CITY COUNCIL AGENDA REPORT
MEETING DATE: NOVEMBER 24, 2014
AGENDA#: 8C
PREPARED BY: SENG THONGVANH, PROJECT ENGINEER
PRESENTED BY: SENG THONGVANH
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION AMENDING THE PROFES-
SIONAL SERVICES CONTRACT WITH WSB &ASSOCIATES FOR MAPLE
LANE, MUSHTOWN ROAD, AND PANAMA AVENUE STREET IMPROVEMENT
PROJECT (PROJECT#14-011)
DISCUSSION: Introduction
The purpose of this agenda item is to consider approval of a resolution amending
the professional services contract with WSB & Associates for property acquisition
services.
History
Each year the City reconstructs street segments that are scheduled for reconstruc-
tion as part of its Capital Improvement Program (CIP) and have exceeded their use-
ful design life. The City uses the Capital Improvement Program and its Pavement
Management Program to plan for infrastructure improvements and the financing for
capital improvements. At its September 9, 2013 meeting the City Council adopted
Resolution 13-126 authorizing staff to prepare a Feasibility Report for the Maple
Lane, Mushtown Road, and Panama Avenue Improvement Project as outlined in
the CIP.
The Maple Lane / Mushtown Road / Panama Avenue neighborhood is considered
in the report and includes improvements to Maple Acres, O'Rourke Addition, Parts
of S 11, T 114, R 22 and Parts of S 2, T 114, R 22. These properties were platted
and developed in the 1950's and 1960's. A map of the project area (Figure 1) is
included in the Feasibility Report. The proposed improvements include street re-
construction, sewer and water construction, storm sewer, storm water quality, con-
crete curb and gutter, and appurtenant work. The Feasibility Report also includes
total estimated costs, preliminary assessment amounts, and a project financing
summary. Also included in the report are design criteria, estimates and information
on watermain, sanitary sewer, storm sewer, and streets. Details on each can be
found in the Feasibility Report.
On November 12, 2013, the City Council accepted the feasibility report and sched-
uled the public hearing.
The public hearing was held on December 9, 2013. A second public hearing was
subsequently held on March 10, 2014 for additional comments. The Council also
ordered project plans and specifications at the meeting.
An open house neighborhood meeting was held on May 20, 2014 to review the
proposed project design with the effected residents. Proposed impacts and design
elements were shared at this meeting for each individual property. Locations of
sanitary sewer and water services were also reviewed with each property owner in
attendance to ensure optimal locations of hookup.
On October 13, 2014, the City Council approved the plans and specifications and
authorized advertisement for bids as well as approving the appraised value and au-
thorizing the officials to make offer for property acquisition. Property acquisition is
necessary for installation of utilities on Panama Avenue. Staff is currently working
on obtaining the necessary permits and bidding of the project will take place shortly.
Current Circumstances
During an individual meeting with a property owner, it was discovered that there was
a potential conflict in regards to property lines shown on Panama Avenue. City staff
requested that WSB review the discrepancy in regards to the property lines and
report back to the City. It was found that property lines as shown in Scott County's
GIS and half section maps were in error. Subsequently, 4 additional parcels are
impacted by the proposed utility installation and thus will require partial property
acquisition. These 4 parcels were not part of the original proposal submitted by
WSB.
ISSUES: Property acquisition on public improvement projects can be a long process. Alt-
hough the process for this project started in a timely manner, discovery of additional
need for property acquisition could add additional time for completion of the required
acquisition. WSB will diligently work to complete the task in a timely manner. Prop-
erty acquisition services are a special service which cannot be completed by City
Staff. The City has evaluated the amendment and believes the costs to be reason-
able.
FINANCIAL The amendment to the contract adds a total of $10,000 to the contract with WSB &
IMPACT: Associates. This addition to the original amount will bring the total to$34,020. Fund-
ing for this additional service is proposed to come from an internal budget amend-
ment. It should be noted that the cost increase was not created by WSB but instead
by an error in the Scott County Records. Considering the number of parcels for
which the county keeps records, the number of errors we have experienced are
modest.
ALTERNATIVES: 1. Approve Resolution 14-XXX amending the professional services contract with
WSB & Associates for the Maple Lane, Mushtown Road, Panama Avenue Im-
provement Project.
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED Motion and second for alternative#1.
MOTION:
2
O� PRI()
ti
U t,y
4646 Dakota Street SE
4'1nrxEs0"�P Prior Lake,MN 55372
RESOLUTION 14-xxx
A RESOLUTION AMENDING THE PROFESSIONAL SERVICES CONTRACT WITH WSB &
ASSOCIATES FOR MAPLE LANE, MUSHTOWN ROAD, PANAMA AVENUE IMPROVEMENT PROJECT
Motion By: Second By:
WHEREAS, On March 10th, 2014 the City of Prior Lake entered into a professional services contract
with WSB &Associates for the Maple Lane, Mushtown Road, Panama Avenue
Improvement Project property acquisition; and,
WHEREAS, It was determine that property acquisition would involve an additional 4 parcels as the
result of an error in Scott County Property Records; and,
WHEREAS, WSB & Associates has provided a letter dated November 18th, 2014 detailing the added
services which will be performed to deliver the Maple Lane, Mushtown Road, Panama
Avenue Improvement Project property acquisition in light of these errors.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The professional services contract with WSB &Associates for Maple Lane, Mushtown Road, Panama
Avenue Improvement project is hereby amended to include additional services as discussed in the
November 18th, 2014 letter from WSB.
3. The amount of the professional services contract with WSB &Associates for the Maple Lane,
Mushtown Road, Panama Avenue Improvement Project is hereby increased by$10,000.00.
4. Funding for these engineering services will be funded by an internal budget amendment. The general
fund budget#501-48378-505 will be amended for these additional services.
PASSED AND ADOPTED THIS 24th DAY OF NOVEMBER 2014.
VOTE Hedberg McGuire Morton Soukup
Morton Soukup
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager
A
WSB
&Associates,Inc. engineering•planning•environmental•construction 477 Temperance Street
St.Paul,MN 55101
Tel: 651-286-8450
Fax:651-286-8488
November 18,2014
Mr.Larry Poppler
City of Prior Lake
4646 Dakota Street
Prior Lake,MN 55372
Re: Amendment# 1-Agreement to Provide Easement Acquisition Services
City of Prior Lake 2014 Improvement Projects
Dear Mr.Poppler:
i
WSB and Associates,Inc.will exceed the amount of our current contract due to the addition of four parcels. It is
anticipated that an additional$10,000.00 shall cover the easement acquisition services on this project.
Additional Fee:
Our easement acquisition services include:
WSB Professional Services Hours Assumes 4 parcels
Project Management ................................................................. 5 $ 640.00
Title Review and Field Title Reports......................................... 12 $ 1,540.00
Documents ............................................................................... 7 $ 880.00
Mortgage Consents ................................................................... 40 $ 5,200.00
Offer Presentations and Negotiations........................................ 8 $ 940.00
FileClosure............................................................................... 6 $ 800.00
Total Estimate for WSB Professional Services 78 $10,000.00
If you are in agreement with the terms of this Amendment,please sign below on the space provided and return one
copy to us for our records.
Please do not hesitate to contact me at 651-286-8455 with any questions or concerns.
Original Contract Amount: $24,040.00
Amendment# 1 $10,000.00
Proposed Contract Amount $34,040.00
Sincerely,
WSB&Associates,Inc.
4,-
Barker
Right of Way Specialist
ACCEPTED BY:
City of Prior Lake
Name
Title
Date