Loading...
HomeMy WebLinkAbout7C - Waterfront Business Park AGENDA #: PREPARED BY: SUBJECT: DATE: INTRODUCTION: BACKGROUND: STAFF AGENDA REPORT 7C BRUCE LONEY, ASSISTANT CITY ENGINEER CONSIDER APPROVAL OF CHANGE ORDER NO.1 PROJECT 93-11, WATERFRONT PASSAGE BUSINESS PARK IMPROVEMENTS JUNE 20, 1994 During the course of construction for Project 93-11, additional work beyond the Contract was done by the Contractor and additional work done by the City. A Change Order for this additional work and deduction has been prepared and enclosed in the Agenda packet for Council approval. The contractor, Imperial Developers, Inc., and their subcontractors, have performed additional work which was not included in the original contract. The additional work is described and itemized costs are shown on the enclosed Change Order form. Also on the Change Order is for an extension of contract time of two weeks to complete the work scheduled for this year. A total of seven (7) additional items and one (1) deduction item are described with the total net cost of the Change Order being $37,709.35. Items 1-4 are associated with the sanitary sewer, watermain and storm sewer systems and were necessary changes that were not in the original contract. Item #1 was for increasing the sanitary sewer service system from 4" to 6" for each potential building site. Items #2 and #4 were for modifying standard hydrants due to a lowering of the street grade change on Fish Point Road. Item #3 was recommended by City's Soil Engineer that drain tiles be installed at the low points to keep the street subgrade as dry as possible. Project 93-11 was graded in September, October and November of 1993. The spring and summer of 1993 was one of the wettest years on record and thus the soil on the site had a higher than normal moisture content. During the grading, areas of unstable soil needed to be removed in order to construct the lot or street areas. These areas were not detected by the soil borings on the project. In order to minimize the amount of subgrade .excavation, a backhoe was utilized to remove saturated soil. The added cost of excavation was determined to be $1.65 per cubic yard for 10.322 cubic yards of excavation after several negotiations with the contractor. This excavation 4629 Dakota St. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPP6RTUNITY EMPLOYER T . r T. ALTERNATIVES: operation was recommended by the City's Soil Engineer and his opinion was that the amount of subgrade excavation was greatly reduced by using a backhoe as the underlying soil layers would not be disturbed by scrapers and dozers. If the areas would have been excavated with scrapers and dozers, the additional cost of subgrade excavation, and additional suitable backfill material would have been more than the extra cost of Item #6. During the course of grading the site, it was apparent that there would be a shortage of good material which was available from the Fire Hall site and there was a surplus of saturated material. In order to balance the site, the contractor obtained granular material by over excavating boulevards and setback areas and then filled these areas with less desirable saturated soil. This excavation method was done to obtain a balance of earthwork to build the Key-Land Home lot area and the necessary street areas, and was less expensive than importing material. To construct the streets within the development cost effectively, Item #5 was utilized which was for providing additional rock sub base. At the time when the streets were constructed, the areas to obtain granular material were depleted as much as possible. Utilizing the 3" minus aggregate sub base limited the amount of subgrade excavation for the streets, this making this alternative the most cost effective. Item #7 was for the concrete valley gutters to serve the Fire Hall. Key-Land Homes, and Becker Arena Ice Products sites. These valley gutters were not known at the time of bidding. The total amount of this Change Order is $37,709.35 with the original contract amount being $789,693.00. The addition of Change Order No.1 represents a 4.8% increase in the original contract amount and the contract amount total is now $827,402.35. The contractor has signed the Payment Voucher and Change Order and submitted a letter stating that this Change Order resolves all claims on Project 93-11 from previous attached claim letters of February 14, 1994 and April 18, 1994. The contractor had a previous claim for soil correction in the amount of $74,583.00. Staff had initially offered $12,578.00 for soil correction. The balance of items were not part of the $74,583.00 claim. The final negotiated amount is as shown in the Change Order. One deduction is included for the repair of street light lines which were damaged by the contractor and paid by the City. Also an extension of contract time of two (2) weeks has been asked for and included with the Change Order. The alternatives are as follows: 1. Approve a motion authorizing Change Order No. 1 in the amount of $37,709.35 to Imperial Developers Inc. recognizing that this payment releases the City from any and all claims made by Imperial Developers Inc. in their letters of February 14, 1994 and April 18, 1994. Imperial Developers Inc. has agreed to that condition in their attached June 13, 1994 letter. -2- RECOMMENDATION: BUDGET IMPACT: ACTION REQUIRED: CCA620.ENG 2. Disapprove the motion for a specific reason. 