Loading...
HomeMy WebLinkAbout9A - Highland/Marsh/Skyline/Eau Clair/Grainwood O� PRIp� U 4646 Dakota Street SE Prior Lake_MN 55372 NNFiso, CITY COUNCIL AGENDA REPORT MEETING DATE: NOVEMBER 10, 2014 AGENDA#: 9A PREPARED BY: KATY GEHLER, PUBLIC WORKS DIRECTOR PRESENTED BY: KATY GEHLER, PUBLIC WORKS DIRECTOR AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING THE FEASIBIL- ITY REPORT AND SCHEDULING A PUBLIC HEARING TO CONSIDER THE IMPROVEMENT OF HIGHLAND, MARSH, SKYLINE, GRAINWOOD, AND EAU CLAIRE. DISCUSSION: Introduction The purpose of this agenda item is to accept the Feasibility Report and schedule a Public Hearing to be held on November 24, 2014 for the im- provement of Highland, Marsh, Skyline, Grainwood, and Eau Claire. Histo Each year the City reconstructs street segments that are scheduled for re- construction as part of its Capital Improvement Program (CIP) and have ex- ceeded their useful design life. The City uses the Capital Improvement Pro- gram and its Pavement Management Program to plan for infrastructure im- provements and the financing for capital improvements. Special assess- ments were planned to be part of the financing for this projects. Minnesota Statute Chapter 429 identifies a process that applies to all projects that will be financed in whole or in part through special assessments or bond pro- ceeds. At its August 25, 2014 meeting the City Council adopted Resolution 14-125 and 14-126 authorizing staff to prepare a Feasibility Report for the Improve- ment of Highland, Marsh, Skyline, Grainwood, and Eau Claire which is the first step in the 429 process. The next step for the Council to accept the feasibility study and call for the Improvement Hearing. At the Improvement Hearing, interested persons may voice their concerns, whether or not they are in the proposed assessment area. A reasonable estimate of the total amount to be assessed and a description of the methodology used to calcu- late individual assessments for affected parcels must be available at the hearing. Current Circumstances The 2015 Road Reconstruction Project includes three distinct areas. The first is what is known as the Fisher Farm area on the west side of County Road 21, the second is the Grainwood area on the East side of CR 21 and the third is north of Grainwood along Eau Claire and 154th. These three are- as will be considered separately for the purposes of assessments, however the construction contract is recommended to include all three to provide cost, scheduling and project administration efficiencies. The Fisher Farm and Grainwood areas were both platted in the late 70's with the road and utility infrastructure being installed in 1977. These areas lack curb and gutter and storm sewer which were recommended in the Feasibility Report. The road and utility improvements along Eau Claire and 154th were installed slightly later in 1983. A map of the project area (Figure 1) is includ- ed in the Feasibility Report. The proposed improvements consider replacement or addition of street, storm sewer, storm water quality, sanitary sewer, watermain, concrete curb and gutter, and appurtenant work depending on the existing conditions. The Feasibility Report includes total estimated costs, preliminary assess- ment amounts, and a project financing summary. Also included in the report are design criteria, estimates and information on watermain, sanitary sewer, storm sewer, and streets. Details on each can be found in the Feasibility Report. A neighborhood meeting was held on October 23, 2014 to provide residents input on the project, most importantly sharing problems or issues they have observed. In addition the engineer reviewed the standards and potential op- tions being considered with the project. Conclusion In summary, the project is feasible from an engineering and economic standpoint. Approval of the Feasibility Report is the next step in the 429 pro- cess and does not grant final approval of the project. If the Council accepts the Feasibility Report, the Chapter 429 special assessment statute requires the Improvement Hearing be conducted before the City Council considers ordering the project. A public hearing is proposed for November 24, 2014. At that meeting the proposed improvements, project schedule and assessments will be present- ed to residents. ISSUES: The Assessment Review Committee met on October 28th, 2014, at which time the assessment map, assessment method and assessment amounts were discussed and recommendations made. Results of the discussion and recommendations will be shared with the Council. FINANCIAL The 2015 Road Reconstruction Project is proposed to be financed by Spe- IMPACT: cial Assessments, tax levy, Sewer Fund, Water Fund, and Water Quality Fund. The assessment amount is based on 40% of the cost of the street and storm sewer improvements. Note that the amount of the assessment will be calculated based on the final construction cost once the project is completed. The amount shown in the table below is an estimate based on the estimated construction costs calculated in the Feasibility Report. Fund- ing sources and amounts are as shown below: Highland/ Grainwood/ Eau Claire/154th Marsh/Skyline Eau Claire (Reclamation/ Reconstruction) (Reconstruction Overlay) Assessments $681,732 $448,163 $3,234 i Sewer Fund $553,785 $364,464 $792 Water Fund $638,764 $431,625 Water Quality Fund $162,863 $72,978 Tax Levy $859,735 $599,266 $185,580 Total Project Cost $2,896,880 $1,916,497 $189,606 Estimated Unit $9,469 $8,619 Overlay Assessment N/A Assessable Units 72 52 Project Linear Feet 3532 2448 ALTERNATIVES: 1. Approve a Resolution accepting the Feasibility Report and establishing a Public Hearing date. 2. Deny this item for a specific reason and provide staff with direction. 3. Table this item until some date in the future. RECOMMENDED Motion and second for alternative#1. MOTION: 3 O� PRlp+p N U tr1 4646 Dakota Street SE Prior Lake,MN 55372 RESOLUTION 14-xxx A RESOLUTION ACCEPTING THE FEASIBILITY REPORT AND CALLING FOR A PUBLIC HEARING FOR THE IMPROVEMENT OF HIGHLAND, MARCH, SKYLINE, GRAINWOOD,AND EAU CLAIRE, CITY PROJECT#TRN15-000004 Motion By: Second By: WHEREAS, Pursuant to Resolutions 14-125 and 14-126, the City Council, on August 25, 2014 ordered a Feasibility Report to be prepared by the City's Engineering Department with reference to the Improvement Highland, Marsh, Skyline, Grainwood, and Eau Claire; and WHEREAS, The Feasibility Report for the Improvement of Highland, Marsh, Skyline, Grainwood, and Eau Claire dated November 2014 contains information that the proposed project is necessary, cost effective, and feasible. NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE, MINNESOTA as follows: 1. The recitals set forth above are incorporated herein. 2. The City Council hereby accepts the Feasibility Report as submitted. 3. The Council will consider the improvement of such streets and areas in accordance with the Report and the assessment of property as described in the Report for all or a portion of the cost of the improvements pursuant to Minnesota Statutes Chapter 429 at an estimated total cost of the improvements of $5,002,982. 4. A Public Hearing shall be held on such proposed improvements on the 24th of November, 2014 at Prior Lake City Hall, with the address of 4646 Dakota Street SE, City of Prior Lake, Minnesota at 7:00 p.m. statutory notice and publication requirements shall be followed. PASSED AND ADOPTED THIS 10th DAY OF NOVEMBER 2014. VOTE Hedberg Keeney McGuire Morton Soukup Aye ❑ ❑ ❑ ❑ ❑ Nay ❑ ❑ ❑ ❑ ❑ Absent ❑ ❑ ❑ ❑ ❑ Abstain ❑ ❑ ❑ ❑ ❑ Frank Boyles, City Manager CERTIFICATION Preliminary Engineering Report for 2015 Street Reconstruction Project City of Prior Lake Prior Lake, MN T18.109027 I hereby certify that this plan, specification or report was prepared by me or under my direct supervision, and that I am a duly Licensed Professional Engineer under the laws of the State of Minnesota. By: Cory L. Bienfang, P.E. License No. 51292 Date: On August 25, 2014, the Prior Lake City Council adopted Resolution 14-125 and 14-126, which ordered the preparation of a Feasibility Report for improvements to the City of Prior Lake’s 2015 Street Reconstruction project area listed below: West side of County Road 21 Highland Avenue · Skyline Avenue · Marsh Street · East side of County Road 21 Grainwood Circle · Eau Claire Trail · Eau Claire Circle · th 154 Street · Figure 1 See in Appendix A for the proposed project location map. This report will review the existing conditions in the project area and discuss, in detail, the proposed improvements. The proposed street improvements will consist of two methods: full street reconstruction and full depth reclamation. The utility improvements will consist of watermain replacement, sanitary sewer replacement, and storm sewer upgrades. It will also provide preliminary cost estimates for the proposed improvements with financing for the project coming from a combination of special assessments, the City’s general tax levy, and the City’s sewer and water utility funds. Figures 2 and 3 See in Appendix A for the proposed street improvements map. Figures 4 and5 See in Appendix A for the existing City owned utilities that are proposed to be replaced. If the City decides to proceed with the proposed street and utility improvements described in this report, it is anticipated construction would begin in 2015 as shown in the detailed project schedule found on page 26. The City has a Capital Improvement Program (CIP) which prioritizes the infrastructure improvement needs within the City and has identified the above listed project area as requiring improvement during the 2015 calendar year. The deteriorated bituminous surface and aging utility infrastructure resulted in the selection of these neighborhood areas. A neighborhood meeting was held on October 23, 2014. The purpose of the meeting was to inform the property owners located within the project area of the improvements being considered, to gather input from the impacted residents, and to answer any questions that the property owners had. Successful projects incorporate a very proactive public process in order to provide information and awareness of the project, as well as to provide comments on potential design options. To facilitate this public input a project questionnaire has been developed, informational pamphlets were distributed (explaining typical infrastructure projects and detailing the MN Statue 429 Assessment Process), and a project website is available with up-to-date project information. Copies of the completed questionnaires already returned to the City can be found in Appendix E. MARSH STREET Existing Conditions th Marsh Street, between County Road 82 (154 Street) and Highland Avenue, is a local residential road in Prior Lake. The road runs west/east in the central portion of the City and serves residential single family homes with direct access. Marsh Street exists as an approximately 31-foot wide bituminous roadway with low bituminous curb. The pavement width is measured from edge of bituminous to edge of bituminous. There are no sidewalks, trails or street lights in place along Marsh Street and Right-of-Way encroachments are found within the boulevard on both sides of the street. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed in 1977. The bituminous pavement within the study area exhibits wear and distress due to traffic loading as well as typical weathering effects experienced with aged asphalt pavement. Significant roadway patching is visible and the existing pavement contains large transverse cracking (cracks running perpendicular across the roadway) and significant alligator-type cracking. Alligator cracking in pavement is an indicator of potential subgrade problems. Soil borings were completed along Marsh Street by Element Materials Technology to determine the existing roadway section. The existing bituminous pavement thickness ranges from 3.5 to 4.0 inches with a sand and gravel aggregate base thickness of approximately 4.0 inches. Existing subgrade soils found beneath the aggregate base consisted of a clayey sand fill material. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. The Overall Condition Index (OCI) for Marsh Street is a 28, making it a candidate for reconstruction. Existing OCI for Marsh Street From Street To Street OCI County Road 82 Skyline Ave 28.92 Highland Ave Skyline Ave 26.92 There is an existing 8-inch diameter ductile iron pipe (DIP) water main which runs the entire length of Marsh Street. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show multiple water main breaks have been experienced in this area. There is an existing 8-inch vitrified clay pipe (VCP) sanitary sewer main which runs the entire length of Marsh Street starting upstream at the manhole at Highland Avenue and ending downstream at the manhole within the turnaround on the far east end. The sewer main then runs from this manhole within the turnaround to the south between the houses and connects into the sewer main in Skyline Avenue. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of some root penetration and cracks in the pipe. Root penetration is significant because it implies failure in the pipe joints where groundwater can seep into the system. The groundwater infiltration adds to the volume of wastewater being treated. Pipe cracks can lead to pipe collapse and sewage backups if left untreated. Service laterals to individual homes within the project area are anticipated to be 4” VCP. There is an existing storm sewer system within Marsh Street consisting of a catchbasin structure on each side of the roadway located in between the turnaround at Highland Avenue and the Skyline Avenue intersection. The collected stormwater is piped by reinforced concrete pipe (RCP) to the north between two houses and connects into storm sewer within County Road 82. There is also a catchbasin structure located within the turnaround on the east end of the street which outlets into the pond area in the southwest quadrant of the intersection of County Road 21 and 82. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and sub-soils, the proposed improvement for Marsh Street is a complete reconstruction of the existing road section. The new roadway is proposed to be constructed with new concrete curb and gutter to improve drainage and support the edge of pavement. Final determination of whether the new curb and gutter will be B618 or mountable will be made during final design. Curb and gutter of the B618 variety has better water conveyance properties, eliminates off tracking from on-street parking, and better suited to keep snow plows within the roadway during snow removal operations. Curb and gutter of the mountable variety is the current City standard, allows for unrestricted property access and generally less intrusive when added to an existing neighborhood without any existing curb and gutter. The new roadway width is proposed to be constructed in accordance to the current City standard of 32-feet back of curb to back of curb. The new roadway horizontal alignment and vertical profile is expected to remain similar to the existing roadway. The street will be reconstructed to a minimum 7-ton design requirement, which holds up to garbage truck, school bus, and infrequent contractor truck loading. Based on geotechnical recommendations the proposed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 8.0-inches of Class V aggregate base 24.0-inches of select granular borrow It is recommended that geotextile fabric be installed at the bottom of the street section to provide separation of the new street section materials from the existing sub-grade soils and provide additional structural support. Additionally, subsurface drain tile will be installed at the bottom of the street section under the curb line to help ensure the new roadway section will remain free draining. This helps to reduce stress on pavement from freeze thaw action. During construction if areas of poorer soil conditions than what the soil borings have shown are discovered, additional subgrade excavation and replacement material will be required. All driveways will be replaced with new like material within the City Right-of-Way, from the new back of curb to edge of Right-of-Way. All disturbed boulevard areas will be restored with 5.0-inches of topsoil and new sod. Figure 6 See in Appendix A for the proposed typical street section for Marsh Street, including a detail for B618 and mountable concrete curb and gutter. