CITY COUNCIL AGENDA REPORT
MEETING DATE: NOVEMBER 12, 2013
AGENDA #: 10D
PREPARED BY: JERILYN ERICKSON, FINANCE DIRECTOR
JANE KANSIER, ASSISTANT CITY MANAGER
PRESENTED BY: JERILYN ERICKSON & JANE KANSIER
AGENDA ITEM: CONSIDER APPROVAL OF A REPORT REGARDING A CONTRACT FOR AN
ENTERPRISE RESOURCE PLANNING (ERP) SYSTEM.
DISCUSSION: Introduction
The purpose of this agenda item is to address questions raised by Council
members during the October 28, 2013 workshop regarding the ERP software
vendor and, if all questions have been satisfied, to request approval of the
agreement with BS&A for an ERP system.
Histo
The City maintains $187 million in total assets, along with an annual budget of
$26+ million. To effectively manage these assets and budgets, the ability to track
expenditures and revenues in real time, to identify trends, and to create long term
budgets and forecasts is imperative. The City's current 1984 vintage financial
system is limited in some of these capabilities. Therefore, the City Council
authorized staff to begin the ERP software selection project in November, 2012.
The Council approved a tentative timeline in December, 2012, to assist staff as we
moved forward with the project.
A Request for Proposals (RFP) seeking proposals from qualified software vendors
was released on July 1, 2013, using these parameters. The RFP focused on the
need for two core modules: Financial and Human Resources. The groupings
within these modules included:
General Ledger, Budgeting, Purchasing,
Accounts Payable, Accounts Receivable,
Cash Recei ts, Pro'ect Accountin
- Human Resources (Employee File),
,; �� = Pa roll
These modules are necessary to address the most critical challenges in the
current environment. Future functionality and modules may be considered in later
phases.
Three vendors submitted proposals and were selected to do product
demonstrations in early September. Each vendor had two days in which to
demonstrate the functionality of their software.
An Evaluation Team, consisting of a cross section of City staff, scored each of the
products and narrowed the selection to two vendors. The team then called
references for each of the vendors to discuss software functionality,
implementation approach and ongoing customer service. At this point, the scores
were very close and the Evaluation Team asked the preferred two vendors (BS&A
and New World Systems) to do an additional demonstration for very specific
functional requirements defined by the staff. Both preferred vendors were also
asked to walk through their respective cost proposals for software licensing,
implementation services and recurring maintenance to gain a greater
understanding of these proposals and to be certain we would only pay for those
functionalities we need at this time. These demonstrations and discussions were
completed on October 23, 2013.
Several City staff have been involved throughout this process. A Project
Management Team, consisting of Administration, Finance and Technical staff, has
been leading the project from the beginning. The Evaluation Team includes the
Project team and additional Finance, Community and Economic Development and
Engineering staff. In addition, up to 20 staff from all sectors of the organization
attended parts of each product demonstration and provided their feedback that
was considered by the Evaluation Team. This cross-sector involvement is critical
because, even though the ERP system is primarily a financial system, one of the
goals of this project is to ensure the system provides efficiencies and process
improvements wherever possible across the entire organization.
Current Circumstances
Based on the point totals, the Evaluation Team recommends the City contract with
BS&A to provide the ERP system. The BS&A proposal for software and
implementation is $214,190. These costs include:
Software (includes discounts) $ 98,955
Data Conversions $ 47,610
Interfaces $ 21,000
Project Management $ 8,750
Implementation & Training $ 27,000
Post Go-Live Assistance $ 3,000
Discounts $ (5,000)
Travel $ 12,875
Total $ 214,190
Annual service fees will be waived for the first year of use after the software is
implemented. Beginning in year 2(2015), the City will incur $26,210 (or some
portion, thereofl in annual service fees, as shown in the table below. In year 3,
service fees may be increased by an amount not to exceed the yearly CPI.
�
General Ledger/Budgeting.NET $ 0 $ 2,500
Purchase Order.NET $ 0 $ 2,130
Accounts Payable.NET $ 0 $ 2,130
Cash Receipting.NET $ 0 $ 2,130
Miscelianeous Receivables.NET $ 0 $ 2,130
Fixed Assests.NET $ 0 $ 2,130
Human Resources.NET $ 0 $ 2,500
Payroll. N ET $ 0 $ 2, 750
Timesheets.NET $ 0 $ 1,530
Special Assessments.NET $ 0 $ 1,400
Employee Web Portal $ 0 $ 2,750
Purchasing Web Portal $ 0 $ 2,130
ANNUAL TOTAL $ 0 $ 26,210
At its workshop on October 28, 2013, the City Council directed staff to move
forward with contract negotiations with BS&A by addressing a number of issues.
