HomeMy WebLinkAbout4H - Sand/Salt Storage Change AGENDA #: PREPARED BY: SUBJECT: DATE: BACKGROUND: DISCUSSION: FISCAL IMPACT: ALTERNATIVES: RECOMMENDATION: STAFF AGENDA REPORT 4H PAUL HOKENESS, PARKS AND RECREATION DIRECTOR CONSIDER AUTHORIZATION OF CHANGE ORDER #1 FOR THE SALT/SAND STORAGE BUILDING OCTOBER 21, 1996 Due to the fact that there were delays in finalizing the contract for the salt/sand storage building the bituminous portion of the building will not be completed until the Spring of 1997. The contract was refined in an effort to assure that it was fair to both the city and the contractor. The contractor (Hunerberg) has requested a change order in the amount of $518.1 0 for the reasons stated below. This change order has been requested for the following reasons: 1. Due to weather related reasons the contractor has to leave the job site following the construction of the walls and roof and will have to mobilize again in the Spring to complete the asphalt floor. The asphalt plants close down in the Fall. 2. Labor and material prices are adjusted in April each year and this change order represents the increases that the contractor will incur when completing the project in 1997. The additional $518.10 would be drawn from the sewer and water fund balance and would bring the total contract amount to $175,493.10 The Council has the following alternatives: 1. Approve Change Order # 1. 2. Table this Agenda item for a specific reason. 3. Deny this Agenda item for a specific reason. Staff recommends Alternative No.1. 1 / otion and second to approve Change Order number 1 for the / salt/sand storage building. 16200 ~&~l?fl~ve. S.E., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245 AN EQUAL OPPORTUNITY EMPLOYER Oct-10-96 02:31P OERTEL ARCHITECTS 612 824 7884 P.Ol . OERTEL ARCHITECTS 1422 WEST LAKE STREET / RAINBOW BUILDfNG / SUITE 312 MINNEAPOLIS, MN 55408 TEL: 612/825-6613 fAX: 6121824-7884 EMAIL: LLPB39A@PRODIGY.COM October 9, 1996 Mr. Paul Hokeness City of Prior Lake 16200 Eagle Creek Avenue, SE Prior Lake, MN 55441 RE: Prior Lake Salt/Sand storage Building OA #96-14 Dear Paul, Per your request, I am providing you the background related to the requested Change Order #1 from Hunerberg Construction. The contract documents were prepared and sent to bidders with a specified construction start date of July 9, 1996 and a completion date of October 4, 1996. Bids were received on July 1, 1996. On July 2, 1996, I recommended that Hunerberq Construction be awarded a contract. On August 5 the council approved awarding the contract to Hunerberg. Although it took several more weeks for the attorney to forward the contract with amendments to the city, I immediately notified Hunerberg of the city's intent to proceed. Had the contract been awarded by July 20, the window of opportunity would have allowed the contractor to complete all the work, including pavement, in fall of 1996. Because of the delays, the construction of the shell will now be pushed out to November/ December of 1996, and the asphalt plants will be long closed, forcing the contractor to perform the paving work in May of 1996. It is my opinion that the contractor is justified in the slight addi tional cost, as the schedule was extended into 1997. The contractor appears to be within the limits of the contract. If you have any further questions, please contract me. sincerely, A, CCS Manager 1 ~ c c HUNERBERG CONSTRUCTION COMPANY New Construction · Residential/Commercial Remodeling . September 24, 1996 Jeff Oertel Oertel Architects 1422 West Lake Street # 312 Rainbow Building Minneapolis, MN 55408 Re: Prior Lake Salt/Sand Storage Building Request for change order We are requesting a change order for the bituminous paving section of the project. The contract was not received until September 5, 1996. This has pushed back the entire schedule and will not allow us to complete the bituminous this year per the schedule in the specification book. I have attached a copy of our subcontractor proposal showing the added cost for work completed in 1997. The following is a breakdown of the cost related to this change order. Pine Bend Paving Inc. Hunerberg Construction Company 10% profit and overhead $471.00 $47.10 Total add. $518.10 Please issue a change order in this amount to be added to our contract of $174,975.00. Sincerely, /\ 1 '~I::l-4k",-,-~ / ~hn J. Hunerberg 0 ... ..... -,. ~ ~.. ,,.... ^\ ,..,-^ ^^'"^ . ~_.. I:'I:'~ nnon CHANGE ORDER O\"'NER ARCHITECT CONTRACTOR FIELD OTHER ...tIA DOCCJIEST C-O! c c c: r-- W r; PROJECT: "0. L' S 1 t/,.... d ~rlOr aKe a~ ~an (name, address),.... t 3 . 