CITY COUNCIL AGENDA REPORT
MEETING DATE: FEBRUARY 10, 2014
AGENDA #: 5G
PREPARED BY: LARRY POPPLER, CITY ENGINEER / INSPECTIONS DIRECTOR
PRESENTED BY: LARRY POPPLER
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION AMENDING THE PROFES-
SIONAL SERVICES CONTRACT WITH WSB & ASSOCIATES FOR THE
RIDGEMONT / MAIN AVENUE / TRUNK HIGHWAY 13 IMPROVEMENT PRO-
JECT (CITY PROJECT #13 -001)
DISCUSSION: Introduction
The Ridgemont / Main / TH 13 project is mostly complete and open for traffic.
Several unforeseen items have increased the need for construction oversight.
This agenda item seeks council approval to amend the contract with WSB & Asso-
ciates to provide the professional services to see this project to its conclusion.
History
On September 10, 2012, the City approved a professional services contract in the
amount of $190,987 for the Ridgemont/Main/TH 13 project. This included the Pre-
liminary Design, Plan design, Bidding, and Construction.
On December 4, 2012, the City learned that we were successful in securing addi-
tional dollars, $674,763, for this project in the form of the "MNDOT Cooperative
Agreement Program ". This additional funding will reduce the amount of City Mu-
nicipal State Aid and City Tax Levy which was planned for this project.
On June 10, 2013, the City Council amended WSB & Associates contract adding
$28,533 to the contract for administration relating to the Cooperative Agreement
Program funding.
Current Circumstances
Attached is a letter request from WSB & Associates for an amendment to the pro-
fessional services agreement for additional services related to the project. WSB &
Associates cites contractor delays, community building changes, delay in ap-
proved signal wire, and entry monument transmission complications as reasons
for the increase construction management on this project. The total amount re-
quested is $26,477.
The late season construction on this project has left a number of items which still
need to be completed. These include the following:
1. Installation of landscaping
2. Signal system completion
3. Parking lot construction
4. General cleanup
5. As -built drawings
6. Project closeout with MNDOT
Construction management is needed for this work in order to finalize this project.
The amendment requested will provide for the project management needed to
complete the project.
Conclusion
It is recommended that the City Council approve an amendment to the profes-
sional services contract with WSB & Associates.
ISSUES: Contractor production rates are cited in the WSB & Associates letter. Last fall, this
contractor was working on other projects within the City as well. Several of these
projects were not fully completed. The Sunset Avenue Project for example is still
not substantially complete. The contractor did fulfill their obligations under the
contract for the Ridgemont Project, however, the production rates lead to addi-
tional construction days and time needed by WSB & Associates to provide con-
struction oversight.
It was intended that the new signal system be operational by November 1st, 2013.
MNDOT rejected the wiring materials for this signal and others within the Metro
Area last fall. New wire has been manufactured and is now ready for installation.
In January the contractor attempted to complete the work with the new wire, how-
ever due to the frozen conditions this work must wait until spring.
The downtown sign, while installed cannot be programmed until final fiber splicing
is completed and signal converters are installed. The work involved is not sub-
stantial, however the colder than normal temperatures have delayed the final work.
A break in the weather is needed to complete these final tasks.
FINANCIAL The City has expended $2,081,000 to date on this project. The overall budget is
IMPACT: $2,427,000. WSB & Associates anticipates a $150,000 savings in the construction
contract due to field adjustments and quantity revisions. The most notable is the
reduction in subgrade excavation.
To date the City has expended the full $219,500.75 contract amount with WSB &
Associates for this project.
ALTERNATIVES: 1. Approve a resolution authorizing an amendment to the professional services
contract with WSB & Associates for the Ridgemont / Main Avenue / Trunk High-
way 13 Improvement Project (City Project #13 -001)
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED Alternative #1
MOTION:
o`� P O AP
ti
u
4646 Dakota Street SE
ivivEsol Prior Lake, MN 55372
RESOLUTION 14-xxx
A RESOLUTION AMENDING THE PROFESSIONAL SERVICES CONTRACT WITH WSB AND
ASSOCIATES FOR THE RIDGEMONTIMAINITH 13 IMPROVEMENT PROJECT
Motion By: Second By:
WHEREAS, On September 10, 2012, the City of Prior Lake entered into a professional services
contract with WSB and Associates for general engineering services which included
preliminary and construction engineering for the Ridgemont/Main/TH 13 project; and,
WHEREAS, The contractor work schedule, community building changes, delay in approved signal
wire, and entry monument transmission complications has caused an increase
construction management on this project; and,
WHEREAS, WSB & Associates has provided a letter dated January 23, 2014, detailing the added
services.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The professional services contract with WSB and Associates for the Ridgemont/Main/TH 13 Project is
hereby amended to include additional services as discussed in the January 23rd, 2014 letter from WSB
and Associates.