Conclusion
The staff is continuing to finalize the contract with BS&A. The contract which is
the City's standardized document will need to be reviewed by the City Attorney.
The staff recommends the Council continue this item to November 25, 2013.
ISSUES: The Council asked the staff to further explore the following list of questions.
1. Split out traininq and implementation costs.
The staff, along with BerryDunn, are continuing to work with BS&A on the
appropriate way to manage this in the contract. BS&A has agreed to allow
reallocation of any training in the pool without penalty.
2. How are reqular updates (in the operations phase) tested? Who does the
testinq?
BS&A offers biweekly updates, but the updates are not mandatory. Unit
testing on all updates is built-in and completed by BS&A prior to the release of
any update. The issue with updates is generally in customization, and the City
does not expect to have any customizations to the software. On the user side,
the process for updates will be very similar to what users see with Adobe
updates. A message will be provided at login, and the user simply clicks install
to receive the update.
3. Attempt to get a cost not to exceed auote on each.
Where appropriate, the contract includes the not to exceed language. In most
cases, the City will be billed for the time used, so costs may be less than noted
in the contract.
4. What do BS&A staff qo throuqh for background checks as it relates to
accessibility to sensitive Citv information?
BS&A has agreed to provide the City with a copy of their privacy agreement
but we have not received it as of this date. The hiring process at BS&A
includes background checks, reference checks, and a 90-day internship prior
to obtaining full-time status.
5. Obtain a recently completed SAS70/SSAE16 report.
BS&A has agreed to provide a copy of this report, but we have not received it
as of this date.
As the Council is aware, the implementation of this new system will be a 12 to 18
month process. During that time a variety of other contracts are coming up for
renegotiation. So that we can focus upon the ERP System, the staff would like to
defer the various projects identified below until completion of the ERP.
�R�i,� � ��� r -U _ -
� � h ��� ���
I� �
Banking Services 2010 — 2013 with 1 one- Staff will review an
US Bank 2009 year extension (through extension of the contract
2014 . throu h 2016.
Audit years 2011-2013;
Auditing Services contract allows for Staff will review an
MMKR 2011 extensions for additional extension of the contract
periods as deemed for audit years 2014-2016.
a ro riate.
Staff will need to consult
IT Services with software vendor, CIT,
Computer etc. to determine how
Integrated N/A Month to Month much additional IT
Technologies resources will be needed
(CIT) during the implementation
and the associated timing
of those resources.
Consider
Financial Advisor issuing N/A Defer as necessary.
Services RFP in
2015
Current contracts expire Will still need to negotiate
Union Contracts N/A 12/31/2014. (in 2014) for contracts
be innin 01/01/2015.
FINANCIAL The initial staff estimate for the ERP System (software only) was $350,000. As a
IMPACT: result of the BerryDunn assessment, this number was revised to $460,000. The
estimate does not include the cost of the software selection consultant ($63,275),
hardware upgrades required by the system ($35,700), or consultant
implementation assistance ($200,000). If all of these elements are included then
the total estimated cost is $514,575.
These estimated cost are more completely laid out below including the likely timing
for payment:
,
i i� . ���� � ... _ _
I f, � �
�N 41K �
Selection Assistance Consultant (BerryDunn) $ 63,275 2013
BerryDunn Additional Work $ 1,410 2013
Initial Software and Implementation $ 214,190 2014
Project Manager Services (estimate) $ 150,000 2013-2014
Additional IT Services (estimate) $ 50,000 2014
Hardware (receipt printers, etc.) $ 4,700 2014
Laptops for training $ 6,000 2014
Network equipment (servers) $ 25,000
TOTAL $ 514,575
These costs will be incurred over time. For example, the initial software selection
consultant costs will be completed in 2013, while the software costs will not be
billed until the 2014. Other costs will be incurred over 2014.The approving
resolution will address the various funding sources to complete this project.
Staff received multiple proposals for project management services. The cost
came in higher than anticipated; therefore, Staff is reviewing options to assure we
receive the services which are prerequisite to effective implementation most cost
effectively.
ALTERNATIVES: 1. Continue negotiations on the ERP Contract with BS&A and bring this item back
to the City Council on November 25, 2013.
2. Direct the staff to investigate and provide responses to additional City Council
questions.
RECOMMENDED Alternative 1
MOTION: