HomeMy WebLinkAbout8B Ct Rd 42 Reconstruction
DATE:
8B
LARRY J, ANDERSON, DIRECfOR OF PUBLIC WORKS
CONSIDER THREE ISSUES REGARDING COUNTY ROAD 42
RECONSTRUCTION
JULY 18, 1994
AGENDA NUMBER:
PREPARED BY:
SUBJECT:
INTRODUCTION:
The purpose of this agenda item is ~o consider three items:
1. To consider payment for the existing colored stamped
concrete medians and landscaping for CSAH 42 from the
Harbor to Crest Avenue.
2. To consider authorization and payment for installing
colored stamped concrete medians at the intersection of
CSAH 18/Crest Avenue and CSAH 42.
3. To discuss the merits of a urban versus rural design for
CSAH 42 from Crest Avenue to County Road 83.
BACKGROUND:
On June 7, 1993, the City Council approved the plans for the
construction of CSAH 42 from Ferndale Avenue to Harbor Place.
This work included the intersection of CSAH 18/Crest Avenue and
CSAH 42. At the same meeting, the Cooperative Agreement for
the project was approved by the City. The Cooperative Agreement
provides a detailed breakdown of costs to be paid by the City and
Scott County.
DISCUSSION:
The three issues are:
1. Consider payment for the existing colored stamped
medians on CSAH 42 from The Harbor to Crest
Avenue.
In September the City of Savage approved a Cooperative
Agreement with Scott County which included the installation of
stamped concrete medians and landscaping on CSAH 42, The
County has indicated that the Cooperative Agreement included the
City of Savage paying for the special medians and plantings.
County representatives indicate that any cost shaling for this work
was to be accomplished through a separate agreement between
Prior Lake and Savage.
The Public Works Director was contacted by the City of Savage in
the fall to determine if the City had interest in a stamped concrete
4629 Dakota St. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL ClPPORl1JNITY EMPLOYER
'1 r
median design. The Public Works Director indicated that a plan
should be provided with a cost breakdown for the City to consider
this further. No commitment was made for funding the special
medians. This information was not provided by Savage, and
construction of the medians commenced this summer.
The cost of the special medians and plantings installed from The
Harbor to Crest Avenue is $168,000. The City of Savage has
indicated that they are willing to pay $74,500 towards their share
of the cost of the existing special medians. Discussion with the
City of Savage and Scott County have been to request the City to
consider payment of $93,500 towards its share of the cost of the
special medians, The County's position is that they have a
Cooperative Agreement which requires Savage to pay all the cost
if the City of Prior Lake does not participate.
2. Consider authorization and payment from installing
colored stamped concrete medians at CSAH I8/Crest
Avenue and CSAH 42 intersection.
The City obtained a copy of the plan for the improvements which
were being made and determined that median improvements were
not included for the intersection of CSAH 18/Crest Avenue and
CSAH 42. The County was contacted to determine the cost to add
stamped concrete for this intersection, and the cost is $52,000. The
attached drawing shows the proposed improvement for the
intersection.
3. Merits of urban versus rural design for CSAH 42 from
Crest Avenue to County Road 83.
City Manager Boyles and Public Works Director Anderson met
with Commissioner Dick Underfcrth and County Engineer Brad
Larson to discuss the merits of CSAH 42 being an urban section
from CSAH 18 to County Road 83. The urban section on the long
range would fit better with long term development. The County
has sufficient right of way to construct a rural section with a thirty
four (34) foot wide depressed median to CSAH 21. This section
provides for the upgrading of CSAH 42 with double left turn lanes
in the future at intersections where needed. The location of
intersections will be driven by the ultimate development of the
area, By using a rural section, the intersection and turn lanes can
be constructed at a later date to accommodate development at a
substantially less cost than with an urban section.
Scott County is proposing that CSAH 42 be upgraded in 1996 to
CSAH 21 and to County Road 83 in 1997. These improvements
are much needed and County funding is marginal to accomplish
this. The additional City cost to go to an urban section from
CSAH 18 to CSAH 21 is approximately $625,000 more than a
rural section. ($1.1 million if special colored and stamped medians
are used,) The County's position is that with limited funding, the
County cannot justify the additional expense and resulting delay in
the improvements.
Pal!e 2
ISSUES:
The existing special median provides an intrinsic value and sense
of place, The improvements are very attractive and are an amenity
to the City. The dollar value of this beyond actual construction
costs is hard to measure. The City should have been approached to
participate in the cost of the improvements at the time of the
preparation of the Cooperative Agreement. The City could have
elected to participate and incorporated the appropriate cost into the
bond issue which funded the City's portion of the cost of the
CSAH 42 project. The fact of the matter is we did not.
The City has no legal obligation to pay for the existing medians;
however, the City does benefit from the improvements since the
majority of the existing improvements are within our corporate
limits.
The Construction Fund does not have funds to underwrite the
$93,500 and/or the $52,000 without eliminating funding for
another project. The one project which has not been constructed is
the CSAH 21 project to the east City limits. The bonding did
include $100,000 for lighting and $60,000 for landscaping. The
plans for CSAH 21 have not been completed. The Council will
ultimately approve the inclusion or exclusion of lighting and
landscaping. The City Council did discuss at the time of the
feasibility study whether or not lighting should be continued to the
east City limits. The existing lighting on CSAH 21 does go to Fish
Point Road which is the entrance to the Business Office Park. The
Council could discuss this again if they desired. The amount of
landscaping could be reduced or installed by the Parks Department
to reduce the cost.
Another source of funding would be to use an off system
expenditure from the Municipal State Aid fund. The cost of the
existing special medians and the medians for the intersection of
CSAH 18/Crest Avenue and CSAH 42 could be paid by Municipal
State Aid funds. While this appears to be an easy source of funding
the CIP needs to be considered. Constructing the projects
programmed for 1994 and the balance of the proposed CIP would
leave a balance of approximately $200,000 in the Municipal State
Aid fund, The Municipal State Aid projects from 1994 through
1999 total a projected amount of $2,958,000 of which the
$200,000 represents about 6% of the total expenditures.
Considering the projected costs are not based upon an engineer's
estimate the 6% is not an unreasonable amount. The unknown
question is will development and City projects be completed
within the context of the CIP. Other option's are to defer projects
from the CIP or pay for the improvements from the 1994
contingency account.
ALTERNATIVES:
Because there are three issues under consideration, there are
numerous options. They are:
l. Existing CSAH 42 Medians -
a. Make no payment
b. Pay the requested $93,500 or some lesser amount
Pa2"e 3
T
yo'
T .."
RECOMMENDATION:
ACTION REQUIRED:
AG718A,ENG
from the construction fund, Municipal State Aid, or
contingency fund, Payments could be spread over a
number of years recognizing that we have not
programmed these costs into our bonding.
2. CSAH 18/CSAH 42 Intersection -
a. Approve completion with standard medians.
b. Approve stamped colored medians and a funding
source for the additional $52,000 cost.
3. Urban versus Rural Design from CSAH 18 to CSAH 83-
a. Approve an urban section recognizing that City
costs will increase well over $1 million.
b, Approve rural section to assure that the basic road
improvements are accomplished in a timely manner
and encourage final urban improvements as
development occurs along this corridor.
There is no question that the City benefits from the roadway
improvements. Nor is there any question that the City of Savage
and/or Scott County should have obtained Prior Lake commitment.
Any payment the City authorizes should be drawn from a
combination of Municipal State Aid funds and from money not
expended by not installing lighting or landscaping on CSAH 21.
To promote a sense of completion and continuity at this important
intersection, staff recommends that we pay the $52,000 for
stamped colored median at Crest Avenue and CSAH 42
intersection. This will provide an opportunity for this median style
to be continued at some point in the future, if desired. The County
has indicated that they would be willing to wait until 1995 for
payment.
The segment of County Road 42 between CSAH 18 and County
Road 83 should be constructed in rural design. We should
continue to encourage the completion of these road improvements
in a timely manner, especially given the shift of completion date
from 1995 to 1996 for the segment from CSAH 21 to Crest
Avenue.
One or more motions dealing with each of the issues addressed
above.
I
h~Q 1 C,-
REVIEWE!'!JYf 1
Page 4
jT.tJ'
FERNDAjD i: i'
- \,
ttll~ :~ I
=~. ~
__,... ... u, .__
._-- .-- ... .,-! ,......
JL
~,
HI..'..
'\ "
"
!~ ~.
r
Ii" .
K. i . R
-r .
i&
~~ ,
II
_"..,;'7Ui;lniii \1-
-~ I
._~:);- I
~!!\'
1.11..-. I
6C.~!U.'~1I I
r .....I~.
~ .~~~e !
:l-~":---I~
._._-;;,,, ".
..-:::-;:-...:;:- ...
I:
,.~ '\"
-.......\.....--
,---
.. I --;-t;;; iilIb I.
~
II
II
_l~_ _. .u,. ..C 't.1 ._a
. I
---=0.:- ~
"' __ .nll 1_ UI I_a
...""...
,,:::'..-
-1-7-..... ..~I"II......
"
~r~
=ki.,
--.---.- 3
-QJ-,.; .
u( ~
Et'i", ..
~e' I \ I
, "
- -.N" I..'..........
r
("l
rn
>'
I = ~
j,. I ,
! I I :: ::: ~ .~J.. ii .~. ~ ~:~~~
:;~~~ I "11 lit. r I: _I
: \A :c -:\ ~ -. .. I I' II "::'.':":::-
; C; l~.,l\ jI-
! ~--:::: "'_ _ : ~ ~ I t:~
i ~..."............., :.: :r'U - --F-~::~
J '\~"" , ~~~:))( l~--;
1 ~",..,..." .\ ......., lit
~ : ';:~::;. "::-:," I, ....11 i
;: :~.:~. BEGIN S.... P 70-618-06
. .. ,M" U. ...... -I.l tt'l"
.............,..... I
........--:. ;:.:....:.:;,. :...:.;.......:.:.....;.........;.....:;.:. ....:.:-:::;:.:::;.::::.: I
-7"" 'L' ... ...,.:~: - -
'~J'u el .!:~:)
r\"'.'
m
t~~
~(~
i~
;>
..,
t'l>
~
'"
C'"
t'l>
:i'
I1Cl
/')
o
=
'"
c:
t'l>
~
Q.
0-
..,
n
o
0'
..,
t'l>
Q.
CI:l
-
;;
a
"0
t'l>
C.
n
o
=
/')
~
-
t'l>
3:
t'l>
C.
;'
=
-.0:.>- ~
Ie.u:
~:.~~ i
I" ...,
.....Iot$.at "I.... hU or
~_""(ecftJI.."~
\:
"J,~oo -
C.s.A.H. 18
.. '
rn ,..._._
~\ QJ'~"'.' QI......'...
8' IM.UI, lM.""
.'~ 1&111 lO""
~ 0).......... n. .@......... IH
nt.utI ,,,.,'u
In " n... ,I
.r'")
\'j
\-0
'~
t'l
2
o
":l
t'l
~
::
>
2
t'l
2
..,
("l
o
2
en
..,
~
~
("l
..,
o
2
!r
;I
,-
_I
..
-.
.
" .
....
.., y, 1.."4:.'
..