HomeMy WebLinkAbout9A - Delay City Sewer and Water Connections
4646 Dakota Street SE
Prior Lake, MN 55372
CITY COUNCIL AGENDA REPORT
MEETING DATE: November 24, 2014
AGENDA #: 9A
PREPARED BY: Frank Boyles, City Manager
PRESENTED BY: Frank Boyles, City Manager
AGENDA ITEM: CONSIDER APPROVAL OF A REPORT WITH RESPECT TO
REQUESTS BY PROPERTY OWNERS TO DELAY CONNECTION TO
CITY SEWER AND WATER SERVICE AS REQUIRED BY SECTIONS
704 AND 705 OF THE PRIOR LAKE CITY CODE
DISCUSSION: Introduction
The purpose of this agenda item is to request City Council direction with
respect to connection of private properties to the city’s sanitary sewer and
domestic water system in the County Road 12/Shoreline/Sunset Avenue
project area.
History
The City completed the utility installations and mailed notice to property
owners for CSAH 12 on November 8, 2013. The work for Sunset Avenue
was completed and notices were mailed on March 14, 2014.
City Code Section 704 provides the properties must connect to municipal
water no longer than one year from its availability even if the private well
continues to function. The private well can be used for all non domestic
purposes for as long as it continues to function and assuming that no cross
connection is made between the two water sources.
Section 705 of the City Code requires the property to connect to sewer
within one year of its availibility. For properties in the annexation area (as
these were) the existing septic system may continue to be used if the
property owner provides certification from an independent inspector that
the system is compliant with current standards. This extension may be
renewed every 36 months as long as the system remains compliant.
Current Circumstances
Our records (attached) show that there are twenty seven potential hook
ups on Sunset Avenue and 15 on Shoreline Boulevard. Of these, seven
properties on Sunset have not yet hooked up. For Shoreline Boulevard,
six properties have not connected.
The staff has received four written requests (attached) for an extension to
the ordinance connection requirements identified above. Three of the
requests are on Shoreline and one on Sunset. The problem is the current
City Code does not provide for exceptions to the one year water hookup
Phone 952.447.9800 / Fax 952.447.4245 / www.cityofpriorlake.com
requirement whereas a 36 month extension can be granted for sewer hook
up upon an independent inspection and a confirmation that the system is
compliant.
So, the options to achieve compliance are:
1. Advise all parties that they must hookup to water and sewer by say
July 31, 2015 and that they can defer sewer hookup for 36 months
provided they have an independent inspector certify to the City that the
septic system is compliant no later than March 31, 2015. The rationale
for this approach includes a number of factors. The project was
somewhat delayed in getting done. Last year’s winter and this years
summer were not condusive to completing such work. Moreover
because of the weather conditions it has become apparent that
contractors are much less available to do this sort of work and if they
are, the prices they quote can be greater than the residents would
otherwise pay. Even with this extra time some property owners may
have to rely upon the city connection process outlined below in the
issues section of this report.
2. Inspect each of the properties immediately to confirm their status and
cite each property which is not compliant. The rationale for this
approach is the fact that with very few exceptions we have sought and
accomplished utility connection within one year of availability. Once
the council has allowed an extension to one party, regardless of the
validity of the reason, others will make requests for reasons they see
as valid and will expect the city to treat them the same. This process
does not delay the collection of fees which keep the city’s funds
available to pay the costs for which they are intended.
3. Amend the city code to provide for a greater time period from utility
availability to connection. The amendment could, for example make
the two ordinances parallel. Presently sewer connection may be
deferred for 36 months if an independent inspection reveals that the
system is compliant. The same thing could be done with water. As long
as a water test confirms that the well water is pure, the resident can
stay hooked up to the well for some span of time. The impact of such
extensions is twofold. On one hand there is greater staff work to assure
that inspections and certifications are accomplished on a timely basis.
Second, the city’s funds must wait to receive fees. In the long run it is
likely that the fees will have to increase to pay for greater finance
charges associated with the extensions.This approach could also
beget more requests for extension.
Conclusion
The city council should determine which, if any of these options, it is
comfortable with.
