HomeMy WebLinkAbout5B - Maple, Mushtown, Panama Additional Acquisitions ob�-,FRIO
U
u
4646 Dakota Street SE
Prior Lake,MN 55372
CITY COUNCIL AGENDA REPORT
MEETING DATE: DECEMBER 8, 2014
AGENDA#: 5B
PREPARED BY: SENG THONGVANH, PROJECT ENGINEER
PRESENTER: SENG THONGVANH
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION APPROVING APPRAISED
VALUE AND AUTHORIZING THE OFFICIALS TO MAKE OFFERS TO
PURCHASE INTERESTS IN REAL PROPERTY AT THE APPRAISED
VALUES FOR THE MAPLE LANE, MUSHTOWN ROAD, AND PANAMA
AVENUE IMPROVEMENT PROJECT, CITY PROJECT#TRN14-000001
DISCUSSION: Introduction
The purpose of this agenda item is to seek approval from the City Council
for the appraised value and authorizing the officials to make offer to
purchase interests in real property at the appraised values.
History
Each year the City reconstructs street segments that are scheduled for
reconstruction as part of its Capital Improvement Program (CIP) and have
exceeded their useful design life. The City uses the Capital Improvement
Program and its Pavement Management Program to plan for infrastructure
improvements and the financing for capital improvements. At its September
9, 2013 meeting the City Council adopted Resolution 13-126 authorizing
staff to prepare a Feasibility Report for the Maple Lane, Mushtown Road,
and Panama Avenue Improvement Project as outlined in the CIP.
The Maple Lane / Mushtown Road / Panama Avenue neighborhood is
considered in the report and includes improvements to Maple Acres,
O'Rourke Addition, Parts of S 11, T 114, R 22 and Parts of S 2, T 114, R
22. These properties were platted and developed in the 1950's and 1960's.
A map of the project area (Figure 1) is included in the Feasibility Report.
The proposed improvements include street reconstruction, sewer and water
construction, storm sewer, storm water quality, concrete curb and gutter,
and appurtenant work. The Feasibility Report also includes total estimated
costs, preliminary assessment amounts, and a project financing summary.
Also included in the report are design criteria, estimates and information on
watermain, sanitary sewer, storm sewer, and streets. Details on each can
be found in the Feasibility Report that was presented to the City Council on
November 12, 2014. The City Council approved the Feasibility Report per
Resolution 13-168.
On November 12, 2013, the City Council accepted the feasibility report and
scheduled the public hearing.
The public hearing was held on December 9, 2013. A second public
hearing was subsequently held on March 10, 2014 for additional
comments. The Council also ordered project plans and specifications at the
meeting.
An open house neighborhood meeting was held on May 20, 2014 to review
the proposed project design with the effected residents. Proposed impacts
and design elements were shared at this meeting for each individual
property. Locations of sanitary sewer and water services were also
reviewed with each property owner in attendance to ensure optimal
locations of hookup.
On October 13, 2014, the City Council approved the plans and
specifications and authorized advertisement for bids as well as approving
the appraised value and authorizing the officials to make offer for property
acquisition for 9 parcels. Property acquisition is necessary for installation
of utilities on Panama Avenue. Staff is currently working on obtaining the
necessary permits and bidding of the project will take place shortly.
Current Circumstances
During an individual meeting with a property owner, it was discovered that
there was a potential conflict in regards to property lines shown on Panama
Avenue. City staff requested that WSB review the discrepancy in regards
to the property lines and report back to the City. It was found that property
lines as shown in Scott County's GIS and half section maps were in error.
Subsequently, 4 additional parcels are impacted by the proposed utility
installation and thus will require property acquisition. There were originally
9 parcels that the City was proposing to acquire easements from. With 4
additional parcels, there will be a total of 13 parcels that will require partial
easement acquisition.
ISSUES: Property acquisition on public improvement projects can be a long process.
Although the process for this project started in a timely manner, discovery
of additional need for property acquisition could add additional time for
completion of the required acquisition. WSB will diligently work to complete
the task in a timely manner. Property acquisition services are a special
service which cannot be completed by City Staff.
FINANCIAL The additional property acquisition costs will add additional costs to the
IMPACT: overall project amount. WSB & Associates has provided the property
appraisals for the 4 additional parcels which will be presented by the City
Engineer. As to the WSB fees associated with this work, the City Council
approved the necessary adjustment at their last meeting.
ALTERNATIVES: The alternatives are as follows:
1. Approve Resolution 14-XX as a part of the consent agenda approving
appraised values and authorizing the officials to make offers to
purchase interests in real property at the appraised values
2. Deny this item for a specific reason and provide staff with direction.
3. Defer this item until a future date.
RECOMMENDED A motion and a second for alternative #1.
MOTION:
2
O� PRIp1P
ti
U
4646 Dakota Street SE
�11 s0-P Prior Lake,MN 55372
RESOLUTION 14-xxx
RESOLUTION APPROVING THE APPRAISED VALUE AND AUTHORIZING THE OFFICIALS TO MAKE
OFFERS TO PURCHASE INTERESTS IN REAL PROPERTY AT THE APPRAISED VALUES FOR THE
MAPLE LANE, MUSHTOWN ROAD,AND PANAMA AVENUE IMPROVEMENT PROJECT,
CITY PROJECT#TRN14.000001
Motion By: Second By:
WHEREAS, The City of Prior Lake, a Minnesota municipal corporation acting by and through the City
Council and is authorized by law to acquire real property("Property")which is needed for
public use or purpose; and
WHEREAS, The City Engineer has ordered appraisals from WSB and Associates and has received
full and final appraisals for the Maple Lane, Mushtown Road, and Panama Avenue
Improvement Project, City Project#TRN14-000001 (the"Project"); and
WHEREAS, It is necessary that the City obtain title and possession to the necessary easements by
negotiation or condemnation before construction contracts may begin; and
WHEREAS, The City wishes to make offers to property owners for the Property based on the appraisal
values as presented by the City Engineer; and
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The appraised values are hereby approved.
3. The City Manager, Public Works Director, City Engineer and City Attorney are hereby authorized to
acquire the Property required for the Project in fee or by easement, through negotiation or
condemnation and to make offers to purchase interests in real property at the current appraised
values as presented by the City Engineer for the Maple Lane, Mushtown Road, and Panama
Avenue Improvement Project, City Project#TRN14-000001.
PASSED AND ADOPTED THIS 8th DAY OF DECEMBER 2014.
VOTE Hedberg Keeney McGuire Morton Soukup
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager