Loading...
HomeMy WebLinkAbout4H - PLFD Station #1 Oroject AGENDA #: PREPARED BY: SUBJECT: DATE: BACKGROUND: DISCUSSION: ISSUES: ALTERNATIVES: STAFF AGENDA REPORT 4 (h) (\(,~ FRANK BOYLES, CITY MANAGER "- CONSIDER APPROVAL OF CHAN E ORDER #2 FOR THE PRIOR LAKE FIRE STATION #1 PROJECT NOVEMBER 21, 1994 Fire Station #1 is being constructed. Council has previously considered andapproved change order #1 to the original contract. Attached is change order #2 in the amount of $4481 which is being considered for approval at the November 21 Council meeting. The attached change order includes seven items, four of which have been changed at no cost. The most expensive item provides for plumbing revisions required to conform with Minnesota Department of Health requirements. Two other significant changes include a revision in the sewer piping to comply with the city's heavier than standard piping thickness requirements. Also included is a change which adds lighting and ground fault protection to cover the radio system. I believe that these change orders are necessary and are for the most part relatively minor. Even with the change order, construction is within the original project budget. Council has the. following alternatives: 1. Approve the change order as requested. 2. Request additional information with respect to the change order. RECOMMENDATION: Alternate #1 is recommended. ACTION REQUIRED: Motion and second as part of the consent agenda to approve change order #2 to the Fire Station #1 project. AGN4G.WRT -1- 4629 Dakota St. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER '. CHAttGE . ORDER Distribution to: OWNER ARCHITECT CONSULTANT FIELD OTHER x AlA DOCUMENT G701 PROJECT: (name, address) Prior Lake Fire Station Prior Lake, MN CHANGE ORDER NO.: TWO (2) TO: (Contractor) Kratochvl Const. Co. P.O. Box # 27 New Prague, MN 56071 INITIATION DATE: October 25, 1994 ARCHITECT'S PROJECT ~O~: 1244.03 ...~..., CONTRACT FOR: Complete Construction CONTRACT DATED: AprU 26, 1994 You are directed to make the following changes In this Contract: 1. Proposal Request # 11, dated 8/31/94. as required by the City Inspector, $ 955.00 revise the sanitary sewer piping from SDR 35 PVC piping to SDR 26 PVC piping. ( Code Requirement) 2. Proposal Request # 12, dated 8/31/94. . Beefs - up. the turn out locker $ 404.00 frames with additional angles. ( Architect Requested ) 3. Proposal Request # 13, dated 9/12/94. Revisions to the Entry Towerframing. $ 326.00 ( Architect Requested ) 4. Proposal Request # 14, dated 9/8/94. Provides for plumbing revisions as per $ 1.185.00 the Minnesota Dept. Of Health. ( Code Requested ) 5. Proposal Request # 15, dated 9/15/94. Provides for an Electric Hand Dryer $ 517.00 In room # 132, ( Electrical rough-in Is under base bid. ). ( Owner Requested ) 6. Proposal Request # 16, dated 9/22/94. Adds lighting & grounding protection $ 926.00 system coverage to the radio system. ( Owner Requested ) 7. Field Order # 4, dated 8/30/94, Clarifys the locations of the floor outlets NO COST CHANGE In Training room # 109. ( Architect Requested ) 8. Field Order # 5, dated 9/1/94. Revises the layout of shower rooms # 118 & 120. $ 168.00 (Architect Requested.) 9. Field Order # 8, dated 9/15/94. Revises the layout & locations of the Tum out NO COST CHANGE racks In the apparatus bay. ( Architect Requested ) 10. Field Order # 7, dated 10/12/94. Clarification of Emergency Generator Exhaust NO COST CHANGE pipe pentratlon thru the SS sloped roof above. ( Mechanical Engineer) 11. Field Order # 8, dated 10/14/94. flip - flops the power/data/and telephone NO COST CHANGE rough In locations In Chiefs office # 109. ( Architect Requested ) The total cost of Change Order # 2, ( Items # 1.11 ), Including the G.C.'s O.H. & P = $ 4,481.00 Not valid untU signed by both the Owner and Architect. Signature of the Contractor Indicates his agreement herewith, Including any adjustment In the Contract Sum or Contract Time. The original Contract Sum was Net change by previously authorized Change Orders The Contract Sum) prior to this Change Order was The Contract Sum wDl be Increased by this Change Order The new Contract Sum Including this Change Order will be The Contract Time wll be unchanged. The Date cI Substantial Completion as of the date of this Change Order therefore Is November 30, 1994. Authorized: $ 1,518,760.00 $ 4,846.00 $ 1,523,606.00 $ 4,481.00 $ 1,528,087.00 . ..... ARCHITECT CONTRACTOR OWNER .~"", BKPR & ASSOC.. INC. Address 222 No. 2nd St.. MoIs. KRATOCHVIL CaNST. CO. Address P.O. Box 27. New Praaue CITY OF PRIOR LAKE Address Prior Lake Bya'\.~ BY BY DATE c:::::x::r '2..b( (~4 DATE DATE AlA DOCUMENT C701 * CHANGE ORDER * APRIL 1978 EDITION * AlA * 1978 THE AMERICAN INSTITUTE OF ARCHITECT, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 ------~----_.,--_.,------~~-..._------, ,-'"..", '_~"_"""'~"_".~--,'->.;....~.""..,---.._, ..