HomeMy WebLinkAbout7B - Credit River Road Public Hearing O� PRIp�
N
U 4646 Dakota Street SE
Prior Lake, MN 55372
`�INx�so�P
CITY COUNCIL AGENDA REPORT
MEETING DATE: DECEMBER 22, 2014
AGENDA#: 713
PREPARED BY: SENG THONGVANH, PROJECT ENGINEER
PRESENTED BY: SENG THONGVANH
AGENDA ITEM: PUBLIC HEARING TO CONSIDER APPROVAL OF A RESOLUTION ORDER-
ING THE IMPROVEMENT AND PREPARATION OF PLANS AND SPECIFICA-
TIONS FOR THE CREDIT RIVER ROAD IMPROVEMENT PROJECT (PROJECT
#15-000006)
DISCUSSION: Introduction
The purpose of this agenda item is to hold the Public Hearing to consider approval
of a resolution ordering the Credit River Road Improvement Project and the prepa-
ration of plans and specifications. A super majority (4/5) is needed to approve the
resolution.
History
Each year the City reconstructs street segments that are scheduled for reconstruc-
tion as part of its Capital Improvement Program (CIP) and have exceeded their
useful design life. The City uses the Capital Improvement Program and its Pave-
ment Management Program to plan for infrastructure improvements and the fi-
nancing for capital improvements. At its August 25, 2014 meeting the City Council
adopted Resolution 14-124 authorizing staff to prepare a Feasibility Report for the
Credit River Road Improvement Project as outlined in the CIP.
The Credit River Road neighborhood is considered in the report and includes im-
provements to Borgerding Addition, Brooksville Hills 1St Addition, Brooksville Hills
8th Addition, Costello's Addition, S 02, T 114, R 22 Block 001, Lot 002 & 003 and
portions of Sections 1 & 2, Township 114, Range 22. These properties were plat-
ted and developed from as early as 1920's to as late as the 1990's. A map of the
project area (Figure 1) is included in the Feasibility Report. The proposed im-
provements include street reconstruction, storm sewer, storm water quality, sani-
tary sewer, watermain, concrete curb and gutter, and appurtenant work.
On November 24, 2014, the City Council accepted the feasibility report and sched-
uled the public hearing.
If this project proceeds, the City intends on using the M.S. Chapter 429 process as
this process applies to all projects that will be financed in whole or in part through
special assessments or bond proceeds.
Current Circumstances
The properties deemed to specially benefit from the improvements, in most cases
the properties abutting the streets located in the project area, are subject to as-
sessment. Each of the affected property owners have been notified in accordance
with the statute regarding tonight's Public Hearing.
A Public Information Meeting was held on December 17, 2014 to provide the prop-
erty owners an opportunity to discuss the project in an informal setting prior to the
Public Hearing. Staff presented the proposed improvements, project costs, esti-
mated assessments and answered general questions regarding the project. Com-
ments will be presented at the Public Hearing.
Conclusion
City Staff is prepared to discuss each of the concerns presented at the Public
Hearing. If the Council deems the issues that have been brought up need to be
addressed in the project plans and specifications, direction could be given to staff.
The purpose of this Public Hearing is to determine whether the project should
move forward to the next step, which is preparation of plans and specifications
which will provide greater information about expected project cost and, therefore,
the assessments associated with the improvements. Once the plans and specifi-
cations are completed, they will be submitted to the City Council for approval and
authorization to advertise for bids. The Council could decide not to continue with
the project upon receipt of bids. A separate Assessment Hearing will be con-
ducted following review of the proposed assessments by the City Council's As-
sessment Review Committee.
In summary, the project is feasible from an engineering and economic standpoint.
If the preparation of the plans and specifications is approved, the work will be com-
pleted by City staff.
ISSUES: The Assessment Review Committee met on October 28th and November 14th, 2014
at which time the following issues were discussed and recommendations made:
Assessment Map
The Assessment Review Committee recommends assessing the properties as
shown on the assessment map.
Street and Storm Sewer Reconstruction
Pursuant to the Assessment Policy, the street and storm sewer reconstruction
should be assessed at up to 40% of the total project cost against the benefiting
properties. The remaining amounts should be recovered through the general ad
valorem property tax.
Assessment Method
The Assessment Review Committee recommends the unit method of assessment
for the project due to the fact that the lots in the project area are of similar size
and/or value. The estimated assessment rate per the Feasibility Report is pro-
posed at $14,785/unit. Note that the amount of the actual assessment will be cal-
culated based on the bids received and final construction costs.
2
Homes on One Side of Roadway
Due to the lack of homes on one side of the roadway, the number of homes to levy
the assessment are less than other local street projects. The Assessment Review
Committee recognized this distinction and recommended that benefit appraisals
be completed for this project. The benefit appraisals may suggest a lower assess-
ment amount. The benefit appraisals are underway and are expected to be com-
plete in January or early February.
Forcemain and Lift Station Replacement
The capacity issues related to the Credit River Lift Station were discussed at the
November 14'ARC meeting as well as the November 24th Council meeting. A
memo dated November 13th drafted by Larry Poppler was reviewed. Due to the
circumstances, the replacement of forcemain under Credit River Road from Ev-
anston to the Credit River Lift Station is necessary to gain the needed capacity.
Due to this replacement and disturbance to Credit River Road, the Assessment
Review Committee recommended proceeding with the project.
Trunk Highway 13/County Road 21 Future Plans
The ARC reviewed 3 options for the TH 13/CR 21 future plans. The options in-
cluded:
1. Existing Alignment - Reconstructing Credit River Road with the City's
typical section within the existing road alignment at Evanston Avenue.
