HomeMy WebLinkAbout4H - Maint Center Construction STAFF AGENDA REPORT DATE: 4H PAUL HOKENESS, PARKS & RECREATION DIRECTOR CONSIDER APPROVAL OF CHANGE ORDER NUMBER 2 FOR THE MAINTENANCE FACILITY MA Y 20, 1996 AGENDA NUMBER: PREPARED BY: SUBJECT: INTRODUCTION: The purpose of this agenda item is to authorize Change Order Number 2 for the Maintenance Facility. BACKGROUND: At the April 15, 1996 Council meeting staff presented a budget sheet w'hich included Change Order # 1 as well as a list of anticipated expenditures and savings. It was our understanding that the council concurrcd with this list but thc record shO\vs that only Changes Order # I was approved. not these additional items. To clarify the record and to bring the project completely up to date we are submitting Change Order #2 \vhich includes a portion of these additional expenditures as well as the additional changes which are necessary at this time so that we may construct the Salt/Sand storage building in the future. (Attached is the Agenda Report from the April 15th meeting which describes in detail the changes and additional expenditures.) In an effort to clarify the issues involved in the construction of the Maintenance Center and the Salt/Sand Building, I have treated them as separate issues. Though portions of the projects overlap. the main effort. at this point, is to complete the construction of the Maintenance Center. DISCUSSION: Change Order number 2 includes the following: 1. SOILS CORRECTIONS. (add $10,000) Soils corrections have been necessary to keep the project on schedule. This change order includes an additional 1.000 cubic yards of materials which have been imported to the site. As mentioned at the April 15th meeting there were poor soils discovered on site and we have run out of granular materials in the borrow site. It is anticipated that an additional 1,300 cubic yards of material will be needed to complete the project and we will submit a third change order to that effect when that time comes. 2. PROVIDE TEMPORARY HEAT FOR BRICK WORK (add $1,400) Due to extremely cold conditions this winter it was necessary to provide additional heat to keep the brick work on schedule. 3. PROVIDE SKYLIGHT ENDWALLS. (add $1,304) Somehow the endwalls for the skylights in the vehicle maintenance area had been CIINGORD2.DOC 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER deleted from the plans. Rather than fill this area with wood or metal it was thought best to order the clear endwalls which would match the skylight. 4. PROVIDE P AINTING AT MAINTENANCE SAY. (add $3,460) Painting of this area was not included in the original contract and it is felt that it would be wise to paint this area now while the walls are new and still clean. It would be more economical to have the contractor paint this area now rather than have our O\\TI crew paint in the future. 5. PROVIDE ELECTRICAL CONDUIT UNDERGROUND TO RUN TO THE SALT/SAND STORAGE BUILDING. (add $1,815) At the April 15th Council meeting the Council approved an additional $10,000.00 for the electrical wiring for the salt/sand storage building. At this time it is felt that it would be best for Rochon to install a conduit to the salt/sand building site from the main building. We will include the costs of mnning the wires and the electrical work in the eonstmction costs of the salt/sand storage building. 6. CREDIT ASPHALT PAVING IN SAL T/ SAND STORAGE BUILDING. (deduct $3,800) A credit was given due to the fact that the blacktop drivcway and floor of the salt/sand storage would not be provided at this time, as originally included in the Rochon contract. The first lift of blacktop would be installed to provide access to the maintenance facility and aftcr the salt/sand storage building is constmctcd the second lift and the interior floor of the facility would be laid. It would be done in this fashion so that we would not destroy our entrancc drive with the heavy equipment which will be used to construct thc salt/sand building. The additional blacktop work for the salt/sand building has bcen includcd in the construction cost estimates for that project. FISCAL IMPACT: This change order increases the contract amount by $14,179.00 when considered in conjunction with Change Order # 1, the net credit to the project budget is $11,707,00 bringing the total contract amount to $2,570,894.00. ALTERNATIVES: 1. Approve Change Order number 2. 