HomeMy WebLinkAbout4F - CSAH 44 Improvements DATE: 4F JOHN WINGARD, ASSISTANT CITY ENGINEER CONSIDER APPROVAL OF P ARTIAL PAYMENT TO SCOTT COUNTY FOR CSAH 44 IMPROVEMENTS (pROJECT 95-06) NOVEMBER 20, 1995 AGENDA #: PREPARED BY: SUBJECT: INTRODUCTION: The purpose of this agenda item is to consider approval of 90% payment to Scott County Highway Department for the amount due of $447,294.66 for the city's share of improvements to CSAH 44, City Project 95-06. See the attached copy of the invoice from Scott County. BACKGROUND: The Cooperative Agreement between Scott County and the City of Prior Lake for CSAH 44 from T .H. 13 to the East City Limits requires the city to deposit with Scott County Treasurer 90% of the estimated city's share of the construction and engineering costs as partial payment. The remaining amount of the city's share will be paid to the county upon completion of the project including landscaping and submittal to the city of the county's final statement of the project costs. DISCUSSION: The payment of this invoice is included in the list of invoices to be paid. Since the amount is quite large, staff is including this agenda write up as background information. On June 19, 1995, the City Council approved the plans and specifications for CSAH 44 and approved the Cooperative Agreement with Scott County. As mentioned in the agenda write up for June 19,1995, the city and county estimated that the total city cost would be $500,000. Based on the bid amounts received by the contractor, Richard Knutson Inc., it appears that the city's share will be slightly under the $500,000 estimate. 1626D.Hioglm€reek Ave. S.E., Prior Lake. Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER T T' ALTERNATIVES: The alternatives are as follows: 1. Approve 90% partial payment of $447,294.66 for the city's share of improvements to CSAH 44. 2. Table this item for a specific reason. 3. Deny this agenda item for a specific reason. RECOMMENDATION: Approve Alternative No.1. FINANCIAL IMP ACT: The CSAH 44 project funding was included in the $950,000 General Obligation Bonds of 1995. The bond issue included Ridgemont Avenue and Creekside Circle along with the $500,000 for the CSAH 44 project. ACTION REQUIRED: Motion and second as part of the Consent Agenda to approve partial payment of $447,294 for the City's share of improvements IOC1<<. . L REVIE CSAH44PO.OOC l' r SCOTT COUNTY HIGHWAY DEPARTMENT 600 COUNTRY TRAIL EAST JORDAN, MN 55352-9339 (612) 496-8346 FAX (612) 496-8365 INVOICE COOPERATIVE AGREEMENT No. 9507 September 26, 1995 Larry Anderson City of Prior Lake Public Works Department 4629 Dakota Street SE Prior Lake, MN 55372 Re: SAP 70-644-01nO-627-20 CP 95-06 (City of Prior Lake) SAP 70-644-01{70-627-20 Construction Costs Preliminary Engineering Construction Engineering CP 95-06 Construction Costs Construction Engineering Total (See Exhbit A) 90% BALANCE DUE SCOTT COUNTY DUE UPON RECEIPT - THANK YOU! MAKE CHECK PAYABLE TO: Scott County Treasurer SEND PAYMENT TO: Scott County Highway Department 600 Country Trail East Jordan, MN 55352-9339 BRADLEY J. LARSON Highway Engineer DANIEL M. JOBE Design Engineer DON D. PAULSON Construction Engineer ~~, n ~ d"S ~"''''r r. (, ::I .l ..J< $ 392,235.35 27,193.27 19,611.77 55,193.98 2.759.70 $ 496,994.07 $ 447,294.66 ..,17\ ?jO .; /'fY ~lil p- i An Equal Opportunity/Affirmative Action/Safety Aware Employer