ISSUES: The assumption in all of the alternatives above where connection is not
made within the ordinance prescribed time period, that all fees (see
attached Process for New Sewer & Water Hook-Up) would be paid by the
property owner except those which reguire the actual connection to
municipal utilities. The intent is to mitigate against futher delays to
reimburse city funds expended to make the utilities available to the subject
properties.
The financial impact of the city’s sewer, water and street projects on
property owners is significant. The cost to connect most often comes on
the heals of a public improvement project which the resident is paying for
incrementally over a twenty year period. So the property owner has likely
already experienced some financial challenges associated with paying the
special assessment. Within the twenty year time frame we ask them to pay
an additional significant amount to connect to water at least and sewer if
their system is out of compliance. The two combined give virtually all
property owners reason to ask for an extension. And that is the crux of the
problem: they all have good reason to make the request so how long an
extension is allowed and on what basis?
If a property owner cannot connect using their own resources, the city can
accomplish the work for them and specially assess the costs. The city
would need to either issue citations if it were to pursue a criminal route to
compliance or bring an injunction against the property owner. In either
case the objective would be to obtain a court order authorizing the city to
enter onto the property to complete the work.
The most likely scenarios will be that a private contractor will act as the
city’s agent to complete this work. The contractor will be excavating
landscaped property, six or more feet deep and ultimately occupying the
basement level of the property owner’s house to break through the floor,
wall or both to bring in utilities. They would also have to properly abandon
the existing well and septic systems. The final action will be to take the
prerequisite steps to specially assess the costs against the property.
Since the contractor is the city’s agent, it is possible that the city could be
pulled into a a dispute regarding restoration, vandalism, or work quality as
has happened with our driveway improvement projects. The city is in a
precarious position here as we do not have inspectors stationed on the
property full time.
Finally the city council should consider what a double edged sword the
quantity of properties requiring hook up can be. The greater the number,
if granted, the greater precedent created. On the other hand the greater
number the city chooses to complete, the more complex, burdensome and
liability creating they can be.
FINANCIAL From a strictly financial perspective, leaving the ordinance as is and
IMPACT:
mandating hook up is the most cost effective from the city’s perspective.
As mentioned above however, the city would incur additional litigation,
liability and other such costs by mandating connection.
ALTERNATIVES: 1. Direct the staff to contact the 12 properties which have not yet
hooked up or are in process to advise them they have until July 31,
2015 to do so subject to the conditions above.
2. Direct the staff to contact the 12 properties to advise that
connection is expected immediately and that court proceedings will
be initiated for anyone who has not pulled a permit within 30 days
of the one year ordinance provision.
3. Direct that staff prepare modifications to the city code as desired
by the city council.
4. Take no action and direct that the city staff research other
alternatives to address this issue.
RECOMMENDED As determined by the city council.
MOTION:
Connection Summary
Sunset Avenue and CSAH 12
Sunset Avenue (Project Complete March 14, 2014)
There are twenty-seven (27) potential hook-ups on Sunset Avenue. The ones that ARE NOT hooked up
include:
17011 Sunset Avenue (Mark Sailer) Submitted compliance report on septic system
17081 Sunset Avenue (Stephen Wagner) No progress, In August, Homeowner informed City they
are selling house
17141 Sunset Avenue (James Rockwell) No progress, Homeowner states they have contractor
lined up this fall
17221 Sunset Avenue (Gene Muelken) In progress, Homeowner paid fees but has not hooked
up
17261 Sunset Avenue (Jason Berry) No progress, Homeowner deciding to re-build
17311 Sunset Avenue (Kevin Gardner) No progress,submitted extension request
1711 Shoreline Boulevard (David Doehlert) No progress, Homeowner has made no contact
Shoreline Boulevard (Project Complete November 8, 2013)
There are fifteen (15) potential hook-ups on Sunset Avenue. The ones that ARE NOT hooked up include:
1735 Shoreline Blvd (Dana Breault) - No progress,submitted extension request
1751 Shoreline Blvd (Theodore Smits) No progress, submitted extension request,Compliance
inspection revealed a non-compliant tank and
drainfields, possible demolition of house
1771 Shoreline Blvd (Stephanie Risberg) No progress, Homeowner received bids for hookup
1781 Shoreline Blvd (Lesli Beauliew) In progress, Homeowner paid fees, but has not hooked
up
1799 Shoreline Blvd (James Scharf) No progress,submitted extension request
1875 Shoreline Blvd (Linda Bigot) No progress, possible demolition
t-
/OL) TO /I�k. C56�)
Foe A Lr f�-t C Mokk -7-1 m6.