3. Table this item for a specific reason. The recommendation is to approve Change Order #1 as the contractor has completed the work and City staff feels the negotiated settlement is acceptable. This amount will be paid from the Construction Fund and has been included with this month's construction voucher. Sufficient funds exist to pay for the additional cost from this Change Order. Make a motion to appro)t'8 Change Order #1 for Project 93-11 authorizing the Mayor an ity Manager to sign the Change Order. C -3- T' rr" CHANGE ORDER CITY OF PRIOR LAKE 4629 DAKOTA STREET S.E. PRIOR LAKE, MN. 55372 DATE: TO: FOR: June 1, 1994 CHANGE ORDER NO.1 Imperial Developers, Inc. Project No. 93-11, Waterfront Passage Business Office Park Improvements City of Prior Lake, Minnesota You are hereby directed to make the following change to your contract dated Se;>tember 7. 1993 . The change and the work affected thereby is subject to all contract stipulations and covenants. This Change Order will increase the contract sum by: Thirty Seven Thousand, Seven Hundred Nine and 35/100 Dollars ($ 37.709.35 ). Add the following: $ 927.50 Item 1: $ 400.00 Item 2: $ 1,905.00 Item 3: $ 500.00 Item 4: $ 13,799.11 Item 5: $ 17,030.32 Item 6: $ 3,638.00 Item 7: $ 38,199.93 'lbtal Additions Deduct the following: $ 490.58 Item 1: $ 490.58 Total Deductions Change sanitary sewer services from 4" to 6". Cost increase is $1.501L.F. of 545 L.F. pipe installed, plus $10.00 per 11 sanitary service each for the increased cost of the wye. Change hydrants from 8'.0" bury to 8'.6" bury. Cost increase is $50.00 per hydrant installed. Add 4" Drain Tile. Cost for installation, including materials and labor is $4.851L.F. of drain tile installed, plus $75.00 per cut out required to connect to the storm sewer structures. QUANTITIES THRU 6/1/94: Drain tile = 300 L.F. Cut outs = 6 Each Install hydrant that was later removed. Cost is $500.00 for the labor required to install and remove. Labor, material and equipment for installing 2122.94 Tons of 3" minus crushed Limestone @ $6.50/I'on as required to construct the roadways. Additional labor and equipment to excavate 10,322 C.Y. of material @ $1.65/C.Y. by using a backhoe to remove the material. Labor, material and equipment for installing 909.5 square feet of concrete valley gutter @ $4.00/SF at the Fire Hall, Key-Land Home and Becker Arena sites. Labor, material and equipment to repair damaged electrical street wires at CSAH 21 and Fish Point Road. 1 I~ Amount of Original Contract Additions approved to date (Nos.-L) $789,693.00 $ 38,199.93 Deductions approved to date (Nos.-L) < 5 490.58 > Revised Contract Amount 5827.402.35 Amount of this Change Order (Add) $ 37,709.35 CHANGE IN CONTRACT TIME Original Contract Times ..................................................................... July 1, 1994 for the completion of all work items except for the bituminous wear course. Net Increase of this Change Order .......................................................................... 14 Calendar Days Contract Time with Approved Change Order .................................................................July 15, 1994 931102.ENG DATE: June 10. 1994 CHANGE ORDER NO. 1 TO: Imperial Developers. Inc. FOR: Project 93-11, Waterfront Passaie Business Office Park FOR: City of Prior Lake. Minnesota Approved as to Form: APPROVALS: Approved CITY OF PRIOR LAKE Owner By CITY ATTORNEY Mayor Date By City Manager Date Approved Imperial Developers. Inc. Contractor U-- C'~ . V tJv'- i.b~-- . By Title eFV 931102.ENG "tit ate Respectfully Submitted, CITY OF PRIOR LAKE ENGINEERING DEPARTMENT B&::do Project Engineer f .' II IMPERIAL DEVELOPERS INC 9001 Grand Avenue South · Bloomington, Minnesota 55420 Office 612.881'6464 Fax 612.881'8700 February 14, 1994 .Waterfront Park Prior Lake Increase in prices due to changed conditions. *Topsoil stripping with backhoe (+topsoil stripping in fills should be paid as subgrade) 4827 cy @ add'] 1.84/yd 5500 cy @ add'l 1.84/yd 5500 cy @ 0.47 8,881.00 *Subgrade excavation with backhoe 10,120.00 2,585.00 *Pond Excavation - All had to be done with backhoe. 22000 cy @ add'l 1.84/yd 40,480.00 *Dry & recompact material that has heen placed in areas 4+6. (This material was not compact- able at the time of construction due to weather conditions.) 5450 cy @ 1.95 10,627.00 *Move blackdirt and spread over areas 4+6 that the City wants compacted. 2100 cy @ 0.90 1,890.00 $74,583.00 The City has offered to pay $12,578.00 of this. (26763 yds of borrow @ 0.47) ,'i?~ ',' , -,:::31/V . \//3.~2~ ~ ~ . ::.:;e'Ner . =,<cz;. -'-:: ,.... ............ -' ._" -' .~, EQUAL OPPORTUNITY EMPLOYER -' FABYANSKE, SVOBODA, WESTRA, DAVIS & HART A PRof:EssIorw. ASSOCIATION L Co. IWIT II. T. FAII'I'AHSICE GERAlD L SI/08OOA *'lit w. 'MSTlIA llOIEIlT L OA VIS .8EMIAH J. 1lEAII~ ~ T. MOZER Cl&toNS J. TAOOIEN SCOTT WMl AIClEllSON "AI.\. L IlA TULE GlIIEGOllY T. SPAW DEAN L TllOMSClN GARY Co. EIDSON DRAFT CARRIE A. GREEN 0WlGMT G. AABUSE ICYI.& E. ~RT J\JOl1l4 E. J(JlOW HOU.Y A. R. ~RT STEl'HEN A. MELCHER IIICHAAD G. .JENSEN n<<:lMAS J. T\lCa OWI~S Go CARPENTSR III MARY SUi M. YOllBRICH ..04AiL J. KINZER JOCELYN L ICNOU. .A.U: A. ClOHERTY 1100 MINNEAPOLIS CENTRE 920 seCOND A VENUE SOUTH MINNEAPOlIS. MINNESOTA 55.&02 m.ePHONE 812-338-0115 TEL..ECOf'lER '12-338-3857 April 18, 1994 Glenn Kessel, Esq. City Attorney City of Prior Lake 4629 Dakota Street S.E. Prior Lake, MN 55372-1714 Re: Waterfront Passage Business Park Dear Mr. Kessel: I represent Imperial Developers, Inc., in regard to its dispute with the City of Prior Lake on the Waterfront Passage Business Park project. Imperial was the excavation and grading contractor on the project, and has asserted five claims against the City for additional costs arising as a result of changes in the work ordered by the City, as well as a differing site conditionfdefective specification. I am writing to outline Imperial's position -regarding its claims. I will address each claim separately. 1. Muck Excavation. Section 02105.2.03 of the specifications states that muck excavation is the quantity of excavation material that is removed from below the natural ground level of wetlands within the roadway embankment area. The City has refused to pay for the top 12 inches of such muck excavation on the basis that it should be treated as common excavation. However. there is nothing in the specifications to suggest that the top 12 inches of excavation should be treated as common excavation. If the City had desired to treat the top 12 inches of muck excavation as common excavation, it could have provided for such treatment in the specifications, as is sometimes done in project specifications. Since the City did not do so on this project, the specifications unambiguously require that Imperial be paid the muck excavation rate for all material excavated in the area designated as muck excavation. In submitting its bid, Imperial was entitled to rely on the City's specifications. 2. Subsrrade Excavation. Sections 01025.C.5 and 02105.2.02 of the project specifications provide that subgrade excavation is the quantity of excavation material below the proposed subgrade elevations within the site to correct unstable areas or to remove topsoil for embankment of roadways or lots as determined by the engineer. Any material below the class 5 aggregate is considered in the industry to be subgrade. Despite this fact, the City has paid , .' Glenn Kessel, Esq. April 18, 1994 Page 2 Imperial at the rate of common excavation for the top 12 inches of such subgrade material that Imperial has excavated. There is no provision in the specifications that would support the City's position that the top 12 inches of Imperial's subgrade excavation should be treated as common excavation. The City could have specified that the top 12 inches of the subgrade excavation would be treated and paid for as common excavation. Since the City did not do so, the specifications unambiguously provide that Imperial shall be paid at the sub grade excavation rate for all materials excavated in areas designated as subgrade excavation, including the top 12 inches of material. The City has argued that page 4 of the plan drawings implies that certain excavation in the areas designated as sub grade excavation would be treated as common excavation. However, even if there was such an implication, where there is any inconsistency between the specifications and the plan drawings, the specifications control. In submitting its bid, Imperial was entitled to rely on the City's specifications. 3. Method of Excavation of Materials. The standard in the industry is to perform excavation work with scrapers and dozers wherever possible because it is more efficient and less costly than other methods of excavation, such as using a back-hoe. Imperial bid the project based upon its intent to perform the excavation with scrapers and dozers, and did, in fact, begin the work using this method of excavation. However, shortly after Imperial began the work, the City's engineer prohibited Imperial from performing any further excavation with scrapers and dozers. Instead, the City's engineer required Imperial to perform the excavation with a back-hoe. The City did so in order to decrease its own costs by decreasing the amount of sub-cutting that was required. However, the City's required method of performing the excavation substantially increased Imperial's costs. By requiring Imperial to