AGENDA #:
PREPARED BY:
SUBJECT:
DATE:
INTRODUCTION:
DISCUSSION:
8A
RALPH TESCHNER FINANCE DIRECTOR
CONSIDER APPROVAL OF 1995-1999 CAPITAL IMPROVEMENT
PROGRAM
JULY 18, 1994
Annually the City prepares a capital improvement program which is
designed to identify infrastructure improvements which are necessary as a
result of primarily two factors; community growth and replacement
consideration. Attached is the 1995-99 CIP (Capital Improvement
Program) which contains those improvements necessary to maintain a
progressive community.
Such projects include not only city initiated improvements but anticipated
County and State road improvements as well. In some cases they involve a
financial responsibility on behalf of Prior Lake while in others they may
not. In addition, capital equipment purchases have been reinstated into the
CIP this year because equipment certificates are anticipated to be issued
next year.
Also included is a condensed project summary sheet (see yellow
attachment entitled "Reference Summary") that presents a list of projects
by year along with a financing source recap. This capsule summary
should be helpful for the Council to refer back and forth between years as
a quick reference guide.
It is important for the Council to recognize that the document is a flexible
planning tool that is affected by a number of governmental agencies plus a
significant impact by the Shakopee Mdewakanton Dakota Community.
The Council should critically review those proposed projects for 1995.
These improvements selected for bonding will affect the property taxes in
1996. Council should remember that the school district and county will
also influence the level of taxes through their annual levies and periodic
referendums and bond issues.
Those programs which are not deemed to be of high priority should be
eliminated now so they do not generate public expectation or demand and
also to avoid unnecessary staff effort and expense. Engineering will follow
up the Council decision with respect to project delineation by preparing a
feasibility report soon after. Adequate lead time is extremely important for
surveying, right of way acquisition and 'engineering to obtain the best
possible bids which is generally early in the year.
4629 Dakota St. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
'T
r
.' .
ALTERNATIVES:
Subsequent years in the CIP are more important from a plan perspective
than an implementation schedule. However, of equal importance is to
balance the tax resources as much as possible. Under the project levy
column of the Reference Summary, where the financing sources are
outlined, is the cumulative property tax impact by dollar and percentage.
The major projects proposed for 1995 and their individual associated tax
impact are as follows:
Project Description
Project Levy City Tax Impact Priority
Titus Street Improvements $18,000
Grainwood Crossing Restrooms $30,000
Lakefront Park Paving $150,000
Ridgemont Avenue $160,000
CSAH 42 west ofCSAH 18 $200,000
Street Overlay Program $480,000
$ 0.60 - 0.09% M1
$ 1.01 - 0.15% HI
$ 5.03 - 0.77% M2
$ 5.36 - 0.82% H2
$ 6.70 - 1.03% HI
$16.08 - 2.46% HI
$34.78 - 5.32 %
Totals ...
$1,038,000
Listed below is a year by year tax recap if all the projects that include a tax
levy were implemented. The Scott County Assessor has estimated the
average Prior Lake market value home in 1994 to be approximately
$120,000 which is revised upwards from last year's amount of $110,000.
The new typical value has been utilized for purposes of calculating the
following tax impact.
(A 1995 base tax of $654.02, which was adjusted to include the tax
increase for the $800,000 General Obligation Improvement bonds recently
approved, was utilized to compute the beginning percentage increases.
Budgetary increases are excluded for purposes of comparing the effect of
capital dollars only within the context of the elp. Also this model assumes
an annual 3% tax capacity valuation growth.)
Project Year and Levy Amount
Tax Impact
1995 ... $1,038,000
1996... $ 980,000
1997 ... $ 920,000
1998 ... $ 660,000
1999... $ 715,000
$34.78 - 5.32%
$31.92 - 4.63%
$29.06 - 4.03%
$20.33 - 2.71 %
$21.34 - 2.77%
Each of the above amounts represent first year tax increases which
gradually slide downwards over the the ten year term of the bond issues
due to valuation growth. Therefore the beginning tax base of $654.02
would actually increase to $782.54 by the year 2000. The total increase of
$128.52 represents an annualized percentage increase during the course of
the 1995-99 CIP of 3.93%.
The appropriate department heads will present project summation of those
improvements which would come under their departmental responsibility.
The Council should carefully examine the proposed projects, focusing
particularly upon those scheduled for 1995.
RECOMMENDATION:
ACTION REQUIRED:
REVIEWED BY:
A94II.WRT
The following alternatives are available for Council consideration:
1. Provide direction to the staff to modify the proposed program
to mitigate annual tax increases while insuring appropriate
maintenance of public infrastructure.
2. Amend the 1995-1999 Capital Improvement Program as per
Council determination.
3. Approve the proposed 1995-1999 Capital Improvement
Program as submitted.
While it is important that the Capital Improvement Program be adopted
expeditiously, it is equally important that the Council be comfortable and
supportive of the proposed projects and their tax consequences. The
August 1st Council meeting looks to be a long meeting. If the Council
wishes to study the CIP in more detail it would be appropriate to establish
a workshop to further this matter. In either event, it is necessary for the
Engineering department to begin the feasibility study as soon as possible
for those ~ects schyduled for 1995.