3. The amount of the professional services contract with WSB and Associates for the Ridgemont/Main/TH
13 Project is hereby increased by an amount not to exceed $26,477.00.
4. Funding for these engineering services will be funded by the Construction Fund for this project. The
Construction Fund #501 - 48376 -505 will be amended for these additional services.
PASSED AND ADOPTED THIS 10TH DAY OF FEBRUARY 2014.
YES NO
Hedberg Hedberg
Keeney Keeney
McGuire McGuire
Morton Morton
Soukup Soukup
Frank Boyles, City Manager
WSB
& Assoc- engineering • planning • environmental • construction 701 Xenia Avenue South
Suite 300
Minneapolis, M11 55416
Tek 763.541.4600
Fax: 763 - 5414700
Jamtary 23, 2014
Mr. Larry Poppler
City Engineer
City of Prior Lake
4646 Dakota Street SE
Prior Lake, MN 55372
Re: Main/Ridgemont Avenue/TH 13 Intersection Improvements
Request for Extra Services Construction Services
City of Prior Lake, MN
WSB Project No. 2020 -01
Dear Mr. Poppler:
I am writing as a follow -up to my conversation and emails requesting consideration for
additional construction service for expanded and extended services that have and will be incurred
to complete the construction and project close out with MnDOT. The main impact to WSB &
Associates, Inc. (WSB) construction services has been the lack of adequate staffing by the
contractor. Chard Tiling and Excavating did not adequately staff the project which leads to lower
than industry standards for production rates. Also compounding the schedule was the delay in •
final approval of the new building facility and the unavoidable delay caused by MnDOT's
rejection of signal wire which has pushed the final completion of the project into the spring of
this year. The City Cooperative agreement requires full -time inspection and documentation of
construction activity for all aspects of the project. With the lack of adequate contractor
construction crews which resulted in reduced production rates, WSB's time in the field was
significantly impacted requiring additional field and office staff time on the project. In addition,
the parking lot construction delays and increased inspection and coordination required for the
building led to additional time required on the project. Also, due to the communication
compatibility issue that arose with the two (2) entrance monuments, led to the need to request
additional construction inspection services. Attached is a brief description of the additional
services and associated fees for your review and approval.
Early in the design process, it was discussed how to handle extra work items, and it was decided
to handle them as the project developed by notifying the City and keeping track of the costs to
evaluate the extra services as the project nears completion. The Main/Ridgemont Avenue/TH 13
Intersection Improvements is not a complicated project; however, the lack of contractors
production rates, delay in approved signal wire, building approval and foundation construction
delays, and the complications with the data transmission requirement of the new entrance
monuments, all have impacted WSB's ability to complete our work on the schedule originally
developed for the project. At this time, we are requesting that additional construction services be
allocated to the project to cover the additional services during the later phases of the construction
for unavoidable construction delays. WSB has worked hard to reduce the actual construction
St. Cloud • Minneapolis • St. Paul
Equal opportunity Employer
wsbeng.com
K..1fi02091f/Ad lkcaltq Serice$LTR•tpopper extra •.kOI411 do:
Mr. Larry Poppler
January 24, 2014
Page 2 of 2
costs which to date we have been able to reduce the costs by over $150,000 to the city. WSB is,
hereby, requesting that $26,477 in additional construction services be added to our contract. ;.
Again, it was a pleasure working with the City on this project, and we look forward to successful
completion of construction of the new intersection this spring.
If you have any questions or require additional information, please call Mr. Don Sterna, Project
Manager, at 763 - 287 -7189.
Sincerely,
WSB & s o at ACCEPTED BY:
City of Prior Lake ;.
Donald W. Sterna, PE Name
Vice President
Attachment Title
Date
EXTRA WORK ITEMS
The following is a brief summary of the extra services and associated costs ineurred during the
construction phase of the project for your review.
1. Kop Park Building and Parking Lot: The City added the construction of the building
foundation for the new Park Building to the construction contract which WSB
administered, inspected, and surveyed the site for construction. WSB also coordinated
with Xcel and CenterPoint Energy to extend both electric and gas services to the
building. The building foundation size was modified several times to accommodate the
future user's size requirements. Therefore, the building site was staked several times as
the exact size, location, and elevation were modified to fit the needs of the community.