2. Table this Agcnda item for a specific rcason. RECOMMENDA TI ON: 3. Dcny this Agenda item for a specific reason. Staff rccommends Alternative No. I. This allows staff to proceed with the projcct as scheduled. M~CO I to a ~ve Change Order numher 2. ACTION REQUIRED: REVIEWED BY: CHNGORD2.DOC May-14-9S 12:4SP OERTEL ARCHITECTS 612 824 7884 PoOl ~n~"uc ORDER OWNER ARCHITECT CONTRACTOR FIELD OTHER a o t:I o o ALA DOcUMEJ.7 G10J '- P~]ECT: Prior Lake Maintenance Building (name, address) Prior take, ,.,N TO CONTRACTOR: (name, address) Rochon Corporation 12866 Hwy. 55 Plymouth. MN 55441 CHANGE ORDER NUMBER: 2 DATE: Apri 1 14, , 996 ARCHITECT'S PR.OJECT NO: CONTRACT DATE: Sept. 19. 1995 CONTRACT fOil: General Construction The ConllaCt is changed as foUows: 1. Soil correction (1000 cy @ S10.00/cy). Add $ 10,000.00 2. Provide temporary heat for brick work. Add $ 1,400.00 3. Provide skylight end walls. Add $ 1,304.00 4. Provide painting at maintenance bay. Add $ 3,460.00 5. Provide electrical conduit underground to run to salt/sand storage building. Add $ 1 .815.00 6. Credit asphalt paving in salt/sand storage bull di ng. Deduct ($ 3,800.00) TOTAL ADD: S 14,179.00 ',-.. Not vlllld untl'algned by the Ow,.r, Architect and Conlractar. 1bc OriJinal (Concraa swn)(8..... I ~ Ja.....Ih:irz) ""Z . . . . . . . . . . . . . . . . . . _ . . _ . .. NCI c:hanFby pn::viously auchorized ChanlcOrdcrs . _. . _ _ _ . . . .. . . . . . . . . . . . _ . _ . . . . .. The (Conuaa Sum)(......bo r' L.l__._) priOltO rhIs Change Order was. . . . . . . . . . S The (ContClCl Sum) to----~Jaa:) will be (ina=s.ed) (....... 1) Cur- _ ')bydUsChanaeOrdc:rlruhumounlOr...... _.... . _..... " '" . ....1 The new (Canuxr 5wn) (fi__~ .. . __ RIIce) indudina this Change Otelcr will be ... The ConEnCt Time will be (lncn:asccl) (dcc:n:ziecS) (unchangcd) by The: date of Sub5W1Ua1 Completion as of me dar.c of tNs C1ansc Order thc:rcforr Is 2,582,601.00 ( 25,886.00) 2,556,715.00 , 4 J 1 79.00 2,570,894.00 ) days. ,.,o~ 'llW ""rnnary l2DI5 not reftas cNnaa in the Comtxl Sum. Conuaa Tame or GuuanlRd M.uimwn I'ria: whiCh ~ been 2uLharizcd by eon.s.n.a.Ion ChanSC Oireaivc. 8RW Elness ~Cjrd St. Rochon CorDoration CO~~wy. 55 Addres Plymouth, MN 55441 By ~;.-'I/III< DATE (,4I1k City of Prior Lake o..,.,~ 16200 Eagle Creek A~e. S.E. AdcIraa Prior Lake, MN 55372-1714 c: BY DAn AlA ~~ CIJ'In . CltAHGa OIlDEJI · IPI? Il:lfnQpI . AM- . C>I.., . THI! ~ II'IST1TUn: or AltCHlTliCTS. "JJ - YOIU( Ava.. Jl/."~ Wo\SKJHGTON, D.C. ZOllOlS G701-1987 REVISED MAINTENANCE CENTER BUDGET CHANGE ORDER #1 Soil Supplements Electrical Work Extra Silt Fence Extra Soil Testing Delete Sunscreen DEDUCT TOTAL $19,321.00 $5,242.00 $2,200.00 $266.00 ($52 915.00) ($25,886.00) CHANGE ORDER #2 Soil Corrections Temporary Heat Provide Skylight Endwalls Paint Maintenance Bay Provide Electrical Conduit Asphalt Credit DEDUCT TOTAL $10,000.00 $1,400.00 $1,304.00 $3,460.00 $1,815.00 ($3.800.00) $14,179.00 TOTAL OF BOTH CHANGE ORDERS ($11,707.00) SA VINGS/REVENUES Deduct From Above Change Orders Permit Fee Credit Balance in Contingency Balance in Furnishings $11,707.00 $20,484.00 $2.000.00 $5000.00 TOTAL + $39,191.00 ADDITIONAL EXPENDITURES Telephones / Computer Wiring Telephones - Equipment Fax Machine, Computer, Printer Soil Corrections $3,531.00 $9,746.00 $1,000.00 $13000.00 TOTAL - $27,277.00 TOTAL BALANCE + $11,914.00 AGENDA #: PREPARED BY: SUBJECT: DATE: INTRODUCTION: BACKGROUND: DISCUSSION: AGEND7B.OOC STAFF AGENDA REPORT 7B PAUL HOKENESS, PARKS AND RECREATION DIRECTOR CONSIDER APPROVAL OF INCREASE IN PROJECT COST OF $26,332.00 FOR MAINTENANCE FACILITY PROJECT. APRIL 15, 1996 The purpose of this agenda item is to receive Council approval for a change order and to request Council authorization to increase the maintenance facility project budget by $26,332.00. On August 7, 1995 the City Council approved advertisement for bids for the construction of a maintenance facility of approximately 45,000 square feet which included a salt/sand storage building. A bid opening was held on September 8, 1995 and fourteen contractors submitted bids. No bids were received for the proposed salt/sand storage building. On September 18, 1995 the City Council awarded bid to Rochon Construction for the maintenance facility with the understanding that the winning contractor would provide cost estimates to the city for the construction of a salt/sand storage building. As the project has proceeded, soil correction costs have been substantially more than originally anticipated. Some additional electrical work and silt fencing has been required as well. The purpose of this memorandum is to: 1. Approve Change Order #1 which is a total deduct from the project of $25,886.00. 