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, the proposed improvement for the existing sanitary sewer along Marsh Street is full replacement of the existing 8-inch VCP with new 8-inch polyvinyl chloride (PVC) pipe. All sanitary sewer manholes are proposed for replacement with new precast concrete structures and new castings that meet City standards. The proposed improvement for the existing sanitary sewer located between the existing houses is to be full length lining of the existing main with a cured-in-place pipe (CIPP). All sewer services are proposed for replacement from the new main to the property line (City Right-of-Way) with new PVC wyes and 4-inch PVC pipe. Proposed Watermain Improvements Based on the watermain pipe age and break history, the proposed improvement for the existing watermain along Marsh Street is full replacement with new 8-inch ductile iron pipe (DIP). All hydrants, valves, and fittings will also be replaced along with the mainline pipe. All water service lines to individual residences are proposed for replacement from the new main to the property line (City Right-of-Way) with new 1-inch copper lines and curb stop and box. Proposed Storm Sewer Improvements The existing catchbasins along Marsh Street are recommended to be removed and replaced with new catchbasins meeting current City standards. The existing storm sewer pipe network will be analyzed based on hydraulic performance and structural condition during final design. Additionally, stormwater quality improvements will be analyzed to help remove sediments and pollutant loads to the downstream system. Figure 4 See in Appendix A for the existing sanitary sewer, watermain and storm sewer utilities within Marsh Street proposed to be improved. SKYLINE AVENUE Existing Conditions Skyline Avenue, between Marsh Street and the south terminus cul-de-sac, is a local residential road in Prior Lake. The road runs north/south in the central portion of the City and serves residential single family homes with direct access. Due to the project’s close proximity to Prior Lake, there are two common access points located on the south end of Skyline Avenue, one on each side of the street. Both lake access areas are owned by the Island View Homeowners Association and will be assessed similar to any other developed lot within the project area. Skyline Avenue exists as an approximately 31-foot wide bituminous roadway with low bituminous curb. The cul-de-sac is located at the south end of the street and exists as a 46-foot radius cul-de-sac measured to the edge of bituminous with low bituminous curb. The pavement width is measured from edge of bituminous to edge of bituminous. There are no sidewalks or trails in place along Skyline Avenue and Right-of-Way encroachments are found within the boulevard on both sides of the street. There is one existing street light along Skyline Avenue and is located on the south side of the cul-de-sac. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed in 1977. The bituminous pavement within the study area exhibits wear and distress due to traffic loading as well as typical weathering effects experienced with aged asphalt pavement. Significant roadway patching is visible and the existing pavement contains large transverse cracking (cracks running perpendicular across the roadway) and significant alligator-type cracking. Alligator cracking in pavement is an indicator of potential subgrade problems. Soil borings were completed along Skyline Avenue by Element Materials Technology to determine the existing roadway section. The existing bituminous pavement thickness ranges from 3.75 to 4.0 inches with a sand and gravel aggregate base thickness of approximately 4.0 inches. Existing subgrade soils found beneath the aggregate base consisted of a sand fill material with silty and clayey sand. Groundwater was observed at a depth of approximately 6-feet within two borings located at the intersection of Highland Avenue and within the cul-de-sac. Based on this indicated high water level, dewatering will be required during construction of the new sanitary sewer and watermain utilities in this area. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. The Overall Condition Index (OCI) for Skyline Avenue is a 27, making it a candidate for reconstruction. Existing OCI for Skyline Avenue From Street To Street OCI Marsh St Highland Ave 26.92 Highland Ave Cul-de-Sac 26.92 There is an existing 6-inch diameter ductile iron pipe (DIP) water main which runs the entire length of Skyline Avenue. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show multiple water main breaks have been experienced in this area. There is an existing 8-inch vitrified clay pipe (VCP) sanitary sewer main which runs the entire length of Skyline Avenue, one section starting upstream at the manhole at Marsh Street and ending downstream at the manhole at Highland Avenue and one section starting upstream at the manhole south of the cul-de-sac and ending downstream at the manhole at Highland Avenue. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of some root penetration, cracks in the pipe and poor service connections. Root penetration is significant because it implies failure in the pipe joints where groundwater can seep into the system. The groundwater infiltration adds to the volume of wastewater being treated. Pipe cracks can lead to pipe collapse and sewage backups if left untreated. Service laterals to individual homes within the project area are anticipated to be 4” VCP. There is an existing storm sewer system within Skyline Avenue consisting of a catchbasin structure on each side of the roadway located at two locations in between Marsh Street and Highland Avenue which outlet to the east into the pond area in the southwest quadrant of the intersection of County Road 21 and 82. There is also a catchbasin structure located within the cul-de-sac on the south end of the street that outlets directly into Upper Prior Lake. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and sub-soils, the proposed improvement for Skyline Avenue is a complete reconstruction of the existing road section. The new roadway is proposed to be constructed with new concrete curb and gutter to improve drainage and support the edge of pavement. Final determination of whether the new curb and gutter will be B618 or mountable will be made during final design. Curb and gutter of the B618 variety has better water conveyance properties, eliminates off tracking from on-street parking, and better suited to keep snow plows within the roadway during snow removal operations. Curb and gutter of the mountable variety is the current City standard, allows for unrestricted property access and generally less intrusive when added to an existing neighborhood without any existing curb and gutter. The new roadway width is proposed to be constructed in accordance to the current City standard of 32-feet back of curb to back of curb. The new roadway horizontal alignment and vertical profile is expected to remain similar to the existing roadway. The street will be reconstructed to a minimum 7-ton design requirement, which holds up to garbage truck, school bus, and infrequent contractor truck loading. Based on geotechnical recommendations the proposed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 8.0-inches of Class V aggregate base 24.0-inches of select granular borrow Based on geotechnical recommendations, the portion of Skyline Avenue from the Highland Avenue intersection south to the cul-de-sac will require up to an additional 12.0-inches of select granular borrow based on the discovered high water level in this area. It is recommended that geotextile fabric be installed at the bottom of the street section to provide separation of the new street section materials from the existing sub-grade soils and provide additional structural support. Additionally, subsurface drain tile will be installed at the bottom of the street section under the curb line to help ensure the new roadway section will remain free draining. This helps to reduce stress on pavement from freeze thaw action. During construction if areas of poorer soil conditions than what the soil borings have shown are discovered, additional subgrade excavation and replacement material will be required. All driveways will be replaced with new like material within the City Right-of-Way, from the new back of curb to edge of Right-of-Way. All disturbed boulevard areas will be restored with 5.0-inches of topsoil and new sod. Figure 6 See in Appendix A for the proposed typical street section for Skyline Avenue, including a detail for B618 and mountable concrete curb and gutter. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, the proposed improvement for the existing sanitary sewer along Skyline Avenue is full replacement of the existing failing 8-inch VCP with new 8-inch polyvinyl chloride (PVC) pipe. All sanitary sewer manholes are proposed for replacement with new precast concrete structures and new castings that meet City standards. All sewer services are proposed for replacement from the new main to the property line (City Right-of-Way) with new PVC wyes and 4-inch PVC pipe. Proposed Watermain Improvements Based on the watermain pipe age and break history, the proposed improvement for the existing watermain along Skyline Avenue is full replacement with new 8-inch ductile iron pipe (DIP). All hydrants, valves, and fittings will also be replaced along with the mainline pipe. All water service lines to individual residences are proposed for replacement from the new main to the property line (City Right-of-Way) with new 1-inch copper lines and curb stop and box. Proposed Storm Sewer Improvements The existing catchbasins along Skyline Avenue are recommended to be removed and replaced with new catchbasins meeting current City standards. The existing storm sewer pipe network will be analyzed based on hydraulic performance and structural condition during final design. Additionally, stormwater quality improvements will be analyzed to help remove sediments and pollutant loads to the downstream system and Upper Prior Lake. Figure 4 See in Appendix A for the existing sanitary sewer, watermain and storm sewer utilities within Skyline Avenue proposed to be improved. HIGHLAND AVENUE Existing Conditions Highland Avenue, between Marsh Street and County Road 21 (Eagle Creek Avenue), is a local residential road in Prior Lake. The road runs north/south in the central portion of the City and serves residential single family homes with direct access. Highland Avenue exists as an approximately 31-foot wide bituminous roadway with low bituminous curb, except for a 420-foot section located on the west side of the Skyline Avenue intersection that has existing concrete curb and gutter. This section was improved by the City’s Public Works department a few years ago due to the complete deterioration of the existing bituminous pavement. The pavement width is measured from edge of bituminous to edge of bituminous. There are no sidewalks, trails or street lights in place along Highland Avenue and Right-of-Way encroachments are found within the boulevard on both sides of the street. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed in 1977. The bituminous pavement within the study area exhibits wear and distress due to traffic loading as well as typical weathering effects experienced with aged asphalt pavement. Significant roadway patching is visible and the existing pavement contains large transverse cracking (cracks running perpendicular across the roadway) and significant alligator-type cracking. Alligator cracking in pavement is an indicator of potential subgrade problems. Soil borings were completed along Highland Avenue by Element Materials Technology to determine the existing roadway section. The existing bituminous pavement thickness ranges from 3.5 to 4.5 inches with a sand and gravel aggregate base thickness of approximately 4.0 inches. Existing subgrade soils found beneath the aggregate base consisted of a clayey sand and lean clay material. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. The Overall Condition Index (OCI) for Highland Avenue is a 28, making it a candidate for reconstruction. Existing OCI for Highland Avenue From Street To Street OCI Marsh Street Skyline Avenue 25.90 Skyline Ave County Road 21 29.92 There is an existing 8-inch diameter ductile iron pipe (DIP) water main which runs the entire length of Highland Avenue. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show multiple water main breaks have been experienced in this area. There is an existing 8-inch vitrified clay pipe (VCP) sanitary sewer main which runs the entire length of Highland Avenue starting upstream at the manhole at Marsh Street and ending downstream at the manhole at County Road 21. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of minor cracks in the pipe. Pipe cracks can lead to pipe collapse and sewage backups if left untreated. Service laterals to individual homes within the project area are anticipated to be 4” VCP. There is an existing storm sewer system within Highland Avenue consisting of a catchbasin structure on each side of the roadway located in between the turnaround at Marsh Street and the Skyline Avenue intersection which outlet directly into Upper Prior Lake. There is also a catchbasin structure on each side of the roadway located on the west side of the Skyline Avenue intersection which are piped to the north and connect into the Skyline Avenue storm sewer system which ultimately outlets into the pond area in the southwest quadrant of the intersection of County Road 21 and 82. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and sub-soils, the proposed improvement for Highland Avenue is a complete reconstruction of the existing road section. The new roadway is proposed to be constructed with new concrete curb and gutter to improve drainage and support the edge of pavement. Final determination of whether the new curb and gutter will be B618 or mountable will be made during final design. Curb and gutter of the B618 variety has better water conveyance properties, eliminates off tracking from on-street parking, and better suited to keep snow plows within the roadway during snow removal operations. Curb and gutter of the mountable variety is the current City standard, allows for unrestricted property access and generally less intrusive when added to an existing neighborhood without any existing curb and gutter. The new roadway width is proposed to be constructed in accordance to the current City standard of 32-feet back of curb to back of curb. The new roadway horizontal alignment and vertical profile is expected to remain similar to the existing roadway. The street will be reconstructed to a minimum 7-ton design requirement, which holds up to garbage truck, school bus, and infrequent contractor truck loading. Based on geotechnical recommendations the proposed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 8.0-inches of Class V aggregate base 24.0-inches of select granular borrow It is recommended that geotextile fabric be installed at the bottom of the street section to provide separation of the new street section materials from the existing sub-grade soils and provide additional structural support. Additionally, subsurface drain tile will be installed at the bottom of the street section under the curb line to help ensure the new roadway section will remain free draining. This helps to reduce stress on pavement from freeze thaw action. During construction if areas of poorer soil conditions than what the soil borings have shown are discovered, additional subgrade excavation and replacement material will be required. All driveways will be replaced with new like material within the City Right-of-Way, from the new back of curb to edge of Right-of-Way. All disturbed boulevard areas will be restored with 5.0-inches of topsoil and new sod. Figure 6 See in Appendix A for the proposed typical street section for Highland Avenue, including a detail for B618 and mountable concrete curb and gutter. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, the proposed improvement for the existing sanitary sewer along Highland Avenue is full replacement of the existing 8-inch VCP with new 8-inch polyvinyl chloride (PVC) pipe. All sanitary sewer manholes are proposed for replacement with new precast concrete structures and new castings that meet current City standards. All sewer services are proposed for replacement from the new main to the property line (City Right-of-Way) with new PVC wyes and 4-inch PVC pipe. Proposed Watermain Improvements Based on the watermain pipe age and break history, the proposed improvement for the existing watermain along Highland Avnue is full replacement with new 8-inch ductile iron pipe (DIP). All hydrants, valves, and fittings will also be replaced along with the mainline pipe. All water service lines to individual residences are proposed for replacement from the new main to the property line (City Right-of-Way) with new 1-inch copper lines and curb stop and box. Proposed Storm Sewer Improvements The existing catchbasins along Highland Avenue are recommended to be removed and replaced with new catchbasins meeting current City standards. The existing storm sewer pipe network will be analyzed based on hydraulic performance and structural condition during final design. Additionally, stormwater quality improvements will be analyzed to help remove sediments and pollutant loads to the downstream system and Upper Prior Lake. Figure 4 See in Appendix A for the existing sanitary sewer, watermain and storm sewer utilities within Highland Avenue proposed to be improved. EAU CLAIRE TRAIL Existing Conditions th Eau Claire Trail, between 154 Street and County Road 21 (Eagle Creek Avenue), is a local residential road in Prior Lake. A portion of the road runs north/south and the other portion runs west/east in the central portion of the City and serves residential single family homes with direct access. The north/south portion also contains the cul- de-sac of Eau Claire Circle. The west/east portion of Eau Claire Trail exists as an approximately 31-foot wide bituminous roadway with low bituminous curb and is the portion under focus for this section of the report. The north/south portion of Eau Claire Trail has existing concrete curb and gutter and will be addressed under the next section of this report. The pavement width is measured from edge of bituminous to edge of bituminous. There are no sidewalks, trails or street lights in place along Eau Claire Trail and Right-of-Way encroachments are found within the boulevard on both sides of the street. No parking signs are currently installed along the south side of the street for this portion of Eau Claire Trail. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed for this portion of Eau Claire Trail in 1977. The bituminous pavement within the study area exhibits wear and distress due to traffic loading as well as typical weathering effects experienced with aged asphalt pavement. Significant roadway patching is visible and the existing pavement contains large transverse cracking (cracks running perpendicular across the roadway) and significant alligator-type cracking. Alligator cracking in pavement is an indicator of potential subgrade problems. Soil borings were completed along Eau Claire Trail by Element Materials Technology to determine the existing roadway section. The existing bituminous pavement thickness ranges from 5.0 to 5.5 inches with a sand and gravel aggregate base thickness of approximately 4.0 inches. Existing subgrade soils found beneath the aggregate base consisted of a clayey sand fill material. Groundwater was observed at a depth of approximately 12-feet within a boring located mid-block for this portion of Eau Claire Trail. Based on this indicated water level, minor dewatering during construction of the new sanitary sewer main may be required in this area. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. The Overall Condition Index (OCI) for the west/east portion of Eau Claire Trail is a 30, making it a candidate for reconstruction. Existing OCI for Eau Claire Trail From Street To Street OCI County Road 21 Calmut Ave 29.92 There is an existing 6-inch diameter ductile iron pipe (DIP) water main which runs the entire length of the west/east portion of Eau Claire Trail. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show multiple water main breaks have been experienced in this area. There is an existing 8-inch sanitary sewer main consisting of both ductile iron pipe (DIP) and vitrified clay pipe (VCP) which runs the entire length of the west/east portion of Eau Claire starting upstream at the manhole at the east end of the west/east portion and ending downstream at the manhole at County Road 21. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of cracks in the pipe and a section of pipe previously repaired. Pipe cracks can lead to pipe collapse and sewage backups if left untreated. Service laterals to individual homes within the project area are anticipated to be 4” DIP or VCP. There is an existing storm sewer system within Eau Claire Trail consisting of a catchbasin structure on each side of the roadway located at the intersection of County Road 21. The collected stormwater is piped to the west and connects into storm sewer within County Road 21. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and sub-soils, the proposed improvement for the west/east portion of Eau Claire Trail is a complete reconstruction of the existing road section. The new roadway is proposed to be constructed with new concrete curb and gutter to improve drainage and support the edge of pavement. Final determination of whether the new curb and gutter will be B618 or mountable will be made during final design. Curb and gutter of the B618 variety has better water conveyance properties, eliminates off tracking from on-street parking, and better suited to keep snow plows within the roadway during snow removal operations. Curb and gutter of the mountable variety is the current City standard, allows for unrestricted property access and generally less intrusive when added to an existing neighborhood without any existing curb and gutter. The new roadway width is proposed to be constructed in accordance to the current City standard of 32-feet back of curb to back of curb. The new roadway horizontal alignment and vertical profile is expected to remain similar to the existing roadway. The street will be reconstructed to a minimum 7-ton design requirement, which holds up to garbage truck, school bus, and infrequent contractor truck loading. Based on geotechnical recommendations the proposed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 8.0-inches of Class V aggregate base 24.0-inches of select granular borrow It is recommended that geotextile fabric be installed at the bottom of the street section to provide separation of the new street section materials from the existing sub-grade soils and provide additional structural support. Additionally, subsurface drain tile will be installed at the bottom of the street section under the curb line to help ensure the new roadway section will remain free draining. This helps to reduce stress on pavement from freeze thaw action. During construction if areas of poorer soil conditions than what the soil borings have shown are discovered, additional subgrade excavation and replacement material will be required. All driveways will be replaced with new like material within the City Right-of-Way, from the new back of curb to edge of Right-of-Way. All disturbed boulevard areas will be restored with 5.0-inches of topsoil and new sod. Figure 6 See in Appendix A for the proposed typical street section for Eau Claire Trail, including a detail for B618 and mountable concrete curb and gutter. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, the proposed improvement for the existing sanitary sewer along the west/east portion of Eau Claire is full replacement of the existing failing 8-inch VCP and DIP with new 8-inch polyvinyl chloride (PVC) pipe. All sanitary sewer manholes are proposed for replacement with new precast concrete structures and new castings that meet City standards. All sewer services are proposed for replacement from the new main to the property line (City Right-of-Way) with new PVC wyes and 4-inch PVC pipe. Proposed Watermain Improvements Based on the watermain pipe age and break history, the proposed improvement for the existing watermain along the west/east portion of Eau Claire is full replacement with new 6-inch ductile iron pipe (DIP). It is not practical to install new 8-inch watermain when connecting to existing 6-inch watermains on each end. All hydrants, valves, and fittings will also be replaced along with the mainline pipe. All water service lines to individual residences are proposed for replacement from the new main to the property line (City Right-of-Way) with new 1-inch copper lines and curb stop and box. Proposed Storm Sewer Improvements The existing catchbasins at the intersection of County Road 21 are recommended to remain in place and analysis of whether any other improvements are necessary will be completed during final design. Figure 5 See in Appendix A for the existing sanitary sewer, watermain and storm sewer utilities within this portion of Eau Claire Trail proposed to be improved. GRAINWOOD CIRCLE Existing Conditions Grainwood Circle, between County Road 21 (Eagle Creek Avenue) and Calmut Avenue, is a local residential road in Prior Lake. The road runs west/east with a square loop on the east end in the central portion of the City and serves residential single family homes with direct access. The west/east portion of Grainwood Circle exists as an approximately 31-foot wide bituminous roadway with low bituminous curb and the square loop portion exists as an approximately 26-foot wide bituminous roadway with low bituminous curb. The pavement width is measured from edge of bituminous to edge of bituminous. There are no sidewalks or trails in place along Grainwood Circle and Right-of-Way encroachments are found within the boulevard on both sides of the street. No parking signs are currently installed along both sides of the street for the 31-foot wide west/east portion and along the outside of the street for the 26-foot wide square loop portion. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed in 1977. An existing overhead electric line and poles are located on the north side of the street along the west/east portion and on the outside of the street for the south and east leg of square loop portion. They shift to the inside of the street for the north leg and no existing lines or poles are found along the west leg of the square loop. There are no street lights along the west/east portion of Grainwood Circle and there is a street light located at each of the four corners of the square loop portion. The bituminous pavement within the study area exhibits wear and distress due to traffic loading as well as typical weathering effects experienced with aged asphalt pavement. Significant roadway patching is visible and the existing pavement contains large transverse cracking (cracks running perpendicular across the roadway) and significant alligator-type cracking. Alligator cracking in pavement is an indicator of potential subgrade problems. Soil borings were completed along Grainwood Circle by Element Materials Technology to determine existing roadway section. The existing bituminous pavement thickness ranges from 3.5 to 7.5 inches with a sand and gravel aggregate base thickness of approximately 4.0 inches. Existing subgrade soils found beneath the aggregate base consisted of a sandy lean clay material. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. The Overall Condition Index (OCI) for Grainwood Circle is a 35, making it a candidate for reconstruction. Existing OCI for Grainwood Circle From Street To Street OCI County Road 21 Calmut Ave 36.90 Grainwood Circle Calmut Ave 33.90 There is an existing 10-inch diameter ductile iron pipe (DIP) water main which runs the entire length of Grainwood Circle. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show multiple water main breaks have been experienced in this area. There is an existing 8-inch ductile iron pipe (DIP) sanitary sewer main which runs the entire length of Grainwood Circle starting upstream at the manhole at Calmut Avenue and ending downstream at the manhole at County Road 21. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of sags, cracks in the pipe, previously repaired sections, and some areas of partial flow blockage. All of these conditions can lead to pipe collapse and sewage backups if left untreated. Service laterals to individual homes within the project area are anticipated to be 4” DIP or VCP. There is an existing storm sewer system within Grainwood Circle consisting of three catchbasin structures at the intersection of the west/east and square loop portion. The collected stormwater is piped by reinforced concrete pipe (RCP) to the south between two houses and outlets directly into Upper Prior Lake. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and sub-soils, the proposed improvement for the entire length of Grainwood Circle is a complete reconstruction of the existing road section. The new roadway is proposed to be constructed with new concrete curb and gutter to improve drainage and support the edge of pavement. Final determination of whether the new curb and gutter will be B618 or mountable will be made during final design. Curb and gutter of the B618 variety has better water conveyance properties, eliminates off tracking from on-street parking, and better suited to keep snow plows within the roadway during snow removal operations. Curb and gutter of the mountable variety is the current City standard, allows for unrestricted property access and generally less intrusive when added to an existing neighborhood without any existing curb and gutter. The new roadway width is proposed to be constructed in accordance to the current City standard of 32-feet back of curb to back of curb for the west/east portion and match the existing width of 26-feet back of curb to back of curb for the square loop portion. The new roadway horizontal alignment and vertical profile is expected to remain similar to the existing roadway. The street will be reconstructed to a minimum 7-ton design requirement, which holds up to garbage truck, school bus, and infrequent contractor truck loading. Based on geotechnical recommendations the proposed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 8.0-inches of Class V aggregate base 24.0-inches of select granular borrow It is recommended that geotextile fabric be installed at the bottom of the street section to provide separation of the new street section materials from the existing sub-grade soils and provide additional structural support. Additionally, subsurface drain tile will be installed at the bottom of the street section under the curb line to help ensure the new roadway section will remain free draining. This helps to reduce stress on pavement from freeze thaw action. During construction if areas of poorer soil conditions than what the soil borings have shown are discovered, additional subgrade excavation and replacement material will be required. All driveways will be replaced with new like material within the City Right-of-Way, from the new back of curb to edge of Right-of-Way. All disturbed boulevard areas will be restored with 5.0-inches of topsoil and new sod. Figure 6 See in Appendix A for the proposed typical street section for Grainwood Circle, including a detail for B618 and mountable concrete curb and gutter. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, the proposed improvement for the existing sanitary sewer along Grainwood Circle is full replacement of the existing 8-inch DIP with new 8-inch polyvinyl chloride (PVC) pipe. All sanitary sewer manholes are proposed for replacement with new precast concrete structures and new castings that meet City standards. All sewer services are proposed for replacement from the new main to the property line (City Right-of-Way) with new PVC wyes and 4-inch PVC pipe. Proposed Watermain Improvements Based on the watermain pipe age and break history, the proposed improvement for the existing watermain along Grainwood Cirlce is full replacement with new 10-inch ductile iron pipe (DIP). All hydrants, valves, and fittings will also be replaced along with the mainline pipe. All water service lines to individual residences are proposed for replacement from the new main to the property line (City Right-of-Way) with new 1-inch copper lines and curb stop and box. Proposed Storm Sewer Improvements The existing catchbasins along Grainwood Cirlce are recommended to be removed and replaced with new catchbasins meeting current City standards. The existing storm sewer pipe network will be analyzed based on hydraulic performance and structural condition during final design. Additionally, stormwater quality improvements will be analyzed to help remove sediments and pollutant loads to Upper Prior Lake. Figure 5 See in Appendix A for the existing sanitary sewer, watermain and storm sewer utilities within Grainwood Circle proposed to be improved. TH 154 STREET Existing Conditions th 154 Street, between Eau Claire Trail and County Road 21 (Eagle Creek Avenue), is a local residential road in Prior Lake. The road runs west/east in the central portion of the City and serves residential single family homes with direct access. Due to the project’s close proximity to Prior Lake, there is one common access point located on th the east end of 154 Street. The lake access area is owned by Windsong on the Lake Association and will be assessed similar to any other developed lot within the project area. th 154 Street exists as an approximately 32-foot wide bituminous roadway with mountable concrete curb and gutter on both sides. The pavement width is measured from back of curb to back of curb. There are no sidewalks or trails in place along th 154 Street and Right-of-Way encroachments are found within the boulevard on both th sides of the street. There is one existing street light along 154 Street and it is located on the north side of roadway on the east end of the street. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed in 1983. The bituminous pavement within the study area is beginning to exhibit wear and distress due to traffic loading as well as typical weathering effects experienced with aging asphalt pavement. The existing pavement contains large transverse cracking (cracks running perpendicular across the roadway), localized random cracking around existing manhole structures, and visible edge cracking typically located within 12 to th 18-inches of the gutter edge. Soil borings are scheduled to be completed along 154 Street by Element Materials Technology to determine the existing roadway section. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. th The Overall Condition Index (OCI) for 154 Street is a 38, making it a candidate for a full depth reclamation. th Existing OCI for 154 Street From Street To Street OCI County Road 21 Eau Claire Trail 37.90 There is an existing 6-inch diameter ductile iron pipe (DIP) water main which runs th the entire length of 154 Street. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show no previous water main breaks have been experienced in this area. There is an existing 8-inch polyvinyl chloride (PVC) sanitary sewer main which runs th the entire length of 154 Street starting upstream at the manhole at Calmut Avenue and ending downstream at the manhole at County Road 21. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of no existing physical defects. Service lines to individual homes within the project area are anticipated to be 4-inch diameter PVC pipe. th There is an existing storm sewer system within 154 Street consisting of a pair of catchbasin structures on each side of the roadway located east of the County Road 21 th intersection. The collected stormwater is piped to the west along 154 Street and connects into storm sewer within County Road 21. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and assumed sub-soils, th the proposed improvement for 154 Street is a full depth reclamation of the existing road section. The existing pavement thickness and underlying aggregate base is proposed to be ground up (reclaimed) to a maximum depth of about 12 inches. The process effectively removes all existing cracking in the pavement and improves the upper portions of the aggregate base by combining the existing aggregate base and bituminous pavement into a new aggregate base. After grinding and blending these layers, space is made for the required new pavement thickness and the roadway is paved with new bituminous pavement. The new street matches the existing concrete curb and gutter so horizontally and vertically the roadway remains the same as the existing roadway. Spot curb and gutter repairs will be completed where required. The proposed reclaimed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 12.0-inches of compacted reclaim material Reclamation is a cost effective roadway maintenance procedure for roadways with an existing aggregate base and requiring only roadway surface improvements. Based on the results of the pending soil borings, if the assumed adequate aggregate base is determined of insufficient thickness to perform the proposed full depth in place reclamation, an alternate roadway maintenance procedure will have to be pursued and the resultant increased costs determined. There are expected to be no improvements beyond the edge of the existing roadway concrete curb and gutter for any proposed roadway maintenance procedures. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, it was determined th no improvements are necessary for the existing sanitary sewer along 154 Street as part of the proposed project. All existing sanitary sewer manholes castings are proposed for replacement with new concrete adjustments rings and new castings that meet current City standards. No improvements are proposed for the existing sewer services based on no proposed improvements to the existing sewer main line. Proposed Watermain Improvements Based on the watermain pipe age, material type, and lack of break history, it was th determined no improvements are necessary for the existing watermain along 154 Street. No improvements are proposed for the existing water services based on no proposed improvements to the existing watermain. Proposed Storm Sewer Improvements th The existing catchbasins along 154 Street are recommended to remain in place and no other improvements are necessary as part of the proposed project. Figure 5 See in Appendix A for the existing sanitary sewer, watermain and storm th sewer utilities within 154 Street proposed to remain in-place. EAU CLAIRE TRAIL & EAU CLAIRE CIRCLE Existing Conditions th Eau Claire Trail, between 154 Street and County Road 21 (Eagle Creek Avenue), is a local residential road in Prior Lake. A portion of the road runs north/south and the other portion runs west/east in the central portion of the City and serves residential single family homes with direct access. The north/south portion also contains the cul- de-sac of Eau Claire Circle. The north/south portion of Eau Claire Trail exists as an approximately 32-foot wide bituminous roadway with mountable concrete curb and gutter on both sides and is the portion under focus for this section of the report. The west/east portion of Eau Claire Trail does not have any existing concrete curb and gutter and was addressed in the previous section of this report. The pavement width is measured from back of curb to back of curb. There are no sidewalks, trails or street lights in place along Eau Claire Trail or Circle and Right-of-Way encroachments are found within the boulevard on both sides of the street. Eau Claire Circle existing as a 41-foot radius cul-de-sac with mountable concrete curb and gutter. City records show the roadway, water main, sanitary sewer, and storm sewer were constructed for both this portion of Eau Claire Trail and Court in 1983. The bituminous pavement within the study area is beginning to exhibit wear and distress due to traffic loading as well as typical weathering effects experienced with aging asphalt pavement. The existing pavement contains large transverse cracking (cracks running perpendicular across the roadway), localized random cracking around existing manhole structures, and visible edge cracking typically located within 12 to 18-inches of the gutter edge. Soil borings are scheduled to be completed by Element Materials Technology to determine the existing roadway section. The City of Prior Lake utilizes a Pavement Management Program to rate an existing public street’s pavement condition. Each street segment is surveyed in the field with information gathered relating to the current road distress; data such as the number of potholes, the number and size of cracks, and other statistics which describe the condition of the pavement is collected. This information is then used to compute an Overall Condition Index (OCI) for each street section. The OCI is a tool for comparing streets when considering where roadway improvements are most needed within the City. The street OCI is a number between 0-100, with 100 being the best or signifying a newly paved street and 0 being the worst. In the pavement industry, it’s generally agreed that streets with an OCI 65 need some improvement. Streets in need of a mill and overlay generally have an OCI in the range of 45-65, while streets with an OCI in the range of 35-45 usually require a full depth reclamation. When the OCI reaches a range of 0-35 or when a need for utility repair is determined, the street usually requires full reconstruction. The Overall Condition Index (OCI) for the north/south portion of Eau Claire Trail is a 39 and for Eau Claire Circle is a 39, making both a candidate for a full depth reclamation. Existing OCI for Eau Claire Trail From Street To Street OCI Eau Claire Circle Calmut Avenue 39.92 th Calmut Avenue 154 Street 37.90 Existing OCI for Eau Claire Circle From Street To Street OCI Eau Claire Trail Cul-de-Sac 38.90 There is an existing 6-inch diameter ductile iron pipe (DIP) water main which runs the entire length of the north/south portion of Eau Claire Trail. An existing 6-inch diameter DIP watermain serves Eau Claire Circle connecting into the Eau Claire Trail watermain. Service lines to individual homes within the project area are anticipated to be ¾-inch or 1-inch diameter copper pipe. City records show no previous water main breaks have been experienced in this area. There is an existing 8-inch polyvinyl chloride (PVC) sanitary sewer main which runs the entire length of the north/south portion of Eau Claire Trail starting upstream at the manhole at Eau Claire Circle and ending downstream at the manhole at the south end of the north/south portion. An existing 8-inch PVC sanitary sewer main serves Eau Claire Circle connecting into the Eau Claire Trail sewer main. The existing condition of the sanitary sewer system was documented by videotaping of the sewer main and televising revealed the presence of no physical defects. Service lines to individual homes within the project area are anticipated to be 4-inch diameter PVC pipe. There is not an existing storm sewer system within this portion of Eau Claire Trail. There is a single catchbasin structure within Eau Claire Circle located on the west end of the cul-de-sac. The collected stormwater is piped by reinforced concrete pipe (RCP) to the west between two houses and connects into storm sewer within County Road 21. Proposed Street Improvements Based on the roadway age, surface deterioration, OCI rating, and sub-soils, the proposed improvement for the north/south portion of Eau Claire Trail and Eau Claire Circle is a full depth reclamation of the existing road section. The existing pavement thickness and underlying aggregate base is proposed to be ground up (reclaimed) to a maximum depth of about 12 inches. The process effectively removes all existing cracking in the pavement and improves the upper portions of the aggregate base by combining the existing aggregate base and bituminous pavement into a new aggregate base. After grinding and blending these layers, space is made for the required new pavement thickness and the roadway is paved with new bituminous pavement. The new street matches the existing concrete curb and gutter so horizontally and vertically the roadway remains the same as the existing roadway. Spot curb and gutter repairs will be completed where required. The proposed reclaimed road section will include: 1.5-inches of bituminous pavement wear course 2.5-inches of bituminous pavement base course 12.0-inches of compacted reclaim material Reclamation is a cost effective roadway maintenance procedure for roadways with an existing aggregate base and requiring only roadway surface improvements. Based on the results of the pending soil borings, if the assumed adequate aggregate base is determined of insufficient thickness to perform the proposed full depth in place reclamation, an alternate roadway maintenance procedure will have to be pursued and the resultant increased costs determined. There are expected to be no improvements beyond the edge of the existing roadway concrete curb and gutter for any proposed roadway maintenance procedures. Proposed Sanitary Sewer Improvements Based on the sewer pipe age, material type, and televising results, it was determined no improvements are necessary for the existing sanitary sewer along the north/south portion of Eau Claire Trail or within Eau Claire Circle as part of the proposed project. All existing sanitary sewer manholes castings are proposed for replacement with new concrete adjustments rings and new castings that meet current City standards. No improvements are proposed for the existing sewer services based on no proposed improvements to the existing sewer main line. Proposed Watermain Improvements Based on the watermain pipe age, material type, and lack of break history, it was determined no improvements are necessary for the existing watermain along the north/south portion of Eau Claire Trail or within Eau Claire Circle as part of the proposed project. No improvements are proposed for the existing water services based on no proposed improvements to the existing watermain. Proposed Storm Sewer Improvements The existing catchbasin within Eau Claire Circle is recommended to remain in place and no other improvements are necessary as part of the proposed project. Figure 5 See in Appendix A for the existing sanitary sewer, watermain and storm sewer utilities within Eau Claire Trail and Eau Claire Circle proposed to remain in- place. As previously described within the report, the number of existing street lights within the project area is limited; one existing street light in the cul-de-sac on the south end of Skyline th Avenue, one existing street light on the east end of 154 Street, and four existing street lights along the square loop of Grainwood Circle. The replacement of existing street lights and the addition of new street lights, especially at intersections has been standard practice on past improvements projects within the City and is expected to be incorporated into this project as well. The actual number and location of the new proposed street lights will be determined during final design. The estimated project cost to complete the improvements proposed herein are presented below. These costs include estimated construction costs, a 10% contingency, and 20% overhead cost: financial (2.5%), legal (2.5%), administrative (5%), and engineering (10%). STREET RECONSTRUCTION COST ESTIMATE (WEST SIDE AREA) MARSH STREET, HIGHLAND AVENUE, & SKYLINE AVENUE Table 1-Estimated Cost Summary (See Appendix B for Detailed Cost Estimate) ESTIMATED TOTAL OVERHEAD CONTINGENCY LOCATION CONSTRUCTION ESTIMATED COST (10%) COST (20%) COST COST Skyline Avenue $900,753.00 $90,075.30 $198,165.66 $1,188,993.97 Highland Avenue $803,394.08 $80,339.41 $176,746.70 $1,060,480.19 Marsh Street $490,458.68 $49,045.87 $107,900.91 $647,405.45 TOTAL $2,194,605.76 $219,460.58 $482,813.27 $2,896,879.61 Table 2 – Funding Summary TOTAL ITEM ESTIMATED ASSESSMENTS CITY SHARE COST Sanitary Sewer $553,784.70 $0 $553,784.70 Watermain $638,763.91 $0 $638,763.91 Storm Sewer $271,438.86 $108,575.54 $162,863.32 Street $1,432,892.14 $573,156.86 $859,735.28 TOTAL $2,896,879.61 $681,732.40 $2,215,147.21 STREET RECONSTRUCTION COST ESTIMATE (EAST SIDE AREA) EAU CLAIRE TRAIL & GRAINWOOD CIRCLE Table 3-Estimated Cost Summary (See Appendix B for Detailed Cost Estimate) TOTAL CONSTRUCTION CONTINGENCY OVERHEAD LOCATION ESTIMATED COST COST (10%) COST (20%) COST Grainwood Circle$1,085,959.01 $108,595.90 $238,910.98 $1,433,465.90 Eau Claire Trail $365,932.85 $36,593.29 $80,505.23 $483,031.36 TOTAL $1,451,891.86 $145,189.19 $319,416.21 $1,916,497.26 Table 4 – Funding Summary TOTAL ITEM ESTIMATED ASSESSMENTS CITY SHARE COST Sanitary Sewer $364,463.88 $0 $364,463.88 Watermain $431,625.15 $0 $431,625.15 Storm Sewer $121,630.08 $48,652.03 $72,978.05 Street $998,778.15 $399,511.26 $599,266.89 TOTAL $1,916,497.26 $448,163.29 $1,468,333.97 STREET RECLAMATION COST ESTIMATE (EAST SIDE AREA) EAU CLAIRE TRAIL & EAU CLAIRE CIRCLE Table 5-Estimated Cost Summary (See Appendix B for Detailed Cost Estimate) TOTAL CONSTRUCTION CONTINGENCY OVERHEAD LOCATION ESTIMATED COST COST (10%) COST (20%) COST Eau Claire Circle $27,844.61 $2,784.46 $6,125.81 $36,754.88 Eau Claire Trail / $115,796.28 $11,579.63 $25,475.18 $152,851.08 th 154 Street TOTAL $143,640.89 $14,364.09 $31,600.99 $189,605.96 Table 6 – Funding Summary TOTAL ITEM ESTIMATED ASSESSMENTS CITY SHARE COST Sanitary Sewer $3,234.00 $0 $3,234.00 Watermain $792.00 $0 $792.00 Storm Sewer $0 $0 $0 Street $185,579.96 $0 $185,579.96 TOTAL $189,605.96 $0 $189,605.96 TOTAL PROJECT COST ESTIMATE Table 7 – Funding Summary for TOTAL PROJECT TOTAL ITEM ESTIMATED ASSESSMENTS CITY SHARE COST Sanitary Sewer $921,482.58 $0 $921,482.58 Watermain $1,071,181.06 $0 $1,071,181.06 Storm Sewer $393,068.94 $157,227.57 $235,841.37 Street $2,617,250.25 $972,668.12 $1,644,582.13 TOTAL $5,002,982.83 $1,129,895.69 $3,873,087.14 Assessments are proposed for the benefited properties per the City’s Assessment Policy for Public and Development-Initiated Improvements as found in Appendix D. The proposed assessments are broken down into three different areas as shown on the assessment map found in Appendix C. For the two areas where a full street reconstruction project is proposed all properties that are identified are proposed to be assessed at a calculated unit assessment rate of 40% of the total street and storm sewer project costs for that area. For the third and final area where a street reclamation project is proposed all properties that are identified are proposed to not be assessed any portion of the project costs as this is considered a general maintenance activity. The property tax levy will be used to finance the costs from the remaining 60% of the reconstruction street and storm sewer project costs and 100% of the reclamation street project costs. The project costs for the sanitary sewer and watermain improvements are considered general maintenance and supported by utility fees under the City sewer and water utilities funds and will not be assessed. The proposed project assessments and funding summary are based on preliminary estimated project costs and may be revised at the time of final assessment hearing. The unit assessment rates are proposed to be assessed over a 10-year period at approximately 5.0% interest. The proposed project schedule is shown below: Receive Feasibility (Preliminary Engineering) Report*……….... November 10, 2014 Call for Public Improvement Hearing*……………….