1 ~ . ;:) orage . Ul c.lng TO CONTRACtOR: . rt~nerberg Constructlon CO. (name, address) 1 37 a 5 2 6 t h A v e . N. if: 10 J P1y~outh, ~N 55441 The Contract is changed as follows: CHANGE ORDER NUMBER: 1 DATE: 3epte~ber 30, 1996 ARCHITECT'S PROJECT ~o: 96-14 CONTRACT DATE: 8/6/96 General Constructi~~ CONTR--\CT FOR: To oerform the 9avin~ in s~ring of 1997, there is an add of $518.1J t~ the contract: . Refer to attached Hunnerberg letter of 9/24/96 for additional information. Not valid until signed by the Owner, Architect and Contractor. The:: origin~J (Comr~ct Sum) (Gu~l.mtee::d ~laximum Price) W:lS . . . . .. ................. S Net ch:mge:: hy previously authorized Ch;mge Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . S The (Comr:xct Sum) (Gu:Il.lmeed Maximum Price) prior to this Change Order ~l:L.-;. . . . . . . . . . S The:: (Comr:lct Sum) (Guar:.uueed ~laximum Price) will he:: (incre:lSel1) (decre:lse::d) (unchanged) hy this Ch~nge Order in the:: amoum of . . . . . . . . . . . . . . . . . . . . . . . . . . . . S The new (ComrJct Sum) (Gu~r:lmee::d :Vla.ximum Price) including this Change Orde::r will he:: .. S 174,975.00 a.GO 174,975.00 518.1) 1 75.49 J. 1 J - ------------...-- 24J days (2d) ld;ty" June 10, 1997 . The:: Comr:lct Time:: will he:: (incre:L-;e::dl (de::cre:::lse::d) (unch;mge::d) hy The date of SuhstJlltial Completion ;1.-; of the <.bte of this Ch:mge:: Ordc:r rl1e::ret()re is :\OTE: TIllS 'ollllllllary dlle..::--. nll( n:tlc..:cf I..'hangL':'i in [he..: ClImr.ll"t :'>lllll. ClIlllr.1L.[ Time..: llr (;ll:lraIUL'c.:d .\bxiIllUIl1 Pnl.'l: ",hldl l1a\'L' heen ;llIlhllrt/nl In (:llll....rnll.ti< In (:hallgc..: Din.:l"tin:. OERT'ST. ARCHIT~CT3 .\H(:! IITE(:T HUNERBERG CON3TRlJCTION CITY OF PriIOR LAK4:: CO:\Tlt\CTOI{ O\\':\!:I{ AddrL"'o'" Add res.'" BY BY P~././77[~ / [)An: mJ [) .-HE CAUT10N: You should sign an original AlA document which has this caution printed in red. An original assures that changes will not be obscured as may occur when documents are reproduced. AlA DOCUMENT G701 · CHA:>i(iE ORDER · I'JX- EDITIO:>i . .-\IA~ .i;I')x- . THE .\~IERIL\:>i 1;\:~TITtTE OF .-\RCHITECTS. l-~;; :\E\X' YORK .-\\'1::.. :\\X'. \l"--\SHI:\CTO:\. D.c. llNN'h G701-1987 WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution, .--.. -- ~1/el/199S 19:36 6124377960 PINE BEND PAVING PAGE ell '1)-- PINE BEND PAVING INC. P.o. BOX 238 I- :~~.~3=AUL, MN 55075 . FAX: 437-7960 ~AT~ ~;. ~...J_~ l:. 9 Co . FAX QUOTATION PROJEC~ 2~~~ ZS+~.D LOCATION ~ L..~ __ SECTION ADDENDUM . I ALL MA~"IALS 70 BE FURNISHED AND INSTALLE~ AUA 1: - $.)je / 9!]!; ~" AW~reCate 8ase Class 5 ~ S!QP/GraveI Limestone ur Recycled -~" Bi tuminous .n~/B1nder COU,'se ~~~ 2331/2332 _.~ 2341 _ J6; .. BttWDinous .w~ Course MNDOT 2341/2342 ~ 2341 Mod 2361 4'. -. . .. ~ I _ I .. I 1 ' . , --- SQ. YDS. Cone .' AAE.4 2 : s " Al'crecate Sand/O,.a:ve I " Bitu.inous MNDC)T 2331/2332 t. 8 J t uIII1 no MNOO"T 2341/2 SQ. YDS. Cone. Stripinc Included --t}~(or add S to price) , · #' 1_ "0.0 ~~tQ.YU'9-= <.20 ~.~ ,~ ) COMMENTS. ~\..1'.~ Ji 110 (oJ. .. rt ... (;dz..- a ~11 1100, 97 ~ ) ~ All work to b. C~.ted in accordance with industry standards and applicable MNDOT SpeCifications. Prices inalude a J J tax e s . ~o IV} 5Z.~ (Price tir= tor 30 days) TOTAL "COS7: S T h"1'Vo~.., t. or ,. ~ JOE .J 'CWf ~, '- ~..: ..... I. · . ,...,,-1... -"'i~ -,' . r.,' '. ~ ,... ""!' -.,' I" ... ... w- the opportunity to provide thia quotation. :;. ;MblJehed tin" .......