-Fil-/r PgOP,(-kTy Trtqx
7"yl I,%rw leO4 p 14s56s5M(-Al-f fi r
pxicc W67611
T m 4fk (l,1) X O u 7-a Pt(4SC 6-(-V6
-FO COM 6 UP
/OUR-5
( 73 5 sNQ���, �� f3t v
November 1, 2014
Frank Boyles
City Manager—City of Prior Lake
Re: Project#12-002, CR12; Shoreline Blvd. Utility Hook Up
Request extension to hook up date:
• The property is currently for sale.
• New ownership may result in a new home structure, requiring a
different hook up area. Therefore involving less distance to the street
and much less cost.
• Current estimate of$ 9250.00 and permit of$ 5800.00 = $15,050.00
for the present location of the hook up. Far beyond my expectation
after speaking with neighbors about the cost of their projects. I do
not have that amount of ready cash to pay for such a project.
Therefore, requesting the install to take place after the sale, and to
the new structure. That would allow only one excavation to take
place to complete the project as opposed to one now and a second
as soon as the new structure is in place.
• Currently a winter resident in Arizona and the property is not in use
as for water and sewage.
Thank you in advance for your serious consideration involving this matter.
Sincerely
Theodore Smits Jr.
Frank Boyles
From: Jennifer Dull
Sent: Monday, November 03, 2014 4:19 PM
To: Frank Boyles
Subject: RE: 17311 Sunset Ave
Frank,
Please see the below email. When Mr. Gardner was attempting to email you, it wouldn't go through.
Jenn
From: Kevin Gardner[mailto:kgardner@mnpools.com]
Sent: Monday, November 03, 2014 3:13 PM
To:Jennifer Dull
Subject: 17311 Sunset Ave
Please forward this to Mr. Boyles,
Dear Mr. Boyles,
I live at 17311 Sunset Avenue I am requesting an extension for the utility connections at our home.We are currently
helping a family member get into single floor living for health reasons.
Our current budget is extremely tight.Will you allow us until late summer 2015 to get the utility's connected?Our
current septic is in excellent shape. It wall installed NEW in 1996.
Thank you for any and all consideration,
Kevin Gardner
17311 Sunset Ave
Shakopee, MN 55379
763.300.9003
1
CC) j- � r �Os�� � K�,� bc�n
4-c) CQA ,,V
L,--)CA ck
S�P�e e� b�e � c;���,\ ✓�� S� r�, �
CcA C r-)0A-
PROCESS FOR NEW SEWER & WATER HOOK-UP (Building Department) 10/21/13
sz
1. Have Homeowner sign the Building Permit Application
2. Before any payment, Homeowner needs to know if they will have a 5/8"
Water Meter or a 1" Water Meter (the prices are different---5/8" = $480.00
+ $110.00 for water reducer= total of $590.00 or 1" Meter = $590.00 +
$150.00 = $740.00). Building Permit#, Sewer & Water Permit# & Plumbing
Permit # will all have same PERMIT NUMBER. Assign the # in next sequence
in Building Permit Roster.
3. For 2013* Fees are:
a. SAC Charge $2435.00
b. Sewer & Water Connect Fee $1500.00
c. Water Tower Fee $1000.00
L Total $4935.00
d. Sewer/Water Permit Fee $ 56.50
e. Plumbing Permit Fee 5 54.50
L Total $5046.00 $5046.00
f. Water Meter & Reducer
5/8" 590.00
Total $ 5636.00
OR
V $ 740.00
Total $5786.00
4. Complete a receipt for monies paid by Homeowner & give a copy to
Homeowner.
5. Make sure Homeowner understands that the Sewer & Water Contractor &
the Plumbing Contractor MUST sign the respective form even though the
Homeowner is paying the fee. PERMIT# CANNOT BE ASSIGNED UNTIL
HOMEOWNER AND BOTH CONTRACTORS HAVE SIGNED THE RESPECTIVE
FORMS.
*2014 Fees will increase by $50.00 for the SAC Charge. Other potential fee
increases are not yet known.