Also the delay in finalizing the building size, building authorization, and the addition of a
•
sanitary sewer stub required the parking lot to be staked several times as the site
conditions changed. The construction delay also has pushed the final completion of the
parking lot, lighting, and site restoration into spring of 2014 requiring additional field
inspection time •
WSB is requesting $5,945 in additional compensation for performing this work.
2. Contract Delays Impacts: WSB's original proposal assumed all construction was to be
completed including the landscaping and turf establishment in 2013. Several delays
outside of WSB's control have delayed the completion of the project until the spring of
2014. The contractor's ability to provide the proper staffing levels has extended the
construction timeline requiring additional staff time in 2014 to complete the project.
Since MnDOT is approving State funding into the project, full -time inspection,
documentation, and testing is required. The lack of average production rates have
significantly impacted the time that WSB's staff is required to be on site. Also, the
unavoidable delay due MnDOT's rejection of the signal wire has significantly extended
the timeframe to construct the signal system. The extended construction timeframe has
required WSB staff to incur more field time monitoring and coordinating with MnDOT
on the roadway and signal construction.
WSB is requesting an additional $17,774 in additional compensation for this expanded
construction timeline.
3. Entrance Monument Coordination: During the construction of the Entrance
•
Monument, it was discovered that the data transmission conductivity was not compatible
between the electronic sign and the communication wire supplied to the sign. Both the
City and WSB were lead to believe the data communication line being supplied by Zayo
(Formally Access Communications) was compatible to the digital signs. Once the work
was completed, it was discovered that additional transmission equipment was required to
convert the data signal from Multi -Mode to Single -Mode in order to connect both the
existing Arcadia Monument and the TH 13/ Main Monument with City Hall. Several site
meetings, numerous phone calls, and coordination between the sign manufacture and the
communication service provided was required to correct the problem.
WSB is requesting an additional $2,758 in additional compensation for this expanded
scope of work. •
•
Extra Work Items Page 1
•
A. Estimate of Cost
14'SB MAIN/ RIDGEMONT AVE/ TH 13 IMPROVEMENTS
& Lale PRIOR LAKE. MNNESOTA
ADDITIONAL CONSTRUCTION SERVICES
Oate I/23/I4
A.) PLAN DESIGN PHASE ! .
Project Field Signal 1 Field Survey Total
Manager I Engineer Inspection : 2 -Person Crew Sr. Tech Clerical Hears Cost
Task Adtripffoa Coor � . .._... - I. __....._.. ......._ - ._._.. — _. — .- -: - -.._._�-- _....._...._ ... ... .
- --
1 KOP PARK BUILDING and PARKING LOT i
A$roidiagCoordn " r Daeomon:do 6 n r .. ----8'_ L. _. _
..
_. . —.. 1 '� o -...�- _ --- __ —_1 6 --_.. — . � _ 52374.00
&Pall Lot andBandia6Stn r1Restaitit ._. ._._.__.. ._-- T-------- - -...1 2 ` y .- -_.- ....._ .....__� _____- _— sI.372Ao
t
C. U61i , d nation 6 2 _ - -_ -. — — 2 — 1 I I 51.309.00
D. l'arking Lot Inspection/ Doanmentation �_........_............. - - -. —_.. B —._ 1 f 1 ___I 1 10 — — 5890.0 r
SUBTOTAL 12 13 1 I 8 1 11 1 4 53 $5.945.00
2 CONSTRUCTION DELAY IMPACTS r
1 - A. Si al Inspauon ,—,_ - --_- -- _--___4. _ .. 16 _ 6 S1,352.00
B.Coraracto!Dday IO 120 1 24 2 1_56 515.922...
SUBTOTAL 12 120 16 24 2 162 517.774.0*
_._ 3 . ._._— Entrance Monument Coordination .._.__.�-! I _.,. _ _
a Cotorl Zay_o Coordination .._ ..__ _ ._. 16 a ! ._ _ ._._ .. I. ? 32 __S2.768.00
I 1
r
SUBTOTAL 16 1 4 , 1 _ 1 2 22 52.758.00
Toms Hoerr 40 142 16 32 11 3 237 . $26.477.∎ 1 1 90.00 ! 98.00 i 149.00 ' 107.00 1 63.00
r r 1p Costc 142 Cosh 55,680.001 512.780.00 1 51668.00 1 $4.768.00 51.077,001 5504.00 S26,477.00�
of Design Labor 526.477.001
bowl Design Phase 1 1 526,471001
Main Street- Rid9emont Ave extra Constitution services 1/23(2014