, ( I
nqcti'\5to \aff ~garding the 1995-1999 Capital Improvement Program.
.1t L,"' I f/., l----
Project Description
L
2.
Fire DeoartInent.
(Equipment)
Bunker Turnout Gear
Pumper Fire Truck
Park Deoarlment.
(Equipment)
Tractor (60 HP)
Dump Truck (Tandem)
Toro Mower (16')
(Developments)
Basketball Courts
Open Air Park Shelters (5)
Grainwood Crossing Restrooms
Neighborhood Parks;
Carriage Hills
Woodridge Estates
Westbury Ponds
Lakefront Park Paving
(Trails)
Knob Hill
Wilds
(Land)
3.
4.
5.
6.
7.
8,
9,
10.
II.
12.
Public Works:
(Equipment)
13. Wing & Plow
14. Tractor Backhoe
15. Front-end Loader
16. VacuunVJetterTruck
(Facility)
17. Sand/Salt Storage Facility
18. Maintenance Building
(Improvements)
19. Repaint Signals (CSAH 42/44)
20. Televise & Seal Sanitary
21. TItus Street Improvements
22. Pike Lake Trail
23. CSAH 21/42 Watennain
24. Ridgemont Avenue
25. Street Overlay Program
26. CSAH 42 west of CSAH 18
27. CSAH 83
Water Resource:
(Improvements)
28. Fish Point Park Drainage Channels
Totals...
Financing Source Summary:
Project Levy.
Equipment Certificates
GenerallUtility Fund Balance
Contributions
Capital Park Fund
Operating Budget
MSA Funds
Trunk Reserve Fund
Developer
Special Assessments
Utility Fund
Intergovernmental
· 1996 Taxes
Cll'Ol.WRT
REFERENCE SUMMARY
1995 CIP PROJECTS
Project Amount Tax Impact
DoUarPercentage
5,000.00 o.b.
190,000.00 e.f
36,000.00 eJ
65,000.00 e.f
67,000.00 e.f
10,000,00 c.p.
25,000.00 c.p.
30,000.00 1.01
30,000.00 c.p,
150,000.00 4.03
12,000.00 c.p.
50,000.00 c.p.
-%
0.15%
0.77%
15,000.00 eJ.
75,000.00 f.b,
100,000.00 e.f.
180,000.00 f.b.
100,000.00 u.f.
2,650,000.00 u.f.
18,000.00 o.b.
30,000.00 o.b.
45,000.00 .60 0.09%
325,000.00 s.a.
330,000.00 I.r.
265,000.00 5.36 0.82%
1,200,000.00 16.08 2.46%
1,200,000.00 6.70 1.03%
4,000,000.00 d.c.
70.000 00 o.b.
$11,473,000.00
1,038,000,00
473,000.00
355,000.00
105,000.00
122,000.00
123,000.00
200,000.00
330,000.00
400,000.00
977,000.00
2,750,000.00
4.600.000 00
$11,473,000.00
34.78
5.32%
Legend
c.p.-capital park
e.f.-equipment fund
f.b.-fund balance
o.b.-operating budget
s.a.-special assessments
I.r.-trunk reserve
u.f.-utility fund
.- '"1'-''' _ .
CIPOI.WRT
Project Description
I.
2.
3.
Fire Deoarlment:
(Equipment)
Bunker Turnout Gear
Bulk Tank Truck
Pumper Fire Truck
(Facility)
Satellite Fire Station
4,
5.
6,
7.
8.
9.
10.
II.
Park Denarlment.
(Developments)
Basketball Courts
Open Air Park Shelters (5)
Neighborhood Parks;
Memorial Park Restrooms
The Pond Irrigation
The Pond Field ExpansionlLighting
Lakefront Park Expansion
Public Works:
(Improvements)
Televise & Seal Sanitary
Street Overlay Program
CSAH 44
12.
13.
14.
15.
Water Resource'
(Improvements)
Fish Point Park Water Quality Imp.
Totals...
Financing Source Summary
Project Levy
Referendum
Contributions
Capital Park Fund
Operating Budget
MSA Funds
Special Assessments
Intergovernmental
REFERENCE SUMMARY
1996 CIP PROJECTS
Project Amount
5,000.00
100,000,00
160,000.00
TBD
10,000.00
25,000.00
30,000.00
50,000.00
100,000.00
325,000.00
400,000.00
30,000.00
1,500,000.00
1,450,000.00
30 000 00
$4,215,000.00
Project Amount
980,000.00
1,085,000.00
5,000.00
60,000.00
65,000.00
170,000.00
900,000.00
950 000 00
$4,215,000.00
Tax Impact
Dollar Percentage
31.92 4,63%
<,_..~..--"." -.........--....'..-.... YT
2.
3.
4.
5.
6.
7.
8.
9.
CIPOl.WRT
Project Description
1.
Fire Deoarlment:
( Equipment)
Bunker Turnout Gear
Park D~Oarlment:
(Developments)
Basketball Courts
Open Air Park Shelters (5)
Neighborhood Parks;
Public Works:
(Equipment)
Leak Detection Sensors
(Improvements)
Televise & Seal Sanitary
Fish Point Road to CSAH 21
Street Overlay Program
CSAH 21 north ofCSAH 82
10.