2. Apprise the Council of potential changes in the total project cost. 3. Request that the Council consider allocating an additional $26,332.00 to the total project. PAGE 16200 Eagle Creek Ave. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER CHANGE ORDER #1 Change Order #1 from BRW Elness Architect, Inc. is attached. The Change Order contemplates four actions: 1. Electrical revisions amounting to $5,242.00 were needed to accommodate the heating system which was selected for the building. The heating system which was selected was in fact $21,500.00 less than the more expensive system. However, electrical modifications were necessary to install this particular system. 2. In order to conform with the City's erosion control policies and, because additional soil mining was involved in an effort to minimize soil correction costs, an additional $2,200.00 was required for silt fencing. 3. Soil corrections in this site have been well beyond that originally anticipated. The work that has been required thus far for the building amounts to an additional $19,321.00 over that which was originally anticipated. The necessity for this additional expenditure is described in greater detail in the ISSUES section of this report. 4. Additional testing was conducted to determine whether additional granular fill could be located on site rather than importing fill. (which costs more by contract). This testing is incorporated in the $266.00 addition. 5. Because of these cost increases and additional soil corrections the staff reviewed the project to determine what if anything could be eliminated. The original architectural scheme included awnings with the building. Since the windows are tinted to provide for cooling and reduce glare, the awnings are not a necessity and did not seem to be a wise use of construction dollars. We are recommending that the awnings be deleted for a total project credit of ($52,915.00). Attached is a Maintenance Center project budget which identifies Change Order #1 and reflects the $25,886.00 credit. Also shown is the credit which was granted by the City Council at the time of project approval which included the permit fee, plan check fee, and park support fee. This credit was also AGEND7B.DOC PAGE offered to the Fire Station and the Council believed it to be equitable to apply the same criteria to the Maintenance Facility. The original investment earnings included in the budget were $40,000.00 Because the project has taken somewhat longer than expected and because of our fiscally conservative estimates, it appears that an additional $55,000 will be available in investment earnings to assist in this project. Ralph indicates that the actual investment receipts may be closer to $95,000.00. (As of March 31, 1996 our investment earnings on this project were $70,759.00). The bad news is that there are additional expenditures required to complete the project which I have listed below and also explained in greater detail in the ISSUES section of this report: POTENTIAL CHANGES IN PROJECT COST Salt/Sand StoraQe BuildinQ One of the major cost increases for the project will be for the salt/sand storage building. The salt/sand storage building was initially expected to be a wooden, barn-like structure capable of holding 2,500 tons of mixed salt and sand salt. The original estimate for this structure was $100,000.00 Upon receipt of quotations from a storage facility contractor, the wooden building costs increased to $147,000.00. Considering the magnitude of that number, staff members asked the architect to obtain a figure for the same size building only constructed of tip up panels similar to the main maintenance facility structure. The bid received was in the amount of $167,000.00 Since receiving this news, the staff has been evaluating the need for a salt/sand storage building, its size and design. The number of conclusions have been reached: 1. There is little financial incentive to reduce the size of the structure since a 1,500 ton capacity tip up panel building has been quoted at $124,000.00 The smaller building, moreover, will result in additional mixing costs to the City as outlined in Doug Hartman's April 4, 1996 memorandum. (attached) 2. The wooden barn-like structure originally proposed, while somewhat less expensive will be susceptible to heavy equipment damage, rotting, and is higher maintenance. In addition, it has aesthetic disadvantage. (See attached photo of Eagan facility). AGEND7B.DOC PAGE ....~~.__._..w_.._..............._..~~_.__.____~.._._".,_".,._~~.._..,...~,..___,~.".....,..____"_~.__._.____.~~.~....'_.->..._.........._..,.... _...__...__...._.____..___.._.._.,.~_..