perform the work in a manner that is not specified in the contract and is inconsistent with industry standards, the City changed the work under the contract. Imperial is entitled to be compensated for its increased costs incurred as a result of this change in the work. 4. Comoaction of Embankments. Section Ol025.C.4 of the project specifications provides that excavated material shall be utilized on the site to the fullest extent possible, and that unsuitable excavated material shall be disposed of as directed by the engineer. A substantial amount of the excavated material consisted of silty, saturated material that was unsuitable for use on the site. Such unsuitable material should have been disposed of as provided in the specifications. However, the City instructed Imperial to spread the unsuitable material in areas 4 and 6, and has stated that it will require Imperial to return to the site in the spring to re-work and dry the material in an attempt to incorporate the material into the embankments being constructed on the site. The City's attempt to incorporate unsuitable material into the project is inconsistent with Section 01025.C.4, and Imperial is entitled to additional compensation for attempting to comply with the City's directives. The City has argued that Section 02105.3.05 of the project specifications requires Imperial, with payment of additional compensation, to re-work and dry the material in an . , Glenn Kessel. Esq. April 18, 1994 Page 3 attempt to make the material suitable for incorporation into the project. While that Section provides that hnperial will not be paid additional compensation for drying soils to meet the moisture content requirements of MnDOT Specification No. 2105.3F, it does not require Imperial to engage in unreasonable effortS to use unsuitable material. Moreover, MnDOT Specification No. 2105.3F, which is incorporated into the project specifications by reference, specifies that construction shall not continue when the existing soil moisture content does not allow for proper compaction of embankments. If the City desired to use the unsuitable material. it should have shut-down the project until such time as the material became workable. s. Excavation of Saturated Material. Before obtaining bids on the project. the City obtained soil borings showing the subsurface conditions. including the water table and moisture content. The results of the soil borings were included in the specifications, and hnperial relied on those soil borings in preparing its bid on the project. However, after hnperial began work on the project. it learned that the borings were materially incorrect in that the subsurface material was substantially wetter than shown in the soil borings. As a result of the saturated condition of the material. hnperial incurred increased costs in excavating and working the material. This materially adverse change in the condition of the material constitutes a differing site condition and a defective specification. for which hnperial is entitled to receive compensation. Section SC-4.2 of the specifications states that the actual water table and moisture contents may vary at the actual time of constrUction, and that the contractor should take its own soil borings to determine the water table and moisture content. The City argues that this statement prevents hnperial from receiving any compensation for the added costs of excavating and handling the satUrated material. However, it is well established under Minnesota law that such a disclaimer does not prevent a contractor from relying on the soil borings contained in the specifications. The relevant inquiry is whether the contractor reasonably relied upon the soil borings. When reasonable reliance on the soil borings is shown. the contractor is entitled to relief. In this case. hnperial had no reason to, believe that the soil borings contained in the specifications were inaccurate. Imperial reasonably relied on the borings in submitting its bid. As a result, Imperial is entitled to recover for the substantially increased costs that it incurred as a result of the differing site condition and defective specification. Imperial wishes to resolve the foregoing claims without the inconvenience of litigation. Please contact me if you wish to discuss this matter further. Sincerely, Richard G. Jensen RGJIhrh/26767.A . II IMPERIAL DEVlLOPERS INC 9001 Grand Avenue South · Bloomington, Minnesota 55420 Office 612.881'6464 Fax 612.881'8700 June 13, 1994 Mr. Bruce Loney City of Prior Lake 4629 Dakota Street SE Prior Lake, Minnesota 55372 Re: Waterfront Industrial Park Prior Lake, MN Dear Bruce, The change order that the City has written on this project takes care of all of the claims that we outlined in our notes of February 14, 1994, and as listed in our attorney's letter of April 18, 1994. Please call with any questions. Sincerely, IMPERIAL DEVELOPERS, INC. ~~ JDH/ar Highway. Heavy · Water · Sewer . Excavating. Grading