11.
Water Resource:
(Improvements)
Pond Dredging
Sand Point Park Water Quality Imp.
Totals...
Financing Source Summary
Project Levy
Contributions
Collector Street Fund
Capital Park Fund
Operating Budget
MSA Funds
Special Assessments
Intergovernmental
REFERENCE SUMMARY
1997 CIP PROJECTS
Project Amount
5,000.00
10,000.00
25,000.00
30,000.00
15,000.00
30,000.00
345,000.00
1,550,000.00
2,350,000.00
20,000.00
30.000.00
$4,410,000.00
Project Amount
920,000.00
5,000.00
55,000.00
60,000.00
100,000.00
690,000.00
930,000.00
I 650 000 00
$4,410,000.00
Tax Impact
Dollar PerCentage
29.06 4.03%
'T
T"
T' .
CIPOI.WRT
Project Description
1.
Fire Deoartment:
(Equipment)
Bunker Turnout Gear
2.
3.
4.
Park Deoartment:
(Developments)
Basketball Courts
Open Air Park Shelters (5)
Neighborhood Parks;
5.
6.
7,
Public Works:
(Improvements)
Televise & Seal Sanitary
Street Overlay Program
CSAH 42 west to city limits
8.
Water Resource:
(Improvements)
Pond Dredging
Financing Source Summary
Project Levy
Contributions
Operating Budget
Capital Park Fund
Special Assessments
Intergovernmental
Totals...
REFERENCE SUMMARY
1998 CIP PROJECTS
Project Amount
5,000.00
10,000.00
25,000.00
50,000.00
30,000.00
1,350,000.00
2,210,000.00
20.000.00
$3,700,000.00
Project Amount
660,000.00
5,000.00
55,000.00
80,000.00
810,000.00
2.090.000 00
$3,700,000.00
Tax Impact
Dollar Percentage
20.33 2.71 %
.
Project Description
Fire Deoartment:
(Equipment)
I. Bunker Turnout Gear
2, Pumper Fire Truck
Park Deoartment.
(Developments)
3. Basketball Courts
4. Open Air Park Shelters (5)
5. Neighborhood Parks;
Public Works'
(Improvements)
6. Televise & Seal Sanitary
7. Street Overlay Program
8. New Municipal Well
9. Carriage Hill Road Extension
10, T.H. 13 Channelization
Water Resource:
(Improvements)
II. Pond Dredging
Totals...
Financing Source Summary
Project Levy
Equipment Certificates
Contributions
Operating Budget
Collector Street Fund
Capital Park Fund
MSA Funds
Trunk Reserve Fund
Special Assessments
Intergovernmental
CIPOI.WRT
REFERENCE SUMMARY
1999 CIP PROJECTS
Project Amount
5,000.00
200,000.00
10,000.00
25,000.00
50,000.00
30,000.00
1,785,000.00
400,000.00
450,000.00
5,500,000.00
35.000.00
$8,490,000.00
Project Amount
715,000.00
200,000.00
5,000.00
55,000.00
75,000.00
80,000.00
375,000.00
400,000.00
1,070,000.00
5.500.000.00
$8,490,000.00
Tax Impact
Dollar Percentage
21.34 2.77%
.._..._H........ -,...,..,,--'~~ 91
MEMORANDUM
TO:
FROM:
DATE:
Mayor and City Council
Frank Boyles, City Manager
July 18, 1994
Resolution 94-39 for Agenda Item 78 (Carriage Hills)
SUBJECT:
Attached is Resolution 94-39 for inclusion with Item 78 for the July 18 meeting.
This item was not completed by Engineering prior to the time the agenda packets
were delivered.
RS9439. WRT
4629 Dakota St. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
-
RESOLUTION 94-39
RESOLUTION RELATING TO PARKING RESTRICTIONS ON
S.A.P. 201-106-03 ON CARRIAGE HILLS PARKWAY FROM
CSAH 21 TO PIKE LAKE TRAIL IN
THE CITY OF PRIOR LAKE, MINNESOTA
MOTION BY:
SECONDED BY:
WHEREAS,
the "City" has planned the improvement of MSAS 106 (Carriage Hills
Parkway) from CSAH 21 to Pike Lake Trail;
WHEREAS,
the "City" will be expending Municipal State Aid Funds on the
improvement of this Street, and;
WHEREAS
this improvement does not provide adequate width for parking on both
sides of the sU'eet; and approval of the proposed construction as a
Municipal State Aid SU'eet project must therefore be conditioned upon
certain parking restrictions.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA, that the "City" shall ban the parking of motor vehicles on both sides on MSAS
106 (Carriage Hills Parkway) from CSAH 21 to Pike Lake Trail.
Passed and adopted this _ day of
, 1994,
YES
NO
Andren
Greenfield
Kedrowski
Schenck
Scott
Andren
Greenfield
Kedrowski
Schenck
Scott
Frank Boyles
City Manager
City of Prior Lake