve b0eri
zooa to zoos increasing steadily over the past
400 -- �----- �-- -- �� several years. The data does not
35o su est that the number of claims
soo — -- __ gg
2so — -- --- per year increased substantially
200 over the study time frame. Nor
� 50 � � has the percentage of claims
�< ,
� 50 �� �� �� �� resulting in liability increased.
o �� �"�f The gaph to the left shows the
2003 2004 2005 2oos proportion of "closed, with
■ Closed, With Damages ❑ Closed, Without Damages � Open Claims damages" remained fairly constant
from 2003 to 2006. Overall,
approximately 40 percent of claims each year close with damages incurred.
We believe there are a couple of likely reasons for the ongoing increase in damage costs. One
probable reason is that an increasing number of homeowners use their basements as added living
area. These "finished" basements are likely to contain items of higher value than those things we
have seen stored in basements in year's past. Another possibility is that society in general is more
aware of the potential health issues associated with mold in one's home. As the need for more
rigorous cleaning and replacement of certain materials following a sewer backup increases, the
costs associated with these activities will continue to increase as well.
Research Design
The purpose of this project was to gain a better understanding of how and why sewer backups
occur, in order to inform loss control efforts to limit the number and cost of claims. LMCIT staff
reviewed more than 1,200 sewer backup claim files dated from 2003 to 2006. All sewer back-up
claim files from this time period were reviewed, regardless of the outcome of the claim. Of the
claim files reviewed, costs were incurred in 602 of the claims (i.e., paid claims for which the city
was determined to be liable) and no cost was incurred for 637 claims (i.e., zero-pay claims for
which the city was determined to NOT be liable).
Two key pieces of information were collected from the sewer backup claim files: the rip marX
cause of the sewer backup as documented in the claim file (e.g., root growth, lift station issues,
system design/construction issues, etc.); and the rip marX reason the city was liable as
documented in the claim file (e.g., inadequate maintenance/records, city response, known system
deficiencies, etc.). This information was obtained from the online claim description and/or the
paper claim files.
Sewer Toolkit
Other Resources - 29
Findings
1. By far, the most prevalent and expensive cause of sewer backups among paid claims tivas an
obstruction in the l ine.
Percent of Claims and Costs by Primary Cause of the Sewer BU for Paid Claims: S1Xty-t}1P00 ]�el'Cellt
zoos to zaos (63.3%) of paid sewer
�o.o . __ _az..�.__._______�.� backups from 2003 to
so.o 2006 were caused by an
so.o -- obstruction in the line.
40A -- -- ;
�� ; --
so.o �°�� ---- � The different types of
zo.o obstructions that caused
�o.o �� ��' sewer backups included
Obstrudion in the lines Liit station pro6lem Designlconsiruction of F�traordinary rainfall Other rOOtS� foreign objects,
ihe system concrete and sand, etc.
o Percent of Claims � Percent of Costs
2. The second most prevalent and costly caa�se of sewer backups tivas lift station problems.
Sewer backups caused by lift station problems occurred with considerably less frequency and were
less costly overall compared to backups due to obstructions. Median claim costs (damages only)
for backups caused by lift station problems, however, were the most expensive at nearly $6,000
per claim. Furthermore, median claim costs for lift station backups were nearly three times as
expensive as those caused by obstructions ($2,312 per claim). Lift station problems were the
cause of sewer backups in 15.3% of the paid claims. The total incurred cost for backups caused by
lift station problems was $l.l million (18.8%).
There were several different sub-sets of lift station problems captured in our study including
weather related problems, equipment failures, and other lift station problems. Lift station
problems attributed to equipment failure was the largest sub-category. Specifically, equipment
failure at a lift station was the specified cause for 80% of backups in the lift station category.
3. Backups caused by the design/construction of the system had the second largest median cost
per claim (damages).
Backups caused by the design/construction of the sewer system occurred with the least frequency.
However, the median claim cost (damages only) for backups of this nature was the second greatest
at nearly $4,000 per claim.
Sewer Toolkit
Other Resources - 30
4. Setiver backup claims with multiple ciczimants were a great deal more costiv than those with a
single claimant.
Median Cost Per Claim By Cause of Back-Up and Type of Claim: The pr11111Cy TT1e�lSUCe USeC� f01'
zoos �o Zoos this sewer backup study was
s2oo,o00 — - --- — — - — -- —
the claim. The claim
$,so,000 represents either a single
$,so,000 claimant or a group of
$,ao,000 � �;, claimants represented by a
$,zo,000 —� "` - � single claim. A claimant is an
$,00,000 -—--- «' individual who has filed a
Sao,000 ------- � �
�� claim against the city.