…….…… November 10, 2014 Conduct Public Improvement Hearing*…..…………………..…. November 24, 2014 Order Improvement Project and Preparation of Final Plans & Specifications*…………….………..….…….....November 24, 2014 Hold Second Neighborhood Meeting…………………………………...January, 2015 Approve Final Plans & Specifications*…..…………………....…….January 26, 2015 Authorize Advertisement for Bids*………………………………….January 26, 2015 Open Bids…………………………………………………………..February 23, 2015 Accept Bids & Award Contract*……………………………………….March 9, 2015 Construction Start………………………………………………………..…May, 2015 Construction Substantially Complete……………………………...…November, 2015 Conduct Assessment Hearing & Adopt Assessment*………………..November, 2015 Construction Final Complete……………………………………………….June, 2016 * City Council Meeting From an engineering standpoint, this proposed project, is feasible, cost effective, and necessary and can best be accomplished by letting competitive bids for the work under one contract in order to complete the work in an orderly and efficient manner. The City and the persons assessed will have to determine the economic feasibility of the proposed improvements. APPENDIX A APPENDIX A - FIGURES 2015 Street Reconstruction Marsh-Highland-Skyline Project Area 375816861 22098 3731 15351 3754 3733 3750 19226 ADDRESS 4030 PO 3782 379614948 3816 3834 22382 3852 3911 3880 3892 3776 22382 600 PO 5458 5458 15541 350 15532 3795 15531 3883 3895 15557 3899 1520415571 15550 15602 15573 15595 15609 15603 15590 PO 600 4060 15609 15587 15582 15621 15608 15596 15631 15626 167 15606 15640 4075 15616 15637 15615 15658 15630 15629 15668 15967 4018 15650 15641 15680 21001 15653 15690 15663 16395 15687 15675 15685 15701 15724 15751 15753 15731 4091 15711 3733 15717 15733 3782 3782 15780 15777 15788 15787 I 15791 Legend 15790 PO Reconstruction Street Segments Parcels Year Paved PO 0150 1977 / PCI 36 Feet 3773 4030 Source: Prior Lake, Scott County, Esri Imagery 3877 4014 3869 2015 Street Reconstruction Grainwood-Eau Claire Project Area 153514169 16861 4090 4070 15351 4030 4050 4215 15507 4085 PO 4055 600 600 25664 4190 PO 4185 15520 4090 15563 4070 15563 1510 4090 15581 7000 15593 4143 4060 15609 4139 37041 4095 4279 4075 5420 4295 4267 4136 7300 4301 4307 1259 4257 4260 4255 4904 3476 4280 40184066 15581 4131 487 4290 14170 4131 4247 4310 15660 1221 4230 4091 4214 15581 N14454 4043 4196 4065 4186 4168 4148 1221 4229 4221 4128 4211 4646 14518 15717 15753 15717 3476 4203 4043 4197 4080 4185 5100 4151 5218 18620 15795 4680 4072 4070 4062 4060 I PO 4052 Legend 4057 4050 4059 Reclaim or Reconstruction 14518 Street Segments PO Reconstruction 1109 Year Paved 4030 4308 Parcels 4014 1983 / PCI 39 4290 0150 4014 4288 Feet 1977 / PCI 36 4646 4014 Source: Prior Lake, Scott County, Esri Imagery PO 14632 14632 PO 2015 Street Reconstruction Marsh-Highland-Skyline Utilities 37581686115351 22098 3731 3754 3733 3750 19226 G !. ADDRESS 4030 !5 "/ !5 !5 !5 !5 "/ "/ "/ "/ "/ "/ ! !5 G "/!. !5 "/ !5 "/ ! !5 !5 !5 ! "/ "/ G !. !5 "/ !5 !5 ! PO !5 !5 G !. 3782 3796 3852 14948 3816 3880 3834!5 22382 3911 "/"/ 3892 3776 22382 !5 "/5458 PO !5 G !. !5 ! 5458 !5 "/ ! !5 15541 "/ 350 G 600 !. 15532 3795 15531 3883 G !. !5 24'' 3895 15557 3899 !5"/"/!5"/ !5 15571 15550 15204 15602 15595 15573 G 15609!. !5 !5 15603 15590 15609 PO 600 !5 4060 15587 !5 15621 15582 15608 15596 G !. !5 15626 !5 15631 ! 167 15606 !5 "/ G "/ !. 15640 15616 !5 4075 15637 15615 ! !5 15658 !5 15630 "/ 15629 "/15668 15967 4018 15641 15650 !5 15680 "/ "/ "/ "/ "/ "/ !5"/ 21001 15653 !5 15690 G !. !"/ 10'' !5 ! G !. 15663 !5 !5"/ "/ 16395 "/ !5 15687 15675 !5 "/ !5 !5 "/ !5 G !. ! "/ 15685 ! !5 ! "/ !5 ! 15701 G !. 15724 15731 15753 15751 !5 4018 !5 15711 4043 4091 4066 "/ 15733 3782 !5 !5 !5 3782 "/ 15780 G !. 15777 I Legend 15787 15788 !5 WaterHydrantsStorm Inlets G "/ !. 15791 WaterFittingsStorm Outlets !5 15790 PO WaterValvesStorm Manholes ! !5 Public Utilities WaterLateralsStorm Mains Year Installed PO WaterMainsSanitaryManholes !5 Sanitary, Watermain & Storm SanitaryMains 4030 Sewer – 1977 3773 0150 3877 Feet 4014 Source: Prior Lake, Scott County, Esri Imagery 3869 2015 Street Reconstruction Grainwood-Eau Claire Utilities 41694170 15351 16861 15351 4090 4070 4050 4030 !5 !5 "/"/ "/ "/ "/ "/ ! !5 G!5 !5 !. !5 "/ ! "/ "/ !5 !5 "/ !5 4215 !5 ! 15507 Public Utilities !5 4085 !5 G !. G !. ! PO 4055 Year Installed ! 600 !5 4190 25664 PO !5 Sanitary, Watermain & 4185 Storm Sewer – 1983 15520 !5 4090 Sanitary, Watermain & 15563 ! Storm Sewer – 1977 4070 15563 24'' !5 !5"/"/!5"/ 1510 G !. 15581 4090 7000 G !. 15593 ! G !. !5 4143 !5 4060 "/ 15609 600 4139 37041 4095 !5 4279 !5 !5 "/ "/ "/ 4075 !5 !5 4267 4295 4307 4136 5420 7300 !5 G 4301 !. 1259 !5 4257 ! !5 4260 4255 !5 G 4904 !. G 3476 !. 4066 4280 40184131 15581 487 14170 !5 4290 !5 4131 "/ 4247 "/ !5"/ G !. 4310 G !. !"/ 15660 10'' !5 !5 ! 1221 4230 15581 !5"/ "/ "/ 4091 4214 !5 N14454 "/ 4065 4196 !5 4043 !5 4186 4168 !5 4148 1221 "/ "/ G !. "/ ! ! !5!5 "/ 4221 ! !5 4229 4128 4646 G !. !5 4211 15753 14518 15717 !5 4043 !5 3476 G !. 4203 !5 4091 !5 4197 !5 "/ "/ 4080 4185 "/ "/ !5 !5 5100 4151 "/ 5218 "/ ! G !. "/ !5 15795 18620 4680 I Legend 4072 4070 ! G !. Water HydrantsStorm Inlets G "/ 4062!. "/ 4060 Water FittingsStorm Outlets !5 4052 PO 4057 4050 Water ValvesStorm Manholes ! !5 4059 1109 14518 Water LateralsStorm Mains PO Water MainsSanitary Manholes !5 4030 Sanitary Mains 4014 4288 0150 4014 Feet 4290 4014 4646 Source: Prior Lake, Scott County, Esri Imagery PO 14632 14632 APPENDIX B APPENDIX B – PRELIMINARY COST ESTIMATES ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (TOTAL PROJECT) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION(1) 1LUMP SUM1.0000150,000.00$ $150,000.00 2101.502CLEAR AND GRUB(1)(10) 2EACH30350.00$ $10,500.00 2104.501REMOVE CURB & GUTTER(1)(10) 3LF22026.00$ $13,209.00 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT(1)(10) 4SF257381.00$ $25,738.00 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT(1)(10) 5SY11127.00$ $7,784.00 2104.505REMOVE BITUMINOUS PAVEMENT(1)(10) 6SQ YD226121.25$ $28,264.73 2104.509REMOVE SIGN POST (1)(10) 7EACH3850.00$ $1,900.00 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH)(1) 8LF8505.00$ $4,250.00 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH)(1) 9LF23004.00$ $9,200.00 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE(1) 10LF15010.00$ $1,500.00 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE(1)(12) 11LF8012.00$ $960.00 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING(1)(12) 12LF8009.00$ $7,200.00 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM(1)(12) 13LF129016.00$ $20,637.28 2104.523SALVAGE & REINSTALL MAILBOX(1)(12) 14EACH11080.00$ $8,800.00 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK(1) 15SY10020.00$ $2,000.00 2104.618SALVAGE & REINSTALL CONCRETE PAVERS(1)(12) 16SF20906.00$ $12,540.00 2104.618SALVAGE & REINSTALL RETAINING WALL(1)(12) 17SF16015.00$ $2,400.00 2105.501COMMON EXCAVATION(10)(CV)(P) 18CY2500810.00$ $250,083.00 2105.507SUBGRADE EXCAVATION(1)(10)(EV) 19CY446014.00$ $62,433.58 2105.609SELECT GRANULAR BORROW(1) 20CY1667212.00$ $200,066.40 2105.526SELECT TOPSOIL BORROW (1)(9)(LV) 21CY395220.00$ $79,039.47 2105.609AGGREGATE BACKFILL(1)(15)(CV) 22CY446014.00$ $62,433.58 2105.604GEOTEXTILE FABRIC TYPE V(1) 23SY257161.50$ $38,573.30 2123.610STREET SWEEPER (WITH PICKUP BROOM)(13) 24HOUR11580.00$ $9,200.00 2130.501WATER DUST CONTROL(1) 25MG9050.00$ $4,500.00 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED)(1) 26TON1104914.50$ $160,207.05 2215.501FULL DEPTH RECLAMATION(1) 27SY391210.00$ $39,122.22 2357.502BITUMINOUS MATERIAL FOR TACK COAT(1) 28GAL13134.00$ $5,251.68 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B)(1) 29TON201067.00$ $134,698.66 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B)(1) 30TON335164.00$ $214,445.64 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT(1) 31SY316320.00$ $63,259.56 2531.5076" CONCRETE DRIVEWAY PAVEMENT(1) 32SY122838.00$ $46,671.60 2531.501CONCRETE CURB AND GUTTER (1) 33LF1289812.00$ $154,779.60 2531.501CONCRETE CURB AND GUTTER DESIGN D418 (1)(7) 34LF34214.00$ $4,781.00 1 of 3City of Prior Lake, MN ENG EST 11/2/2014 2540.601TEMPORARY MAILBOXES(3) 35LUMP SUM1.00003,000.00$ $3,000.00 2540.618INSTALL CONCRETE PAVERS 36SF15012.00$ $1,800.00 2563.601TRAFFIC CONTROL(3) 37LUMP SUM1.00015,000.00$ $15,000.00 2564.537INSTALL SIGN TYPE C(1) 38EACH2650.00$ $1,300.00 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME)(1)(11) 39EACH14260.00$ $3,640.00 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC)(1)(3) 40EACH30350.00$ $10,500.00 2571.505SHRUB 18" HT (VARIETY - SEE SPEC)(1)(3) 41EACH6050.00$ $3,000.00 2573.502SILT FENCE, TYPE HEAVY DUTY(1)(3)(10) 42LF22003.00$ $6,600.00 2573.530STORM DRAIN INLET PROTECTION(1)(3)(10) 43EACH31350.00$ $10,850.00 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL(1)(3)(10) 44LF11504.00$ $4,600.00 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE(1)(3)(10) 45EACH121,000.00$ $12,000.00 2575.505SODDING TYPE LAWN(1)(3) 46SY246823.00$ $74,046.00 SCHEDULE "A" - STREETS (TOTAL PROJECT) SUBTOTAL$1,982,765.34 10% CONTINGENCY$198,276.53 SCHEDULE "A" - STREETS (TOTAL PROJECT)PROJECT TOTAL$2,181,041.88 SCHEDULE "B" - SANITARY SEWER (TOTAL PROJECT) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE(3) 47 EACH28425.00$ $11,900.00 2105.601DEWATERING(3) 48 LUMP SUM1.0000100,000.00$ $100,000.00 2451.607PIPE BEDDING MATERIAL(1)(14)(LV) 49 CY138740.00$ $55,485.87 2503.602CONNECT TO EXISTING MANHOLES (SAN)(1)(5) 50 EACH5800.00$ $4,000.00 2503.6028"X4" PVC SDR 26 WYE(1)(6) 51 EACH110250.00$ $27,500.00 2503.6034" PVC SEWER SDR 26(1)(6) 52 LF506025.00$ $126,500.00 2503.6038" PVC SEWER SDR 26(1) 53 LF633235.00$ $221,613.00 2503.603LINING SEWER PIPE 8"(1) 54 LF49160.00$ $29,436.00 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT)(1)LIN FT 55 133120.00$ $16,008.00 2506.50248" DIAMETER SANITARY MANHOLE(1)(8)EACH 56 292,400.00$ $69,600.00 2506.622ADJUST FRAME & RING CASTINGEACH 57 7350.00$ $2,450.00 58 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX(1)(8) EACH96350.00$ $33,600.00 SCHEDULE "B" - SANITARY SEWER (TOTAL PROJECT) TOTAL$698,092.87 10% CONTINGENCY$69,809.29 SCHEDULE "B" - SANITARY SEWER (TOTAL PROJECT)PROJECT TOTAL$767,902.15 SCHEDULE "C" - WATERMAIN (TOTAL PROJECT) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN(1) 59 LF61408.00$ $49,120.00 2504.601TEMPORARY WATER SERVICE(1) 60 LUMP SUM1.000090,000.00$ $90,000.00 2504.602CONNECT TO EXISTING WATER MAIN(1)(5) 61 EACH61,000.00$ $6,000.00 2504.602HYDRANT WITH 6" GATE VALVE & BOX(1)(6)(8) 62 EACH193,500.00$ $66,500.00 2504.602ADJUST VALVE BOX 63 EACH4150.00$ $600.00 2504.6028" GATE VALVE AND BOX (1)(8) 64 EACH121,600.00$ $19,200.00 2504.60210" GATE VALVE AND BOX (1)(8) 65 EACH62,000.00$ $12,000.00 2504.6021" CORPORATION STOP(1) 66 EACH110180.00$ $19,800.00 2504.6021" CURB STOP & BOX(1)(8) 67 EACH110275.00$ $30,250.00 2504.6031" TYPE K COPPER PIPE(1) 68 LF550035.00$ $192,500.00 2504.6036" WATERMAIN DUCTILE IRON CL 52(1) 69 LF57035.00$ $19,950.00 2504.6038" WATERMAIN DUCTILE IRON CL 52(1) 70 LF471237.00$ $174,358.80 2504.60310" WATERMAIN DUCTILE IRON CL 52(1) 71 LF173545.00$ $78,057.00 2504.608DUCTILE IRON FITTINGS(1) 72 LBS96715.00$ $48,352.50 73 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY(1) EACH28175.00$ $4,812.50 2 of 3City of Prior Lake, MN ENG EST 11/2/2014 SCHEDULE "C" - WATERMAIN (TOTAL PROJECT) TOTAL$811,500.80 10% CONTINGENCY$81,150.08 SCHEDULE "C" - WATERMAIN (TOTAL PROJECT)PROJECT TOTAL$892,650.88 SCHEDULE "D" - STORM SEWER (TOTAL PROJECT) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT)(1)(10) 74LF17307.00$ $12,110.00 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK)(1) 75LF128985.00$ $64,491.50 2501.51518" RC PIPE APRON(1) 76EACH6800.00$ $4,800.00 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM)(1) 77LF217638.00$ $82,688.00 2503.602CONNECT TO EXISTING STORM SEWER(1)(5) 78EACH1800.00$ $800.00 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301)(1)(8) 79EACH151,200.00$ $18,000.00 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300)(1)(8) 80EACH152,200.00$ $33,000.00 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY)(1)(8) 81LUMP SUM1.000080,000.00$ $80,000.00 2511.501RANDOM RIP RAP CLASS III 82CY4245.00$ $1,890.00 SCHEDULE "D" - STORM SEWER (TOTAL PROJECT) TOTAL$297,779.50 10% CONTINGENCY$29,777.95 SCHEDULE "D" - STORM SEWER (TOTAL PROJECT)PROJECT TOTAL$327,557.45 SCHEDULE "A" - STREETS (TOTAL PROJECT)$1,982,765.34 SCHEDULE "B" - SANITARY SEWER (TOTAL PROJECT)$698,092.87 SCHEDULE "C" - WATERMAIN (TOTAL PROJECT)$811,500.80 SCHEDULE "D" - STORM SEWER (TOTAL PROJECT)$297,779.50 PROJECT SUBTOTAL$3,790,138.51 10% CONTINGENCY$379,013.85 ESTIMATED PROJECT CONSTRUCTION TOTAL$4,169,152.36 20% CONSTRUCTION OVERHEAD$833,830.47 ESTIMATED PROJECT GRAND TOTAL$5,002,982.83 3 of 3City of Prior Lake, MN ENG EST 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (SKYLINE AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.22150,000.00$ 33,000.00$ 2101.502CLEAR AND GRUB 2EACH5350.00$ 1,750.00$ 2104.501REMOVE CURB & GUTTER 3LF6.00$ -$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF62701.00$ 6,270.00$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY1507.00$ 1,050.00$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD55321.25$ 6,914.72$ 2104.509REMOVE SIGN POST 7EACH650.00$ 300.00$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF1005.00$ 500.00$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF6004.00$ 2,400.00$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF1009.00$ 900.00$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF30716.00$ 4,905.60$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH2580.00$ 2,000.00$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY1020.00$ 200.00$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF4506.00$ 2,700.00$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF15.00$ -$ 2105.501COMMON EXCAVATION 18CY634310.00$ 63,428.89$ 2105.507SUBGRADE EXCAVATION 19CY95114.00$ 13,320.07$ 2105.609SELECT GRANULAR BORROW 20CY422912.00$ 50,743.11$ 2105.526SELECT TOPSOIL BORROW 21CY92820.00$ 18,558.22$ 2105.609AGGREGATE BACKFILL 22CY95114.00$ 13,320.07$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY63431.50$ 9,514.33$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON280514.50$ 40,672.20$ 2215.501FULL DEPTH RECLAMATION 27SY10.00$ -$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL2734.00$ 1,090.13$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON43167.00$ 