HomeMy WebLinkAbout7C - Carriage Hills Pkwy
AGENDA #:
PREPARED BY:
SUBJECT:
7C
LARRY ANDERSON, DIRECTOR OF PUBLIC
WORKS
CONSIDER APPROVAL OF A MOTION TO
REIMBURSE MSA CONSULTING ENGINEERS
FOR ADDITIONAL WORK REQUIRED ON
CARRIAGE HILLS P ARKW A Y PROJECT PHASE I
NOVEMBER 20, 1995
DATE:
INTRODUCTION:
The purpose of this agenda item is to consider a motion to
reimburse the City's engineering consultant, MSA
Consulting Engineers, for expenses beyond the contracted
not-to-exceed budget for Phases I of the Carriage Hills
Parkway Project. Phase I is adjacent to the Carriage Hills
plat.
BACKGROUND:
The contract with MSA Consulting Engineers established
the following budget for Phase I:
CARRIAGE HILLS P ARKW A Y - PHASE I
Design
$44,600
Construction Services
$33,700
The not-to-exceed budget includes design phase and
construction administration phase tasks, as well as,
easement description preparation. The construction
services are for inspection and construction staking.
Shown below is a comparison of the budget and the
amounts MSA Consulting Engineers have invoiced the City
of Prior Lake for Phase I:
BUDGETED
Design: $44,600.00
Construction Services: $33.700.00
TOTAL $78,300.00
ACTUAL
$72,474.51
$32.817.96
$105,292.47
The city has not paid bills in excess of the authorized
amount.
16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
T '1"
DISCUSSION:
The billings received are $29,092.47 in excess of the
authorized amount. MSA Consulting Engineers have
legitimately done work beyond the contract requirement in
order to complete the project. A description of that work is
provided in this agenda write up. Staff has negotiated with
MSA Consulting Engineers to reduce the request for
additional services to $18,800 for design. This would
increase the amount for design from $44,600 to $63,400.
MSA Consulting Engineers has reduced their billing in
recognition of all the work they have done for the city and
to show their appreciation to work for the city. The
Carriage Hills Parkway Phase II (within the Knob Hill plat)
will be approximately $10,000 under budget as the design
and construction did not have all the complications of the
first phase. The city will receive Municipal State Aid
funding for all of the engineering costs incurred.
The following is a summary of significant items which
caused costs to increase beyond the original scope of
services:
1. Land acquisition from the Vierling property was
unsuccessful without condemnation. Staff negotiated a
settlement with the property owner which was not
executed due to the property owner backing out of the
agreement. Condemnation was implemented after
additional negotiations were made with Council
assistance.
2. A right-of-way (ROW) acquisition plan was done so
that ROW acquisition costs could be reimbursed from
Municipal State Aid. The plan was expanded to include
ROW for Carriage Hills Phase II and Pike Lake Trail as
these improvements also involved the Vierling
property. The condemnation award was $71,910 and
the city has been reimbursed from Municipal State Aid
for this amount. By including the Pike Lake Trail and
Carriage Hills Phase II land acquisition with this
project, an additional condemnation action was
avoided. A separate condemnation action would be a
minimum of$10,000.
AGCHP9S.DOC
2
T T'
3. In order to include the Pike Lake Trail and Carriage
Hills Parkway Phase II parcels, substantial design costs
were incurred, mostly for Pike Lake Trail. The design
included the use of retaining walls to reduce tree loss
and land acquisition.
4. The storm sewer, which originally went through the
center of Vierling's property was realigned to follow
the roadway to eliminate severance damages for right-
of-way acquisition. MSA performed additional
drainage studies to prove that runoff from the Carriage
Hills plat and Carriage Hills Parkway did not exceed
the pre-development volume and rate. This was done to
eliminate the need for acquisition of the 16.6 acre
wetland along CSAH 21. During the condemnation
hearings, the appraiser for the Vierlings stated that the
wetlands have a value of $4,000 an acre or $66,000. No
award was given for this as the wetland was not a part
of the taking.
5. The design of Carriage Hills Parkway was modified to
flatten the fill slopes to allow farming, and steepen the
cut slopes to reduce the area required for permanent
land acquisition. Without permanent acquisition the cut
slopes would have been farmed and erosion of the
slopes onto the sidewalk and roadway would have
resulted.
6. The project was bid in the fall of 1994 and bids were
rejected. The re-bidding of the project reduced project
costs by $130,000 but increased engineering costs for
bidding.
7. Scott County changed the design of CSAH 21 from the
preliminary design requiring Carriage Hills Parkway to
be redesigned. The intersection with CSAH 21
alignment was also changed to provide a better
intersection for the Jeffers property.
8. The Carriage Hills 2nd Addition intersection was not
constructed according to original plans thus requiring
plan modifications.
AGCHP9S.DOC
3
T
y-
In summary, the request for payment for additional services
is justified and will be recouped from Municipal State Aid
if approved by the Council. In fact, the full amount of their
costs incurred could be recouped if authorized by the
Council.
The city did save $130,000 by re-bidding the project,
because the first bids received were not competitive. By
showing that the Carriage Hills development and parkway
did not increase stormwater flow to the Vierling property,
wetland acquisition was not acquired. The Vierling's
appraiser stated that the value of the wetland was $66,000.
It is unknown what the commissioners award would have
been. Stormwater design changes were needed to
implement this. It is unknown what the amount of
severance damages would have been awarded if the storm
sewer had not been rerouted. A second condemnation
action would have cost a minimum of $10,000. The city
saved substantially more money by implementing design
changes than incurred in engineering costs.
ALTERNATIVES:
The alternatives are as follows:
I. Motion to authorize payment for additional services
rendered with respect to Carriage Hills Parkway
Phase I.
2. Deny motion for a specific reason
3. Table motion for a specific reason.
RECOMMENDATION: The recommendation is Alternative No.1.
FINANCIAL IMPACT: The additional costs will be borne by the construction
account. Staff will apply for State Aid money to reimburse
this account.
ACTION REQillRED: Motion and second to authorize the design fee to be
increased from $44,600 to $63,400 for additional services
rendered by MSA onsulting Engineers in conjunction
. th C . e Hi! Parkway Phase 1.
AGCHP9S.DOC 4
T T'