$so,000 '�
Although the majority of the
$ao,000 data collected for this study
$�o,000 � �� � was claim-based, we did
$o
Obstruction LiftStatlon DesigN &traordlnary Other Total �,Xll��j'e a'dh"]'dQe C�S't5' bV
Construction Rainfall Y b .7
comparing single claimant
m Single-Claimant Claim � Multi-Claimant Claim claims to multiple claimant
claims in the primary cause
categories. The data indicates that overall, multiple-claimant claims are considerably more
expensive than single-claimant claims regardless of what caused the backup.
Taking this one step further, the findings tell us sewer backups from lift station issues or
design/construction of the system result in very costly claims. If we consider that, in general,
claims related to lift stations and system design/construction are likely to impact a number of
people and therefore result in multiple claimants, it seems logical that median claim costs for lift
station and system design/construction claims are some of the highest. In addition, median claim
costs for the extraordinary rainfall category are extremely large due to several severe storm events
which triggered four sewer back-up claims with multiple claimants who experienced significant
amounts of damage.
5. Issues related to maintenartce and inspection were the primary reason for city liabili in
sewer backup claims.
Problems associated with the maintenance and inspection of sewer lines were the primary reason
for city liability in 55.3% of paid claims. Total costs incurred due to maintenance and inspection
issues were $2.4 million (40.7%).
While staff certainly anticipated maintenance and inspection would be found among the top
reasons for city liability, the extent to which maintenance and inspection issues played out in the
data was unexpected. City liability due to lift station issues was of note, but again, not at the level
we predicted. One of the issues staff watched closely throughout the study included liability
related to city response to a sewer backup. We found that liability associated with this category
was minimal.
Sewer Toolkit
Other Resources - 31
6. There was no d�erence in the cause of sewer backups for claims in which the ciry was liable
(paid claims) and for claims in tivhich the city was NOT liable (zero pay claims).
Sewer backups in Minnesota appear to be attributable to the same types of "causes" regardless of
whether the city was found to be liable for the backup. That is, we found little difference in the
cause of backups regardless of whether the claim had incurred costs. Zero-pay claims, ar those for
which the city was determined not to be liable far the backup, were also primarily caused by an
obstruction in the line. Nearly 67% of backups for which the city was not liable and no damages
were paid can be attributed to an obstruction in the line, compared to 66% of paid claims.
The above piece of information is perhaps the most confounding in the entire study. It begs the
question, "Why were cities liable in some cases and not in others?" The most likely answer is that
even though the sewer backup occurred, the city in question probably had reasonable policies and
procedures in place and followed them leading up to and after the backup. As such, the city was
not liable because it had the proper documentation and procedures in place and actually followed
them.
Plan of Action
We now know the primary reason for sewer backups and for city liability related to sewer backups
for claims filed from 2003-2006. LMCIT staff believes that losses can be better controlled in both
of these areas by developing training and materials that will enable cities to: 1) establish the
policies and procedures needed for adequate maintenance and inspection of the city's sanitary
sewer system; and 2) to properly document actions such as maintenance, inspection and
communication to limit city liability.
Unfortunately, improved maintenance and inspection policies and procedures are unlikely to
reduce the number of claims resulting from lift station problems and design/construction issues.
To address this area of claims it will be necessary to work with cities from an operations
perspective. Next steps might involve conferring with city engineers and public works directors to
identify what cities are doing now and determine what they could do differently to prevent
backups as well as limit liability in this area.
For additional information, please contact Tracie Chamberlin, LMCIT Loss Control Manager, at
651-281-1210 or tchamberlin a,lmc•or� or Mandy Clemenson, RiskDataAnalyst, at 651-281-1272
or mclemensonn,lmc.org.
Mandy Clemenson 03/08
Sewer Toolkit
Other Resources - 32
�� `'
� �� ' � °.
� � � � �� �
�.,� �
�,, � � � °� ��
�,
r
m��e� - . � � _ _
,
� � � �� �� � ��
�:
� � - _ � �
� �
, ,, ' � � �
� f � - `, �� � �,,:
� � _ r, \\ � u e �.