28,873.20$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON71864.00$ 45,967.29$ 1 of 3City of Prior Lake, MN SKYLINE AVE 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY76620.00$ 15,326.67$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY16538.00$ 6,270.00$ 2531.501CONCRETE CURB AND GUTTER 33LF306612.00$ 36,792.00$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF14.00$ -$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.223,000.00$ 660.00$ 2540.618INSTALL CONCRETE PAVERS 36SF15012.00$ 1,800.00$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.2215,000.00$ 3,300.00$ 2564.537INSTALL SIGN TYPE C 38EACH450.00$ 200.00$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH2260.00$ 520.00$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH5350.00$ 1,750.00$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH1050.00$ 500.00$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF4003.00$ 1,200.00$ 2573.530STORM DRAIN INLET PROTECTION 43EACH10350.00$ 3,500.00$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF1504.00$ 600.00$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH21,000.00$ 2,000.00$ 2575.505SODDING TYPE LAWN 46SY58403.00$ 17,520.00$ SCHEDULE "A" - STREETS (SKYLINE AVENUE) TOTAL442,016.50$ 10% CONTINGENCY$ 44,201.65 SCHEDULE "A" - STREETS (SKYLINE AVENUE)PROJECT TOTAL486,218.15$ SCHEDULE "B" - SANITARY SEWER (SKYLINE AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH8425.00$ 3,400.00$ 2105.601DEWATERING 48LUMP SUM0.25100,000.00$ 25,000.00$ 2451.607PIPE BEDDING MATERIAL 49CY37740.00$ 15,075.20$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH1800.00$ 800.00$ 2503.6028"X4" PVC SDR 26 WYE 51EACH25250.00$ 6,250.00$ 2503.6034" PVC SEWER SDR 26 52LF115025.00$ 28,750.00$ 2503.6038" PVC SEWER SDR 26 53LF141335.00$ 49,465.50$ 2503.603LINING SEWER PIPE 8" 54LF10060.00$ 6,000.00$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT41120.00$ 4,968.00$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH92,400.00$ 21,600.00$ 2506.622ADJUST FRAME & RING CASTING 57EACH350.00$ -$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH25350.00$ 8,750.00$ SCHEDULE "B" - SANITARY SEWER (SKYLINE AVENUE) TOTAL170,058.70$ 10% CONTINGENCY$ 17,005.87 SCHEDULE "B" - SANITARY SEWER (SKYLINE AVENUE)PROJECT TOTAL187,064.57$ SCHEDULE "C" - WATERMAIN (SKYLINE AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF16588.00$ 13,264.00$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM0.2490,000.00$ 21,600.00$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH11,000.00$ 1,000.00$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH43,500.00$ 14,000.00$ 2504.602ADJUST VALVE BOX 63EACH150.00$ -$ 2504.6028" GATE VALVE AND BOX 64EACH41,600.00$ 6,400.00$ 2504.60210" GATE VALVE AND BOX 65EACH2,000.00$ -$ 2504.6021" CORPORATION STOP 66EACH25180.00$ 4,500.00$ 2 of 3City of Prior Lake, MN SKYLINE AVE 11/2/2014 2504.6021" CURB STOP & BOX 67EACH25275.00$ 6,875.00$ 2504.6031" TYPE K COPPER PIPE 68LF125035.00$ 43,750.00$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF12035.00$ 4,200.00$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF174137.00$ 64,413.30$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF45.00$ -$ 2504.608DUCTILE IRON FITTINGS 72LBS26115.00$ 13,056.75$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH6175.00$ 1,093.75$ SCHEDULE "C" - WATERMAIN (SKYLINE AVENUE) TOTAL194,152.80$ 10% CONTINGENCY$ 19,415.28 SCHEDULE "C" - WATERMAIN (SKYLINE AVENUE)PROJECT TOTAL213,568.08$ SCHEDULE "D" - STORM SEWER (SKYLINE AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF7507.00$ 5,250.00$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF30665.00$ 15,330.00$ 2501.51518" RC PIPE APRON 76EACH3800.00$ 2,400.00$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF90038.00$ 34,200.00$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH41,200.00$ 4,800.00$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH62,200.00$ 13,200.00$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM0.2380,000.00$ 18,400.00$ 2511.501RANDOM RIP RAP CLASS III 82CY2145.00$ 945.00$ SCHEDULE "D" - STORM SEWER (SKYLINE AVENUE) TOTAL94,525.00$ 10% CONTINGENCY$ 9,452.50 SCHEDULE "D" - STORM SEWER (SKYLINE AVENUE)PROJECT TOTAL103,977.50$ SCHEDULE "A" - STREETS (SKYLINE AVENUE)$ 486,218.15 SCHEDULE "B" - SANITARY SEWER (SKYLINE AVENUE)$ 187,064.57 SCHEDULE "C" - WATERMAIN (SKYLINE AVENUE)$ 213,568.08 SCHEDULE "D" - STORM SEWER (SKYLINE AVENUE)$ 103,977.50 ESTIMATED PROJECT CONSTRUCTION TOTAL$ 990,828.30 20% CONSTRUCTION OVERHEAD$ 198,165.66 ESTIMATED PROJECT GRAND TOTAL$ 1,188,993.97 3 of 3City of Prior Lake, MN SKYLINE AVE 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (HIGHLAND AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.21150,000.00$ 31,500.00$ 2101.502CLEAR AND GRUB 2EACH5350.00$ 1,750.00$ 2104.501REMOVE CURB & GUTTER 3LF18006.00$ 10,800.00$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF42001.00$ 4,200.00$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY5007.00$ 3,500.00$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD50581.25$ 6,322.71$ 2104.509REMOVE SIGN POST 7EACH650.00$ 300.00$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF4005.00$ 2,000.00$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF4504.00$ 1,800.00$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF2009.00$ 1,800.00$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF28016.00$ 4,485.60$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH2780.00$ 2,160.00$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY1020.00$ 200.00$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF6.00$ -$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF15.00$ -$ 2105.501COMMON EXCAVATION 18CY554810.00$ 55,476.67$ 2105.507SUBGRADE EXCAVATION 19CY83214.00$ 11,650.10$ 2105.609SELECT GRANULAR BORROW 20CY369812.00$ 44,381.33$ 2105.526SELECT TOPSOIL BORROW 21CY84820.00$ 16,969.33$ 2105.609AGGREGATE BACKFILL 22CY83214.00$ 11,650.10$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY58001.50$ 8,699.75$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON245314.50$ 35,573.04$ 2215.501FULL DEPTH RECLAMATION 27SY10.00$ -$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL2494.00$ 996.80$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON37767.00$ 25,253.31$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON62864.00$ 40,204.27$ 1 of 3City of Prior Lake, MN HIGHLAND AVE 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY51320.00$ 10,266.67$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY55038.00$ 20,900.00$ 2531.501CONCRETE CURB AND GUTTER 33LF280412.00$ 33,642.00$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF14.00$ -$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.213,000.00$ 630.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.2115,000.00$ 3,150.00$ 2564.537INSTALL SIGN TYPE C 38EACH450.00$ 200.00$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH2260.00$ 520.00$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH5350.00$ 1,750.00$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH1050.00$ 500.00$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF4003.00$ 1,200.00$ 2573.530STORM DRAIN INLET PROTECTION 43EACH6350.00$ 2,100.00$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF1504.00$ 600.00$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH21,000.00$ 2,000.00$ 2575.505SODDING TYPE LAWN 46SY53403.00$ 16,020.00$ SCHEDULE "A" - STREETS (HIGHLAND AVENUE) TOTAL416,851.67$ 10% CONTINGENCY$ 41,685.17 SCHEDULE "A" - STREETS (HIGHLAND AVENUE)PROJECT TOTAL458,536.83$ SCHEDULE "B" - SANITARY SEWER (HIGHLAND AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH7425.00$ 2,975.00$ 2105.601DEWATERING 48LUMP SUM0.20100,000.00$ 20,000.00$ 2451.607PIPE BEDDING MATERIAL 49CY12240.00$ 4,890.67$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH1800.00$ 800.00$ 2503.6028"X4" PVC SDR 26 WYE 51EACH27250.00$ 6,750.00$ 2503.6034" PVC SEWER SDR 26 52LF124225.00$ 31,050.00$ 2503.6038" PVC SEWER SDR 26 53LF137635.00$ 48,142.50$ 2503.603LINING SEWER PIPE 8" 54LF60.00$ -$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT32120.00$ 3,864.00$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH72,400.00$ 16,800.00$ 2506.622ADJUST FRAME & RING CASTING 57EACH350.00$ -$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH27350.00$ 9,450.00$ SCHEDULE "B" - SANITARY SEWER (HIGHLAND AVENUE) TOTAL144,722.17$ 10% CONTINGENCY$ 14,472.22 SCHEDULE "B" - SANITARY SEWER (HIGHLAND AVENUE)PROJECT TOTAL159,194.38$ SCHEDULE "C" - WATERMAIN (HIGHLAND AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF13408.00$ 10,720.00$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM0.2290,000.00$ 19,800.00$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH11,000.00$ 1,000.00$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH43,500.00$ 14,000.00$ 2504.602ADJUST VALVE BOX 63EACH150.00$ -$ 2504.6028" GATE VALVE AND BOX 64EACH31,600.00$ 4,800.00$ 2504.60210" GATE VALVE AND BOX 65EACH2,000.00$ -$ 2504.6021" CORPORATION STOP 66EACH27180.00$ 4,860.00$ 2 of 3City of Prior Lake, MN HIGHLAND AVE 11/2/2014 2504.6021" CURB STOP & BOX 67EACH27275.00$ 7,425.00$ 2504.6031" TYPE K COPPER PIPE 68LF135035.00$ 47,250.00$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF12035.00$ 4,200.00$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF140737.00$ 52,059.00$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF45.00$ -$ 2504.608DUCTILE IRON FITTINGS 72LBS21115.00$ 10,552.50$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH7175.00$ 1,181.25$ SCHEDULE "C" - WATERMAIN (HIGHLAND AVENUE) TOTAL177,847.75$ 10% CONTINGENCY$ 17,784.78 SCHEDULE "C" - WATERMAIN (HIGHLAND AVENUE)PROJECT TOTAL195,632.53$ SCHEDULE "D" - STORM SEWER (HIGHLAND AVENUE) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF4007.00$ 2,800.00$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF28045.00$ 14,017.50$ 2501.51518" RC PIPE APRON 76EACH1800.00$ 800.00$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF48038.00$ 18,240.00$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH31,200.00$ 3,600.00$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH32,200.00$ 6,600.00$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM0.2280,000.00$ 17,600.00$ 2511.501RANDOM RIP RAP CLASS III 82CY745.00$ 315.00$ SCHEDULE "D" - STORM SEWER (HIGHLAND AVENUE) TOTAL63,972.50$ 10% CONTINGENCY$ 6,397.25 SCHEDULE "D" - STORM SEWER (HIGHLAND AVENUE)PROJECT TOTAL70,369.75$ SCHEDULE "A" - STREETS (HIGHLAND AVENUE)$ 458,536.83 SCHEDULE "B" - SANITARY SEWER (HIGHLAND AVENUE)$ 159,194.38 SCHEDULE "C" - WATERMAIN (HIGHLAND AVENUE)$ 195,632.53 SCHEDULE "D" - STORM SEWER (HIGHLAND AVENUE)$ 70,369.75 ESTIMATED PROJECT GRAND TOTAL$ 883,733.49 20% CONSTRUCTION OVERHEAD$ 176,746.70 ESTIMATED PROJECT GRAND TOTAL$ 1,060,480.19 3 of 3City of Prior Lake, MN HIGHLAND AVE 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (MARSH STREET) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.12150,000.00$ 17,400.00$ 2101.502CLEAR AND GRUB 2EACH5350.00$ 1,750.00$ 2104.501REMOVE CURB & GUTTER 3LF6.00$ -$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF31001.00$ 3,100.00$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY1007.00$ 700.00$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD28321.25$ 3,540.24$ 2104.509REMOVE SIGN POST 7EACH650.00$ 300.00$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF1005.00$ 500.00$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF3004.00$ 1,200.00$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF2009.00$ 1,800.00$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF15716.00$ 2,516.80$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH1780.00$ 1,360.00$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY1020.00$ 200.00$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF6.00$ -$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF15.00$ -$ 2105.501COMMON EXCAVATION 18CY310610.00$ 31,062.78$ 2105.507SUBGRADE EXCAVATION 19CY46614.00$ 6,523.18$ 2105.609SELECT GRANULAR BORROW 20CY207112.00$ 24,850.22$ 2105.526SELECT TOPSOIL BORROW 21CY45420.00$ 9,088.44$ 2105.609AGGREGATE BACKFILL 22CY46614.00$ 6,523.18$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY31061.50$ 4,659.42$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON137414.50$ 19,918.24$ 2215.501FULL DEPTH RECLAMATION 27SY10.00$ -$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL1394.00$ 556.11$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON21167.00$ 14,139.96$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON35264.00$ 22,511.38$ 1 of 3City of Prior Lake, MN MARSH ST 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY39620.00$ 7,922.22$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY11538.00$ 4,370.00$ 2531.501CONCRETE CURB AND GUTTER 33LF157312.00$ 18,876.00$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF14.00$ -$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.123,000.00$ 348.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.1215,000.00$ 1,740.00$ 2564.537INSTALL SIGN TYPE C 38EACH450.00$ 200.00$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH2260.00$ 520.00$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH5350.00$ 1,750.00$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH1050.00$ 500.00$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF2003.00$ 600.00$ 2573.530STORM DRAIN INLET PROTECTION 43EACH5350.00$ 1,750.00$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF4004.00$ 1,600.00$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH21,000.00$ 2,000.00$ 2575.505SODDING TYPE LAWN 46SY28603.00$ 8,580.00$ SCHEDULE "A" - STREETS (MARSH STREET) TOTAL226,656.18$ 10% CONTINGENCY$ 22,665.62 SCHEDULE "A" - STREETS (MARSH STREET)PROJECT TOTAL249,321.79$ SCHEDULE "B" - SANITARY SEWER (MARSH STREET) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH3425.00$ 1,275.00$ 2105.601DEWATERING 48LUMP SUM0.15100,000.00$ 15,000.00$ 2451.607PIPE BEDDING MATERIAL 49CY7040.00$ 2,816.00$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH1800.00$ 800.00$ 2503.6028"X4" PVC SDR 26 WYE 51EACH17250.00$ 4,250.00$ 2503.6034" PVC SEWER SDR 26 52LF78225.00$ 19,550.00$ 2503.6038" PVC SEWER SDR 26 53LF79235.00$ 27,720.00$ 2503.603LINING SEWER PIPE 8" 54LF39160.00$ 23,436.00$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT14120.00$ 1,656.00$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH32,400.00$ 7,200.00$ 2506.622ADJUST FRAME & RING CASTING 57EACH350.00$ -$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH3350.00$ 1,050.00$ SCHEDULE "B" - SANITARY SEWER (MARSH STREET) TOTAL104,753.00$ 10% CONTINGENCY$ 10,475.30 SCHEDULE "B" - SANITARY SEWER (MARSH STREET)PROJECT TOTAL115,228.30$ SCHEDULE "C" - WATERMAIN (MARSH STREET) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF7908.00$ 6,320.00$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM0.1490,000.00$ 12,600.00$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH11,000.00$ 1,000.00$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH33,500.00$ 10,500.00$ 2504.602ADJUST VALVE BOX 63EACH150.00$ -$ 2504.6028" GATE VALVE AND BOX 64EACH21,600.00$ 3,200.00$ 2504.60210" GATE VALVE AND BOX 65EACH2,000.00$ -$ 2504.6021" CORPORATION STOP 66EACH17180.00$ 3,060.00$ 2 of 3City of Prior Lake, MN MARSH ST 11/2/2014 2504.6021" CURB STOP & BOX 67EACH17275.00$ 4,675.00$ 2504.6031" TYPE K COPPER PIPE 68LF85035.00$ 29,750.00$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF9035.00$ 3,150.00$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF83037.00$ 30,691.50$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF45.00$ -$ 2504.608DUCTILE IRON FITTINGS 72LBS12445.00$ 6,221.25$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH4175.00$ 743.75$ SCHEDULE "C" - WATERMAIN (MARSH STREET) TOTAL111,911.50$ 10% CONTINGENCY$ 11,191.15 SCHEDULE "C" - WATERMAIN (MARSH STREET)PROJECT TOTAL123,102.65$ SCHEDULE "D" - STORM SEWER (MARSH STREET) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF3307.00$ 2,310.00$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF15735.00$ 7,865.00$ 2501.51518" RC PIPE APRON 76EACH1800.00$ 800.00$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF39638.00$ 15,048.00$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH1800.00$ 800.00$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH31,200.00$ 3,600.00$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH22,200.00$ 4,400.00$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM0.1580,000.00$ 12,000.00$ 2511.501RANDOM RIP RAP CLASS III 82CY745.00$ 315.00$ SCHEDULE "D" - STORM SEWER (MARSH STREET) TOTAL47,138.00$ 10% CONTINGENCY$ 4,713.80 SCHEDULE "D" - STORM SEWER (MARSH STREET)PROJECT TOTAL51,851.80$ SCHEDULE "A" - STREETS (MARSH STREET)$ 249,321.79 SCHEDULE "B" - SANITARY SEWER (MARSH STREET)$ 115,228.30 SCHEDULE "C" - WATERMAIN (MARSH STREET)$ 123,102.65 SCHEDULE "D" - STORM SEWER (MARSH STREET)$ 51,851.80 ESTIMATED PROJECT CONSTRUCTION TOTAL$ 539,504.54 20% CONSTRUCTION OVERHEAD$ 107,900.91 ESTIMATED PROJECT GRAND TOTAL$ 647,405.45 3 of 3City of Prior Lake, MN MARSH ST 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (GRAINWOOD 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.13150,000.00$ 19,500.00$ 2101.502CLEAR AND GRUB 2EACH5350.00$ 1,750.00$ 2104.501REMOVE CURB & GUTTER 3LF6.00$ -$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF43881.00$ 4,388.00$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY1817.00$ 1,267.00$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD31371.25$ 3,921.50$ 2104.509REMOVE SIGN POST 7EACH650.00$ 300.00$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF1255.00$ 625.00$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF3004.00$ 1,200.00$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF15010.00$ 1,500.00$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF8012.00$ 960.00$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF1009.00$ 900.00$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF17416.00$ 2,782.08$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH1480.00$ 1,120.00$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY2020.00$ 400.00$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF3006.00$ 1,800.00$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF6015.00$ 900.00$ 2105.501COMMON EXCAVATION 18CY344110.00$ 34,408.00$ 2105.507SUBGRADE EXCAVATION 19CY51614.00$ 7,225.68$ 2105.609SELECT GRANULAR BORROW 20CY229412.00$ 27,526.40$ 2105.526SELECT TOPSOIL BORROW 21CY52620.00$ 10,524.80$ 2105.609AGGREGATE BACKFILL 22CY51614.00$ 7,225.68$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY35971.50$ 5,395.80$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON152214.50$ 22,063.28$ 2215.501FULL DEPTH RECLAMATION 27SY10.00$ -$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL1554.00$ 618.24$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON23467.00$ 15,662.72$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON39064.00$ 24,935.68$ 1 of 3City of Prior Lake, MN GRAINWOOD 32' B-B 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY53620.00$ 10,726.22$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY19938.00$ 7,565.80$ 2531.501CONCRETE CURB AND GUTTER 33LF173912.00$ 20,865.60$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF14.00$ -$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.133,000.00$ 390.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.1315,000.00$ 1,950.00$ 2564.537INSTALL SIGN TYPE C 38EACH450.00$ 200.00$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH2260.00$ 520.00$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH5350.00$ 1,750.00$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH1050.00$ 500.00$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF4003.00$ 1,200.00$ 2573.530STORM DRAIN INLET PROTECTION 43EACH3350.00$ 1,050.00$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF1504.00$ 600.00$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH21,000.00$ 2,000.00$ 2575.505SODDING TYPE LAWN 46SY33123.00$ 9,936.00$ SCHEDULE "A" - STREETS (GRAINWOOD 32' B-B) TOTAL259,853.48$ 10% CONTINGENCY$ 25,985.35 SCHEDULE "A" - STREETS (GRAINWOOD 32' B-B)PROJECT TOTAL285,838.83$ SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH3425.00$ 1,275.00$ 2105.601DEWATERING 48LUMP SUM0.12100,000.00$ 12,000.00$ 2451.607PIPE BEDDING MATERIAL 49CY21640.00$ 8,624.00$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH1800.00$ 800.00$ 2503.6028"X4" PVC SDR 26 WYE 51EACH14250.00$ 3,500.00$ 2503.6034" PVC SEWER SDR 26 52LF64425.00$ 16,100.00$ 2503.6038" PVC SEWER SDR 26 53LF80935.00$ 28,297.50$ 2503.603LINING SEWER PIPE 8" 54LF60.00$ -$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT14120.00$ 1,656.00$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH32,400.00$ 7,200.00$ 2506.622ADJUST FRAME & RING CASTING 57EACH350.00$ -$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH14350.00$ 4,900.00$ SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 32' B-B) TOTAL84,352.50$ 10% CONTINGENCY$ 8,435.25 SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 32' B-B)PROJECT TOTAL92,787.75$ SCHEDULE "C" - WATERMAIN (GRAINWOOD 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF7698.00$ 6,152.00$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM0.1390,000.00$ 11,700.00$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH11,000.00$ 1,000.00$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH23,500.00$ 7,000.00$ 2504.602ADJUST VALVE BOX 63EACH150.00$ -$ 2504.6028" GATE VALVE AND BOX 64EACH1,600.00$ -$ 2504.60210" GATE VALVE AND BOX 65EACH32,000.00$ 6,000.00$ 2504.6021" CORPORATION STOP 66EACH14180.00$ 2,520.00$ 2 of 3City of Prior Lake, MN GRAINWOOD 32' B-B 11/2/2014 2504.6021" CURB STOP & BOX 67EACH14275.00$ 3,850.00$ 2504.6031" TYPE K COPPER PIPE 68LF70035.00$ 24,500.00$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF6035.00$ 2,100.00$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF37.00$ -$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF80745.00$ 36,335.25$ 2504.608DUCTILE IRON FITTINGS 72LBS12115.00$ 6,055.88$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH4175.00$ 612.50$ SCHEDULE "C" - WATERMAIN (GRAINWOOD 32' B-B) TOTAL107,825.63$ 10% CONTINGENCY$ 10,782.56 SCHEDULE "C" - WATERMAIN (GRAINWOOD 32' B-B)PROJECT TOTAL118,608.19$ SCHEDULE "D" - STORM SEWER (GRAINWOOD 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF7.00$ -$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF17395.00$ 8,694.00$ 2501.51518" RC PIPE APRON 76EACH800.00$ -$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF10038.00$ 3,800.00$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH21,200.00$ 2,400.00$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH12,200.00$ 2,200.00$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM0.1380,000.00$ 10,400.00$ 2511.501RANDOM RIP RAP CLASS III 82CY45.00$ -$ SCHEDULE "D" - STORM SEWER (GRAINWOOD 32' B-B) TOTAL27,494.00$ 10% CONTINGENCY$ 2,749.40 SCHEDULE "D" - STORM SEWER (GRAINWOOD 32' B-B)PROJECT TOTAL30,243.40$ 3 of 3City of Prior Lake, MN GRAINWOOD 32' B-B 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (GRAINWOOD 26' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.15150,000.00$ 22,650.00$ 2101.502CLEAR AND GRUB 2EACH5350.00$ 1,750.00$ 2104.501REMOVE CURB & GUTTER 3LF606.00$ 360.00$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF48001.00$ 4,800.00$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY1817.00$ 1,267.00$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD34001.25$ 4,250.28$ 2104.509REMOVE SIGN POST 7EACH850.00$ 400.00$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF1255.00$ 625.00$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF4004.00$ 1,600.00$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF1009.00$ 900.00$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF22516.00$ 3,595.20$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH1980.00$ 1,520.00$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY4020.00$ 800.00$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF13406.00$ 8,040.00$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF10015.00$ 1,500.00$ 2105.501COMMON EXCAVATION 18CY366210.00$ 36,617.78$ 2105.507SUBGRADE EXCAVATION 19CY54914.00$ 7,689.73$ 2105.609SELECT GRANULAR BORROW 20CY244112.00$ 29,294.22$ 2105.526SELECT TOPSOIL BORROW 21CY68020.00$ 13,600.89$ 2105.609AGGREGATE BACKFILL 22CY54914.00$ 7,689.73$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY38281.50$ 5,742.33$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON160914.50$ 23,327.77$ 2215.501FULL DEPTH RECLAMATION 27SY10.00$ -$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL1574.00$ 627.73$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON23767.00$ 15,903.23$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON39664.00$ 25,318.58$ 1 of 3City of Prior Lake, MN GRAINWOOD 26' B-B 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY58720.00$ 11,733.33$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY19938.00$ 7,565.80$ 2531.501CONCRETE CURB AND GUTTER 33LF224712.00$ 26,964.00$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF14.00$ -$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.153,000.00$ 453.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.1515,000.00$ 2,265.00$ 2564.537INSTALL SIGN TYPE C 38EACH650.00$ 300.00$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH4260.00$ 1,040.00$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH5350.00$ 1,750.00$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH1050.00$ 500.00$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF4003.00$ 1,200.00$ 2573.530STORM DRAIN INLET PROTECTION 43EACH7350.00$ 2,450.00$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF1504.00$ 600.00$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH21,000.00$ 2,000.00$ 2575.505SODDING TYPE LAWN 46SY42803.00$ 12,840.00$ SCHEDULE "A" - STREETS (GRAINWOOD 26' B-B) TOTAL293,230.61$ 10% CONTINGENCY$ 29,323.06 SCHEDULE "A" - STREETS (GRAINWOOD 26' B-B)PROJECT TOTAL322,553.68$ SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 26' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH4425.00$ 1,700.00$ 2105.601DEWATERING 48LUMP SUM0.19100,000.00$ 19,000.00$ 2451.607PIPE BEDDING MATERIAL 49CY53740.00$ 21,466.67$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH800.00$ -$ 2503.6028"X4" PVC SDR 26 WYE 51EACH19250.00$ 4,750.00$ 2503.6034" PVC SEWER SDR 26 52LF87425.00$ 21,850.00$ 2503.6038" PVC SEWER SDR 26 53LF120835.00$ 42,262.50$ 2503.603LINING SEWER PIPE 8" 54LF60.00$ -$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT18120.00$ 2,208.00$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH42,400.00$ 9,600.00$ 2506.622ADJUST FRAME & RING CASTING 57EACH350.00$ -$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH19350.00$ 6,650.00$ SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 26' B-B) TOTAL129,487.17$ 10% CONTINGENCY$ 12,948.72 SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 26' B-B)PROJECT TOTAL142,435.88$ SCHEDULE "C" - WATERMAIN (GRAINWOOD 26' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF8838.00$ 7,064.00$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM0.1790,000.00$ 15,300.00$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH11,000.00$ 1,000.00$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH33,500.00$ 10,500.00$ 2504.602ADJUST VALVE BOX 63EACH150.00$ -$ 2504.6028" GATE VALVE AND BOX 64EACH1,600.00$ -$ 2504.60210" GATE VALVE AND BOX 65EACH32,000.00$ 6,000.00$ 2504.6021" CORPORATION STOP 66EACH19180.00$ 3,420.00$ 2 of 3City of Prior Lake, MN GRAINWOOD 26' B-B 11/2/2014 2504.6021" CURB STOP & BOX 67EACH19275.00$ 5,225.00$ 2504.6031" TYPE K COPPER PIPE 68LF95035.00$ 33,250.00$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF9035.00$ 3,150.00$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF37.00$ -$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF92745.00$ 41,721.75$ 2504.608DUCTILE IRON FITTINGS 72LBS13915.00$ 6,953.63$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH5175.00$ 831.25$ SCHEDULE "C" - WATERMAIN (GRAINWOOD 26' B-B) TOTAL134,415.63$ 10% CONTINGENCY$ 13,441.56 SCHEDULE "C" - WATERMAIN (GRAINWOOD 26' B-B)PROJECT TOTAL147,857.19$ SCHEDULE "D" - STORM SEWER (GRAINWOOD 26' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF2507.00$ 1,750.00$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF22475.00$ 11,235.00$ 2501.51518" RC PIPE APRON 76EACH1800.00$ 800.00$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF30038.00$ 11,400.00$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH31,200.00$ 3,600.00$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH32,200.00$ 6,600.00$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM0.1780,000.00$ 13,600.00$ 2511.501RANDOM RIP RAP CLASS III 82CY745.00$ 315.00$ SCHEDULE "D" - STORM SEWER (GRAINWOOD 26' B-B) TOTAL49,300.00$ 10% CONTINGENCY$ 4,930.00 SCHEDULE "D" - STORM SEWER (GRAINWOOD 26' B-B)PROJECT TOTAL54,230.00$ SCHEDULE "A" - STREETS (GRAINWOOD 26' B-B)$ 322,553.68 SCHEDULE "B" - SANITARY SEWER (GRAINWOOD 26' B-B)$ 142,435.88 SCHEDULE "C" - WATERMAIN (GRAINWOOD 26' B-B)$ 147,857.19 SCHEDULE "D" - STORM SEWER (GRAINWOOD 26' B-B)$ 54,230.00 ESTIMATED PROJECT CONSTRUCTION TOTAL$ 667,076.75 20% CONSTRUCTION OVERHEAD$ 133,415.35 ESTIMATED PROJECT GRAND TOTAL$ 800,492.10 3 of 3City of Prior Lake, MN GRAINWOOD 26' B-B 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECON 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.10150,000.00$ 15,000.00$ 2101.502CLEAR AND GRUB 2EACH5350.00$ 1,750.00$ 2104.501REMOVE CURB & GUTTER 3LF6.00$ -$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF29801.00$ 2,980.00$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY7.00$ -$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD26521.25$ 3,315.28$ 2104.509REMOVE SIGN POST 7EACH650.00$ 300.00$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF5.00$ -$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF2504.00$ 1,000.00$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF1009.00$ 900.00$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF14716.00$ 2,352.00$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH880.00$ 640.00$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY1020.00$ 200.00$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF6.00$ -$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF15.00$ -$ 2105.501COMMON EXCAVATION 18CY290910.00$ 29,088.89$ 2105.507SUBGRADE EXCAVATION 19CY43614.00$ 6,108.67$ 2105.609SELECT GRANULAR BORROW 20CY193912.00$ 23,271.11$ 2105.526SELECT TOPSOIL BORROW 21CY44520.00$ 8,897.78$ 2105.609AGGREGATE BACKFILL 22CY43614.00$ 6,108.67$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY30411.50$ 4,561.67$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON128614.50$ 18,652.53$ 2215.501FULL DEPTH RECLAMATION 27SY10.00$ -$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL1314.00$ 522.67$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON19867.00$ 13,241.43$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON32964.00$ 21,080.89$ 1 of 3City of Prior Lake, MN EAU CLAIRE TRAIL 32' RECON 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY36420.00$ 7,284.44$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY38.00$ -$ 2531.501CONCRETE CURB AND GUTTER 33LF147012.00$ 17,640.00$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF14.00$ -$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.103,000.00$ 300.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.1015,000.00$ 1,500.00$ 2564.537INSTALL SIGN TYPE C 38EACH450.00$ 200.00$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH2260.00$ 520.00$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH5350.00$ 1,750.00$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH1050.00$ 500.00$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF4003.00$ 1,200.00$ 2573.530STORM DRAIN INLET PROTECTION 43EACH350.00$ -$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF1504.00$ 600.00$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH21,000.00$ 2,000.00$ 2575.505SODDING TYPE LAWN 46SY28003.00$ 8,400.00$ SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECON 32' B-B) TOTAL203,566.02$ 10% CONTINGENCY$ 20,356.60 SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECON 32' B-B)PROJECT TOTAL223,922.62$ SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECON 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH3425.00$ 1,275.00$ 2105.601DEWATERING 48LUMP SUM0.09100,000.00$ 9,000.00$ 2451.607PIPE BEDDING MATERIAL 49CY6540.00$ 2,613.33$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH1800.00$ 800.00$ 2503.6028"X4" PVC SDR 26 WYE 51EACH8250.00$ 2,000.00$ 2503.6034" PVC SEWER SDR 26 52LF36825.00$ 9,200.00$ 2503.6038" PVC SEWER SDR 26 53LF73535.00$ 25,725.00$ 2503.603LINING SEWER PIPE 8" 54LF60.00$ -$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT14120.00$ 1,656.00$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH32,400.00$ 7,200.00$ 2506.622ADJUST FRAME & RING CASTING 57EACH350.00$ -$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH8350.00$ 2,800.00$ SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECON 32' B-B) TOTAL62,269.33$ 10% CONTINGENCY$ 6,226.93 SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECON 32' B-B)PROJECT TOTAL68,496.27$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECON 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF7008.00$ 5,600.00$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM0.1090,000.00$ 9,000.00$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH11,000.00$ 1,000.00$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH33,500.00$ 10,500.00$ 2504.602ADJUST VALVE BOX 63EACH150.00$ -$ 2504.6028" GATE VALVE AND BOX 64EACH31,600.00$ 4,800.00$ 2504.60210" GATE VALVE AND BOX 65EACH2,000.00$ -$ 2504.6021" CORPORATION STOP 66EACH8180.00$ 1,440.00$ 2 of 3City of Prior Lake, MN EAU CLAIRE TRAIL 32' RECON 11/2/2014 2504.6021" CURB STOP & BOX 67EACH8275.00$ 2,200.00$ 2504.6031" TYPE K COPPER PIPE 68LF40035.00$ 14,000.00$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF9035.00$ 3,150.00$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF73537.00$ 27,195.00$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF45.00$ -$ 2504.608DUCTILE IRON FITTINGS 72LBS11035.00$ 5,512.50$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH2175.00$ 350.00$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECON 32' B-B) TOTAL84,747.50$ 10% CONTINGENCY$ 8,474.75 SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECON 32' B-B)PROJECT TOTAL93,222.25$ SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECON 32' B-B) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF7.00$ -$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF14705.00$ 7,350.00$ 2501.51518" RC PIPE APRON 76EACH800.00$ -$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF38.00$ -$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH1,200.