______._..._._.~~,..__~~___.+.._.,.._.._.____,_._._,..,.__~.____._ 3. A 2,500 ton capacity tip up panel salt/sand building, while representing the greatest cost, appears to be the best investment in that it is resistant to damage by equipment, is capable of ready expansion when needed, and is aesthetically consistent with the maintenance facility. Additional Soil Correction Additional soil corrections in the estimated amount of $23,000 are required for the heavy vehicle driveway/parking area. PaintinQ Vehicle Maintenance Area The original bid award excluded painting of the vehicle maintenance area in the amount of $3,460. After reconsidering this issue, I believe that the City's best interest would be served if the vehicle storage area were painted along with the initial project. This is a reasonable dollar amount and would be much less expensive than our crew painting this area at a later date. Additional Heat For Brick Work Because of the intensely cold weather, additional heat has been needed to allow for the brick work to proceed. This has amounted to an additional $1,400.00 Other Three additional items are adds to the project which were not contemplated in the base bid. They include $2,000.00 for telephone/computer wiring, telephone equipment in the amount of $7,000.00 and a fax/computer estimated at $1,000.00 ISSUES: From a staff perspective, it appears that the only significant means of saving costs in the project are through the deletion of the proposed awnings. The Council should determine whether this is an appropriate action and if so, approve Change Order #1 accordingly. The soils condition in the Waterfront Passage Office Park have been documented to be bad. The natural question is therefore why wasn't the magnitude of the soil correction incorporated in the architects estimates and therefore in the contractors bids rather than having to be added at this point. While soil borings were taken on the site, the following factors contributed to these substantial increases for soil corrections. There were two deep pockets of poor soils which were found during excavation and were not identified in the original soil borings. This is not an uncommon occurrence in construction, AGEND7BDOC PAGE as soil borings are taken randomly throughout the site and it is not always possible to identify all poor soils. The costly portion of making these soil amendments is importing granular materials. We did not have enough borrow material on the site to make these soil corrections. The original budget included $30,000.00 for furnishings which was going to include furniture, phones, and office equipment. The furniture alone will cost approximately $30,000.00 leaving no additional funds for phones, office equipment and installation. The furniture which is being purchased for the building includes tables and chairs for the multi-purpose room and conference room, as well as desks and chairs for the supervisors and receptionist. The furniture which is being ordered is from the State contract and is very conservative, yet functional and durable. A salUsand storage building is not presently required by MPCA standards, however, we are required to control runoff which includes covering the pile. I believe it is reasonable to expect that such standards for building enclosures will be adopted within the next few years. While the City certainly may not be able to construct a salUsand storage building that meets its ultimate needs, it is important to construct a building which at least meets its current needs. Such a building should architecturally blend with the principal building on the site. This is particularly important since the ordinance requires that the building be either substantially screened from adjacent properties or roadways or consist of the same architectural materials as the principal structure. ALTERNATIVES: 1. Approve Change Order #1 2. Approve an additional expenditure of up to $26,332.00. 3. Defer action for further information. RECOMMENDATION: Alternatives #1 and #2. ACTION REQUIRED: Approve Change Order #1 and the addition of $26,332.00 to the project cost by a motion and second. FISCAL IMPACT: Because the project has been somewhat less expeditious than anticipated and because investment experience has been favorable, staff is anticipating that the investment earnings may cover all or the vast majority of the $26,332 project budget increase. In the event that this source would be insufficient the remaining funds would be taken from the sewer and water fund balance. Reviewed by: Frank Boyles, City Manager AGEND7B.DOC PAGE