I_ � ,_
. �
., y��E �
; �
.
v.
ss �
��a , �, r s -
e � ��
� - �,
f c� y ... ..�
. e `F . �. �� ' L� > r & ��
�
_ .- .. . � i F� � - 8 � � �
v n
. r . _
�' 2 : t ❑
�,� '
ti � � �
b ❑_� � c
... ��� ,,. � � '
�� � �,- , d_ ,� �r �
, _
s a�yeo . ; �< e � - � a �
= s�o,
� . �, � � �
� _ - - — � _
F � . > _
� . Aoa,s �a �, _ � d
m, : �
� � -, � o � ,
- �, � ° �
„
� � y�
. �
,
d o, � � ❑
- � � �
, 3_ , � d
y ;
m � . „ F.
. ,,..� � .
� _ � � � _
� .,, .
�� � �
.,.
� - ., a,.e�,se
�,a � �-
� . a� d a�_s= �
� ,�w `
� E _
� � :� � � , - _� -
e 6��A ��
i= _
�
� � _
s = �� a
�. � G o
�
.. # P e�Pn `' "NV ^ .. � .
31r�a�- � �� ~ N.. .� �I
n �
= � n 3 y
� � 2 = 3 i
n.
I i. , ,
. � c; y a ' �' c �� a : •�, � � � � _
; _
, �
e '
s � „ __ t
x s ` ' z ` �"
, � . _._ F � a. c �j - ..�.,.�. � '
. o � iow�� . ° �. �J
0
e t �f s ._ " ���
o m q
�
� c°` 5f ° •• `� �:
.
y �. b a� . ..
u i`
A u�
_ � "i�] ° P „ � a�' � �1 � �
�
. , ,� g —� � � �
„E,_ �� . � w� � � � : �
u __J �i � 't
� � ; �,
y �, � �.
. . "' e j � .. � . .
\ €
c�� � �`", - � ;
� F
s ;.� �
} :
; ,
; ��,.,. ,_ — , �
; � - �
� �
� �
�
� ' �
w —
E o �'
M ~ O
.�. c ......
� _� N I � � W E a
� m 6
J 3 ��/a �' � � ;
L � a ? '� m
d o
°� � aW� � ���ao- �
C O � W -' H c m � Z � N
; a ' c N ��� �a Q � � � p �
� c � � � � � � � � �
Q ` � ` > {0 F- ° N
` C /��kF x lL 0 � p 11J d p �
/� �Q � Q y� W J LL C.� J � °
U � }' s. J � � � I / �� U � .,,.. .. ... '
✓ �
�21) � �
o � � PRio� .
� � EQUIPMENT PURCHASE ANALYSIS
v � 4646 Dakota Street SE #77O EASEMENT MACHINE
Prior Lake, MN 55372
'ttj NNESp� P
�'�"'�.� � ' � � '� ,
1 `—�.,� t� �a � �"�'��
, : t �
¢�� � � � � , � ,�' _ .,, ��� ,, f .�
� $ c_� it.�w...�._. r'� �. .
' � '� � a„� .t,
,�� � ���� -�� � � fi�:
�� . �
� � ::
� �� � r �
�a�:�l��� ��� _ �:,�, ,., �
�%�� a� t� ,
fl/ � . �� � �i
���� � P � ;.
i� �
..o
X`� �' �
r��� � , � x
3� � , �
{ � , ., o �..,
.. ,� 70 n � � € i *'�*�.,
„ ; �
.
� , ��:
� . ��� '� �� �/
� w. - � � � ' �
; �r. � � , � �, ..� ,! .�-
. p . . :
s .�, , ._,. „�.e.
��s � „ � g � � a �
i �� : �' � ' ,.�y
�'r�r Sr t �.
` � �� ; � %3 i i � � � t ��
! S�tt3yj )� � .'R ���
,r, � � d �� .� � g ��'�� a � � s + j = '�i
f ��
� S ' �� �
� �,`�' Y ' ;��.'`��:,. � rk ��iD"� sa��s c. ��y �+'�.
'`!%' �� j ����� ' �� d � ' � f �� �� �, ' . �
//w��/� s+" � 3':�. :�:r�4�,1� .'
Unit #770 is utilized by utility staff to extend the functionality of the jetting truck for maintaining the
operational integrity of the sewer system. The jetting truck has a useful reach of about 300'. There are
about 10.3 miles of sewer in the city that is located in backyard easements along the lake or in low areas
that cannot be jetted using the large jetting truck. The easement machine allows for access to these
areas that are typically landscaped and more susceptible to damage by certain equipment..