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH2,200.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM0.1080,000.00$ 8,000.00$ 2511.501RANDOM RIP RAP CLASS III 82CY45.00$ -$ SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECON 32' B-B) TOTAL15,350.00$ 10% CONTINGENCY$ 1,535.00 SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECON 32' B-B)PROJECT TOTAL16,885.00$ SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECON 32' B-B)$ 223,922.62 SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECON 32' B-B)68,496.27$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECON 32' B-B)$ 93,222.25 SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECON 32' B-B)$ 16,885.00 ESTIMATED PROJECT CONSTRUCTION TOTAL$ 402,526.14 20% CONSTRUCTION OVERHEAD$ 80,505.23 ESTIMATED PROJECT GRAND TOTAL$ 483,031.36 3 of 3City of Prior Lake, MN EAU CLAIRE TRAIL 32' RECON 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (EAU CLAIRE CIRCLE RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.01150,000.00$ 1,950.00$ 2101.502CLEAR AND GRUB 2EACH350.00$ -$ 2104.501REMOVE CURB & GUTTER 3LF646.00$ 384.00$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF1.00$ -$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY7.00$ -$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD1.25$ -$ 2104.509REMOVE SIGN POST 7EACH50.00$ -$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF5.00$ -$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF4.00$ -$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF9.00$ -$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF16.00$ -$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH80.00$ -$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY20.00$ -$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF6.00$ -$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF15.00$ -$ 2105.501COMMON EXCAVATION 18CY10.00$ -$ 2105.507SUBGRADE EXCAVATION 19CY13314.00$ 1,858.37$ 2105.609SELECT GRANULAR BORROW 20CY12.00$ -$ 2105.526SELECT TOPSOIL BORROW 21CY2020.00$ 400.00$ 2105.609AGGREGATE BACKFILL 22CY13314.00$ 1,858.37$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY1.50$ -$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1080.00$ 800.00$ 2130.501WATER DUST CONTROL 25MG1050.00$ 500.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON14.50$ -$ 2215.501FULL DEPTH RECLAMATION 27SY74710.00$ 7,466.67$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL374.00$ 149.33$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON6267.00$ 4,127.20$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON10364.00$ 6,570.67$ 1 of 3City of Prior Lake, MN EAU CLAIRE CIRCLE RECLAIM 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY20.00$ -$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY38.00$ -$ 2531.501CONCRETE CURB AND GUTTER 33LF12.00$ -$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF6414.00$ 896.00$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.013,000.00$ 39.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.0115,000.00$ 195.00$ 2564.537INSTALL SIGN TYPE C 38EACH50.00$ -$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH260.00$ -$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH350.00$ -$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH50.00$ -$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF3.00$ -$ 2573.530STORM DRAIN INLET PROTECTION 43EACH350.00$ -$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF4.00$ -$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH1,000.00$ -$ 2575.505SODDING TYPE LAWN 46SY503.00$ 150.00$ SCHEDULE "A" - STREETS (EAU CLAIRE CIRCLE RECLAIM) TOTAL27,344.61$ 10% CONTINGENCY$ 2,734.46 SCHEDULE "A" - STREETS (EAU CLAIRE CIRCLE RECLAIM)PROJECT TOTAL30,079.07$ SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE CIRCLE RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH425.00$ -$ 2105.601DEWATERING 48LUMP SUM100,000.00$ -$ 2451.607PIPE BEDDING MATERIAL 49CY40.00$ -$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH800.00$ -$ 2503.6028"X4" PVC SDR 26 WYE 51EACH250.00$ -$ 2503.6034" PVC SEWER SDR 26 52LF25.00$ -$ 2503.6038" PVC SEWER SDR 26 53LF35.00$ -$ 2503.603LINING SEWER PIPE 8" 54LF60.00$ -$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT120.00$ -$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH2,400.00$ -$ 2506.622ADJUST FRAME & RING CASTING 57EACH1350.00$ 350.00$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH350.00$ -$ SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE CIRCLE RECLAIM) TOTAL350.00$ 10% CONTINGENCY$ 35.00 SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE CIRCLE RECLAIM)PROJECT TOTAL385.00$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE CIRCLE RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF8.00$ -$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM90,000.00$ -$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH1,000.00$ -$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH3,500.00$ -$ 2504.602ADJUST VALVE BOX 63EACH1150.00$ 150.00$ 2504.6028" GATE VALVE AND BOX 64EACH1,600.00$ -$ 2504.60210" GATE VALVE AND BOX 65EACH2,000.00$ -$ 2504.6021" CORPORATION STOP 66EACH180.00$ -$ 2 of 3City of Prior Lake, MN EAU CLAIRE CIRCLE RECLAIM 11/2/2014 2504.6021" CURB STOP & BOX 67EACH275.00$ -$ 2504.6031" TYPE K COPPER PIPE 68LF35.00$ -$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF35.00$ -$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF37.00$ -$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF45.00$ -$ 2504.608DUCTILE IRON FITTINGS 72LBS5.00$ -$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH175.00$ -$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE CIRCLE RECLAIM) TOTAL150.00$ 10% CONTINGENCY$ 15.00 SCHEDULE "C" - WATERMAIN (EAU CLAIRE CIRCLE RECLAIM)PROJECT TOTAL165.00$ SCHEDULE "D" - STORM SEWER (EAU CLAIRE CIRCLE RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF7.00$ -$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF5.00$ -$ 2501.51518" RC PIPE APRON 76EACH800.00$ -$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF38.00$ -$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH1,200.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH2,200.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM80,000.00$ -$ 2511.501RANDOM RIP RAP CLASS III 82CY45.00$ -$ SCHEDULE "D" - STORM SEWER (EAU CLAIRE CIRCLE RECLAIM) TOTAL-$ 10% CONTINGENCY$ - SCHEDULE "D" - STORM SEWER (EAU CLAIRE CIRCLE RECLAIM)PROJECT TOTAL-$ SCHEDULE "A" - STREETS (EAU CLAIRE CIRCLE RECLAIM)$ 30,079.07 SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE CIRCLE RECLAIM)$ 385.00 SCHEDULE "C" - WATERMAIN (EAU CLAIRE CIRCLE RECLAIM)$ 165.00 SCHEDULE "D" - STORM SEWER (EAU CLAIRE CIRCLE RECLAIM)$ - ESTIMATED PROJECT CONSTRUCTION TOTAL$ 30,629.07 20% CONSTRUCTION OVERHEAD$ 6,125.81 ESTIMATED PROJECT GRAND TOTAL$ 36,754.88 3 of 3City of Prior Lake, MN EAU CLAIRE CIRCLE RECLAIM 11/2/2014 ENGINEER'S ESTIMATE 2015 STREET RECONSTRUCTION PROJECT CITY OF PRIOR LAKE, MINNESOTA BMI PROJECT NO. T18.109027 (1) EXACT QUANTITIES AND LOCATIONS TO BE DETERMINED IN THE FIELD AS DIRECTED BY THE ENGINEER (2) INCLUDES GRANULAR BORROW- SEE DETAILS. (3) PAID ONCE, REGARDLESS OF TYPE OR QUANTITY INSTALLED, MAINTENANCE INLUDED (4) LINEAR FOOT FROM MAIN TO CURB STOP FOR ALL FIELD MODIFIED WATER SERVICES NOT INSTALLED PER PLAN IN A COMMON TRENCH WITH THE SANITARY SEWER SERVICE (5) INCLUDES FITTINGS & MATERIALS REQUIRED. (6) INCLUDES BEDDING AND/OR ENCASEMENT MATERIAL AS REQUIRED. (7) MATCH EXISTING IN RECLAIM AREA, NECESSARY CONCRETE SAWING IS INCIDENTAL TO REMOVAL (8) CASTING, VALVE BOX, AND CURB BOX ADJUSTMENTS INCIDENTAL (9) ALL DISTURED AREAS ARE TO BE EXCAVATED 5" AND FILLED WITH TOPSOIL EXCAVATION INCIDENTIAL. (10) PAYMENT INCLUDES ITS REMOVAL AND DISPOSAL AS REQUIRED (11) SPECIFIC STREET NAME SIGNS CALLED OUT ON PLAN SHEETS (12) INCLUDES REMOVAL (13) APPX EVEN MIX OF EACH TREE VARIETY (14) USED AS DIRECTED BY THE ENGINEER. (15) MATERIAL UTILIZED FOR SUBGRADE EXCAVATED AREAS (CV) COMPACTED VOLUME (EV) EXCAVATED VOLUME (P) PLAN QUANTITY SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2021.501MOBILIZATION 1LUMP SUM0.06150,000.00$ 9,000.00$ 2101.502CLEAR AND GRUB 2EACH350.00$ -$ 2104.501REMOVE CURB & GUTTER 3LF2786.00$ 1,665.00$ 2104.505REMOVE BITUMINOUS DRIVEWAY PAVEMENT 4SF1.00$ -$ 2104.505REMOVE CONCRETE DRIVEWAY PAVEMENT 5SY7.00$ -$ 2104.505REMOVE BITUMINOUS PAVEMENT 6SQ YD1.25$ -$ 2104.509REMOVE SIGN POST 7EACH50.00$ -$ 2104.511SAWING CONCRETE PAVEMENT (FULL DEPTH) 8LF5.00$ -$ 2104.513SAWING BITUMINOUS PAVEMENT (FULL DEPTH) 9LF4.00$ -$ 2104.521SALVAGE & REINSTALL WOOD RAIL FENCE 10LF10.00$ -$ 2104.521SALVAGE & REINSTALL CHAIN LINK FENCE 11LF12.00$ -$ 2104.521SALVAGE & REINSTALL LANDSCAPE EDGING 12LF9.00$ -$ 2104.521SALVAGE & REINSTALL SPRINKLER SYSTEM 13LF16.00$ -$ 2104.523SALVAGE & REINSTALL MAILBOX 14EACH80.00$ -$ 2104.604SALVAGE & REINSTALL LANDSCAPE ROCK 15SY20.00$ -$ 2104.618SALVAGE & REINSTALL CONCRETE PAVERS 16SF6.00$ -$ 2104.618SALVAGE & REINSTALL RETAINING WALL 17SF15.00$ -$ 2105.501COMMON EXCAVATION 18CY10.00$ -$ 2105.507SUBGRADE EXCAVATION 19CY57614.00$ 8,057.78$ 2105.609SELECT GRANULAR BORROW 20CY12.00$ -$ 2105.526SELECT TOPSOIL BORROW 21CY5020.00$ 1,000.00$ 2105.609AGGREGATE BACKFILL 22CY57614.00$ 8,057.78$ 2105.604GEOTEXTILE FABRIC TYPE V 23SY1.50$ -$ 2123.610STREET SWEEPER (WITH PICKUP BROOM) 24HOUR1580.00$ 1,200.00$ 2130.501WATER DUST CONTROL 25MG2050.00$ 1,000.00$ 2211.501AGGREGATE BASE CLASS 5 MOD. (100% CRUSHED) 26TON14.50$ -$ 2215.501FULL DEPTH RECLAMATION 27SY316610.00$ 31,655.56$ 2357.502BITUMINOUS MATERIAL FOR TACK COAT 28GAL1734.00$ 690.67$ 2360.501TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) 29TON26167.00$ 17,497.61$ 2360.502TYPE SP 12.5 NON-WEARING COURSE MIXTURE (3,B) 30TON43564.00$ 27,856.89$ 1 of 3City of Prior Lake, MN EAU CLAIRE TRAIL RECLAIM 11/2/2014 2360.503TYPE SP 9.5 WEAR CRS MIX (3,B) 3" THICK DRIVEWAY PAVEMENT 31SY20.00$ -$ 2531.5076" CONCRETE DRIVEWAY PAVEMENT 32SY38.00$ -$ 2531.501CONCRETE CURB AND GUTTER 33LF12.00$ -$ 2531.501CONCRETE CURB AND GUTTER DESIGN D418 34LF27814.00$ 3,885.00$ 2540.601TEMPORARY MAILBOXES 35LUMP SUM0.063,000.00$ 180.00$ 2540.618INSTALL CONCRETE PAVERS 36SF12.00$ -$ 2563.601TRAFFIC CONTROL 37LUMP SUM0.0615,000.00$ 900.00$ 2564.537INSTALL SIGN TYPE C 38EACH50.00$ -$ 2564.537INSTALL SIGN TYPE SPECIAL (STREET NAME) 39EACH260.00$ -$ 2571.502TREE 2.5" CAL B&B (VARIETY - SEE SPEC) 40EACH350.00$ -$ 2571.505SHRUB 18" HT (VARIETY - SEE SPEC) 41EACH50.00$ -$ 2573.502SILT FENCE, TYPE HEAVY DUTY 42LF3.00$ -$ 2573.530STORM DRAIN INLET PROTECTION 43EACH350.00$ -$ 2573.540FILTER LOG TYPE WOOD FIBER BIOROLL 44LF4.00$ -$ 2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCE 45EACH1,000.00$ -$ 2575.505SODDING TYPE LAWN 46SY2003.00$ 600.00$ SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECLAIM) TOTAL113,246.28$ 10% CONTINGENCY$ 11,324.63 SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECLAIM)PROJECT TOTAL124,570.90$ SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.509REMOVE MANHOLE 47EACH425.00$ -$ 2105.601DEWATERING 48LUMP SUM100,000.00$ -$ 2451.607PIPE BEDDING MATERIAL 49CY40.00$ -$ 2503.602CONNECT TO EXISTING MANHOLES (SAN) 50EACH800.00$ -$ 2503.6028"X4" PVC SDR 26 WYE 51EACH250.00$ -$ 2503.6034" PVC SEWER SDR 26 52LF25.00$ -$ 2503.6038" PVC SEWER SDR 26 53LF35.00$ -$ 2503.603LINING SEWER PIPE 8" 54LF60.00$ -$ 2506.501SANITARY MANHOLE EXTRA DEPTH (>8FT) 55LIN FT120.00$ -$ 2506.50248" DIAMETER SANITARY MANHOLE 56EACH2,400.00$ -$ 2506.622ADJUST FRAME & RING CASTING 57EACH6350.00$ 2,100.00$ 2506.602 CASTING ASSEMBLY SPECIAL - TRACER WIRE LOCATE BOX 58EACH350.00$ -$ SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECLAIM) TOTAL2,100.00$ 10% CONTINGENCY$ 210.00 SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECLAIM)PROJECT TOTAL2,310.00$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE WATERMAIN 59LF8.00$ -$ 2504.601TEMPORARY WATER SERVICE 60LUMP SUM90,000.00$ -$ 2504.602CONNECT TO EXISTING WATER MAIN 61EACH1,000.00$ -$ 2504.602HYDRANT WITH 6" GATE VALVE & BOX 62EACH3,500.00$ -$ 2504.602ADJUST VALVE BOX 63EACH3150.00$ 450.00$ 2504.6028" GATE VALVE AND BOX 64EACH1,600.00$ -$ 2504.60210" GATE VALVE AND BOX 65EACH2,000.00$ -$ 2504.6021" CORPORATION STOP 66EACH180.00$ -$ 2 of 3City of Prior Lake, MN EAU CLAIRE TRAIL RECLAIM 11/2/2014 2504.6021" CURB STOP & BOX 67EACH275.00$ -$ 2504.6031" TYPE K COPPER PIPE 68LF35.00$ -$ 2504.6036" WATERMAIN DUCTILE IRON CL 52 69LF35.00$ -$ 2504.6038" WATERMAIN DUCTILE IRON CL 52 70LF37.00$ -$ 2504.60310" WATERMAIN DUCTILE IRON CL 52 71LF45.00$ -$ 2504.608DUCTILE IRON FITTINGS 72LBS5.00$ -$ 2506.602CURB STOP BOX DRIVEWAY CASTING ASSEMBLY 73EACH175.00$ -$ SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECLAIM) TOTAL450.00$ 10% CONTINGENCY$ 45.00 SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECLAIM)PROJECT TOTAL495.00$ SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECLAIM) ITEM NO.SPEC. REF UNIT PRICE TOTAL PRICE DESCRIPTIONUNITQTY 2104.501REMOVE SEWER PIPE (STORM CULVERT) 74LF7.00$ -$ 2502.5414" PERF TP PIPE DRAIN (WITH GEOTEXTILE FILTER SOCK) 75LF5.00$ -$ 2501.51518" RC PIPE APRON 76EACH800.00$ -$ 2503.54118" RC PIPE SEWER CL V DESIGN 3006 (STORM) 77LF38.00$ -$ 2503.602CONNECT TO EXISTING STORM SEWER 78EACH800.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES (2'X3') (PLATE#301) 79EACH1,200.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES 48-4022 (PLATE#300) 80EACH2,200.00$ -$ 2506.502CONST DRAINAGE STRUCTURE DES SPECIAL 1 (WATER QUALITY) 81LUMP SUM80,000.00$ -$ 2511.501RANDOM RIP RAP CLASS III 82CY45.00$ -$ SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECLAIM) TOTAL-$ 10% CONTINGENCY$ - SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECLAIM)PROJECT TOTAL-$ SCHEDULE "A" - STREETS (EAU CLAIRE TRAIL RECLAIM)$ 124,570.90 SCHEDULE "B" - SANITARY SEWER (EAU CLAIRE TRAIL RECLAIM)$ 2,310.00 SCHEDULE "C" - WATERMAIN (EAU CLAIRE TRAIL RECLAIM)$ 495.00 SCHEDULE "D" - STORM SEWER (EAU CLAIRE TRAIL RECLAIM)$ - ESTIMATED PROJECT CONSTRUCTION TOTAL$ 127,375.90 20% CONSTRUCTION OVERHEAD$ 25,475.18 ESTIMATED PROJECT GRAND TOTAL$ 152,851.08 3 of 3City of Prior Lake, MN EAU CLAIRE TRAIL RECLAIM 11/2/2014 APPENDIX C APPENDIX C – PRELIMINARY ASSESSMENT AREAS MAP CLAIRE TRL NE 4185 EAU J & LINDA C WORRELL FRANK CLAIRE TRL NE 4094 EAU NA & ATTN: FO WELLS FARGO BANK CLAIRE TRL NE 4066 EAU GILBERTSON CHRIS 4055 154 ST NE BURNETTE KIPP J CLAIRE TRL NE 4043 EAU CLAIRE TRL NE 4040 EAU CLIFFORD & BARBARA CLAIRE CIR NE DOUSETTE JEFF WITTSTRUCK 4060 EAU SWANKE SHANE 4025 154 ST NW HWY DEPT SCOTT COUNTY 3895 MARSH ST NW & JENNIFER M SEURER DOLAN D 3892 MARSH ST NW GONZALEZ ANTONIO 3883 MARSH ST NW STEPHANIE L SAFE 3880 MARSH ST NW J & LISA A UPHOFF JEFFREY 3870 MARSH ST NW D & DEBRA K MCGAHEY MICHAEL AVE NW 15790 SKYLINE SIPE TODD H 3852 MARSH ST NW A & PATRICE J ZUTTER BRUCE ST NW 3834 MARSH WEST ROBERT G 3816 MARSH ST NW BRADLEY D DYBDAHL 3796 MARSH ST NW JAMES H SR MICHAEL 3776 MARSH ST NW L & HOLLY ROSE TODD APPENDIX D APPENDIX D … ASSESSMENT POLICY APPENDIX E APPENDIX E … PROJECT QUESTIONNAIRES APPENDIX F APPENDIX F … GEOTECHNICAL SOIL BORING LOGS