The existing 1990 Sreco EMSP Easement Machine is 23 years old and has accumulated 1300 hours.
Due to its age, the machine has developed several mechanical issues including the hydraulic drive and
steering systems. Outside of the mechanical repairs needed, the machine has proven to have some
operational and safety deficiencies which has significantly limited its use.
1. High center of gravity — The machine is a wheeled style that has a high center of gravity. This
machine has been prone to rolling on the moderate slopes it must navigate to access the sewers.
2. Hydraulic overflows — The location of the hydraulic fluid input and tank allow spillage of fluid from
the machine on certain slopes.
3. Steering — The unit cannot be easily maneuvered and has been prone to damaging sodded
areas.
4. Rough terrain — Some of the terrain that must be accessed is rough or sandy areas. The wheels
do not allow easy access to this terrain.
Due to the challenges with the current style of machine, staff investigated a track style machine to
compare to the wheeled unit.
The track machine offers the following benefits:
1. Center of gravity — The center of gravity is lower with the track machine. In addition the tracks
can adjust from 34" wide to 46" wide allowing greater stability on steeper slopes.
Page 1 of 4
EQUIPMENT PURCHASE ANALYSIS
#77O EASEMENT MACHINE
2. Skid Style Steering – The skid style steering allows the tracks to be controlled independently for
greater ease of operation and maneuverability.
3. Ground Pressure – The unit has crawler type rubber tracks which disperse the load of the
machine across a greater area lowering the overall ground pressure significantly reducing the
potential for damage to homeowner yards.
4. Rough Terrain – The tracks can operate on rough and soft terrain.
5. Pressure Release – The unit is equipped with a water pressure gauge and relief valve at the
operator station to prevent damage to the hose and provide operator safety.
6. Auto Levelwind – The unit is equipped with a levelwind that allows for adjustment of the hose
during operation to most efficiently access the manhole and provides for operator safety when
winding the hose.
• ' .-;,-� d;� • o
•. i�� '�.;:
� J aJ-FOOR7-I
R'm•k Horse Easement JIac6lne
. _ WORK-HORSE _ _
� e»� .`� ,f
.. �'` ,
�� � , �
F � F
�.. '� �, :. � •...-- , . �
� � �
, � a4 '� ,� `�''��.
E'—� � � ,
t '�, r.�
� . , �
34" ; � " '� � � i �._. �', `�:�' � �
, ,-
( / / � 1 � 5 i t l
� R �h ` �� � ` ��S � F }� � Y
t i Y � � � :t .
� , 400 � , _ 1' � 30°
_� � + ' " �
b -rhe 9 inch �`ide tracks estend h} from 3� inches to 461nches.
-This increases the degree of angle or slope f►•om 17 degrees to 3U degrees. (See
dra«'in� abo��e)
-Tl�ls allo«s the unit to enter a 36 inch gate to reach a back ��urd easement and g1�•es
46 " the added staUlllh� to access easements in rough terrain ai�eas.
In accordance with the City's purchasing policy, bids were solicited through the State of Minnesota
Purchasing Program. Quotes were received from Flexible Pipe Tool Company representing Sreco and
MacQueen Equipment representing Sewer Equipment Company of America. The bids/quotes were as
follows:
Flexible Tool MacQueen
Vendor Pipe (State Bid)
State Bid
Model Sreco EMSP-6 JAJ-600
Wheeled Track
Price $39,577.00 $64,374.00
Trade-in $2,000.00 $3,500.00
Sub-total $37,577.00 $60,875.00
Tax $2,583.42 $4,185.16
Total $40,160.42 $65,060.16
Page 2 of 4
EQUIPMENT PURCHASE ANALYSIS
#77O EASEMENT MACHINE
A detailed eight step analysis is completed for the purchase of all replacement or new equipment. The
analysis below summarizes the results of this process.
I. Refurbishinq Analvsis:
The 1990 Sreco EMSP-6 (Unit #770) needs $24,400.00 in repairs to be retained and operational for
its intended use. Currently this unit is 23 years old and has accumulated 1300 hours. To refurbish and
extend the life expectancy of this unit is not cost effective.
Summary of Needed Repairs for the Existin 1990 Sreco EMSP-6
Needed Repairs Grand Total
Re airs/Parts
Replace Hydraulic Drive and Steering System $11,875.00
Mechanical Repairs $1,700.00
Replace wheels and outriggers $1,625.00
Replace Hoses $1,700.00
Subtotal for Parts $16,900.00
Labor $7,500.00
Total $24,400.00
II. Lease/Rental Options:
The easement jetter is a highly specialized piece of equipment with limited use. Due to the low
usage, staff explored rental and contracted services options. The City has about 18,000 I.f. of
sanitary sewer in easement areas that should be jetted each year. This work could be accomplished
in about 80 hours of work time.
Contracted Services — Staff explored the use of contracted services. Rates ranged from $1.35-$1.45
per linear foot of sewer. This equates to about $24,300 annually.
Rental - These machine are very rare, therefore we were not able to find a vendor with a rental unit in
Minnesota.
It also should be noted that this machine is used in emergency situations throughout the year. If
contracted services or rental were utilized, we would have limited access to a machine during
potential backups and overflows when time is of the essence.
III. Zero Value Operation:
This piece of equipment is beyond its life expectancy for its intended purpose and needs significant
repairs to remain safely in use. Initial repairs have been estimated at $24,400. In addition, the unit is
dated and will continue to have operational safety issues. At this time, the City will receive a trade-in
value of $3,500.00.
IV. Alternative Fuel Analvsis:
This piece of equipment operates on a 20 HP gas engine.
V. Equipment Utilization:
This piece of equipment has a highly specialized use forjetting sewers. However, staff also uses the
jetting equipment to address sedimentation in storm sewers and thaw frozen culverts and pipes
during the spring melt to alleviate flooding. Likewise, this piece of equipment can be used in
easement areas and other off road locations for similar uses. If the track machine is purchased, staff
will be able to access easement areas in both summer and winter conditions.
Page 3 of 4
EQUIPMENT PURCHASE ANALYSIS
#77O EASEMENT MACHINE
VI. Equipment Partnership:
The city contacted the cities of Savage and Shakopee and the SMSC to explore potential
collaborations. All entities responded that they have more limited easement jetting needs and are
able to address this maintenance with the equipment they currently own, therefore do not see an
opportunity for a joint venture at this time. Staff will continue to explore equipment partnerships with
our regional partners.
VII. Used Equipment Options:
Staff explored used equipment options. MacQueen Equipment has a JAJ-600WH (track style)
demonstration unit available for sale. The unit would come with the same full one-year warranty as a
new machine. The full cost comparison is shown below.
Flexible Tool MacQueen MacQueen
Vendor Pipe (State Bid) �Demo Unitj
State Bid
Model Sreco EMSP-6 JAJ-600WH JAJ-600WH
Wheeled Track Track
Price $39,577.00 $64,374.00 $49,345.00
Trade-in $2,000.00 $3,500.00 $3,500.00
Sub-total $37,577.00 $60,875.00 $45,845.00
Tax $2,583.42 $4,185.16 $3,151.84
Total $40,160.42 $65,060.16 $48,996.84
VIII. Alternative Annual Cost Analvsis
Based on the options analyzed, the lowest annual cost option is to purchase an easement machine.
While the tracked machine is more expensive per year than the wheeled machine, we believe that the
year around flexibility it affords, coupled with the safety created by lower center of gravity, improved
traction and wider wheel base represent a safety piece of equipment for city use in the next decade.
Present
Initial Cost Value Annual Annual
Includes Future Life Maintenance Interest Cost
Trade Trade (Years) Cost Rate % A/P Operation
New - Track Machine $48,996.84 $3,000.00 20 $426.34 2% 0.0612 $3,241.35
New — Wheeled $40,160.42 $3,000.00 20 $426.34 2% 0.0612 $2,700.56
Refurbish $24,400.00 $3,000.00 5 $426.34 2% 0.2212 $5,160.02
Rental NOT AVAILABLE
Contracted Service 18,000 I.f. of sanitary sewer per year @$1.35 $24,300.00
RECOMMENDATION
Based on the analysis, the lowest annual cost option that meets the City's needs is to replace the
existing 1990 Sreco EMSP-6 Easement Jetting Machine. The demo track machine from MacQueen
Equipment is being recommended as it significantly increases the safety for operators of the
equipment as well as provides increased functionality allowing for greater usage. MacQueen
submitted a quote for the demonstration unit of $48,996.84. Staff is recommending this vendor. The
2013 Equipment Plan budgeted $49,862 for this purchase.
Page 4 of 4