Option 1 would likely mean that this stretch of Credit River Road (ap-
proximately 300 feet) would be reconstructed again when the intersec-
tion project takes place.
2. Shift Alignment- Reconstructing Credit River Road with the City's typi-
cal section and shifting road alignment to account for expansion of
County Road 21. The shifting of the road alignment (option 2) would
require property acquisition and would cost approximately $9,000.
This option would not necessarily mean this area of Credit River Road
would not be impacted again with the TH 13/CR 21 intersection. It
would give the City an opportunity during the design of the intersection
project to try to minimize impacts or avoid reconstructing this portion of
Credit River Road again.
3. Temporary Road Section - Building a temporary street section for the
area that may be impacted by future construction of the TH 13/CR 21
intersection. Option 3 would provide a cost savings of approximately
$33,000. The ARC recommended that if this option were chosen the
assessed parcels would be the same as the other two options as they
would not be assessed with the TH 13 and CR 21 project.
The ARC recommended that the final decision on which road option to use at this
location be deferred until additional design information is available that would bet-
ter illustrate impacts of each option.
3
FINANCIAL The Credit River Road Improvement Project is proposed to be financed by Special
IMPACT: Assessments, tax levy, Sewer Fund, Water Fund, and Trunk Sewer Fund. Funding
sources and amounts are as shown below:
ITEMS COST
Street/Storm Sewer* $1,046,434.50
Watermain $ 253,018.00
Sanitary Sewer $1,092,475.00
Street Lights $ 10,000.00
City's Proiect Support Costs** $ 258,349.04
TOTAL PROJECT COST $2,660,276.54
*Includes Water Quality Costs
**City's Project Support Costs includes the following:
Engineering
Administration
Financing
Assessments $399,185.10
Sewer Fund $300,387.18
Water Fund $309,744.95
Water Quality Fund $16,420.67
Trunk Sewer Fund $939,105.96
Tax Lev $695,432.67
Project Total Cost $2,660,276.54
ALTERNATIVES: 1. Conduct the public hearing and in the absence of compelling information to the
contrary, approve Resolution 14-XX ordering the Credit River Road Improve-
ment project and preparation of plans and specifications.
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED Motion and second for alternative#1.
MOTION:
4
O� PRip�
ti
U
4646 Dakota Street SE
�tINNESO�p' Prior Lake,MN 55372
RESOLUTION 14-xxx
ORDERING IMPROVEMENTS AND PREPARATION OF PLANS AND SPECIFICATIONS FOR CREDIT
RIVER ROAD IMPROVEMENT PROJECT (PROJECT#TRN15.000006); FINANCING THE CREDIT
RIVER ROAD IMPROVEMENT PROJECT,TO BE UNDERTAKEN BY THE CITY AND ESTABLISHING
COMPLIANCE WITH REIMBURSEMENT BOND REGULATIONS UNDER THE INTERNAL REVENUE
CODE
Motion By: Second By:
WHEREAS, the Prior Lake City Council on its own initiative has determined that it desires to complete
the Public Improvement Project to Credit River Road; and
WHREAS, on November 24, 2014; the City Council adopted Resolution 14-183 accepting the
Feasibility Report and calling for a Public Hearing to be held on the Credit River Road
Improvement Project which includes sanitary sewer, watermain, storm sewer, aggregate
base, concrete curb and gutter, bituminous surfacing, and appurtenant work; and
WHEREAS, ten days mailed notice and two weeks published notice of the hearing was given, and the
hearing was held on the 22nd day of December, 2014, at which time all persons desiring to
be heard were given an opportunity to be heard thereon; and
WHERES, since the project was initiated by the City Council it must be approved by 4/5ths vote in
accordance with Minnesota Statutes 429.031 Subdivision 1(f); and
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. Such improvement is necessary, cost-effective, and feasible as detailed in the feasibility report.
3. The City Engineer is hereby authorized to prepare plans and specifications for the improvements
delineated in City Council Resolution 14-183 adopted on November 24, 2014 and by the required
statutory 4/5ths vote does hereby order the project.
4. The City Engineer is hereby designated as the Engineer for these improvements and is authorized to
record engineering expenses in the Construction Fund (#501-43500.00-55020-TRN15-000006).
5. The Engineer shall prepare plans and specifications for the making of such improvements for Credit
River Road.
6. The City Council authorizes the following preliminary funding sources and corresponding transfers to
the Construction Fund for the project:
Assessments $399,185.10
Sewer Fund $300,387.18
Water Fund $309,744.95
Water Quality Fund $16,420.67
Trunk Sewer Fund $939,105.96
Tax Lev $695,432.67
Project Total Cost $2,660,276.54
7. The City has determined to make a declaration of official intent ("Declaration") to reimburse certain
estimated costs for this project from proceeds of bonds in accordance with the Internal Revenue
Service Reimbursement Regulations (Treasury Reg. 1.150-2).
8. The City may declare other separate statements of reimbursement intent in connection with specific
public improvements projects as they are initiated under Minnesota Statutes Chapters 429 and 444, or
for other capital projects, with the understanding that such additional declarations of reimbursement
intent will supplement this resolution. All reimbursed expenditures will be capital expenditures, costs of
issuance of the bonds, or other expenditures eligible for reimbursement under Section 1.150-2(d)(3)of
the Reimbursement Regulations.
9. This Declaration has been made no later than 60 days after payment of any original expenditure to be
subject to a reimbursement allocation with respect to the proceeds of bonds, except for the following
expenditures:
a. costs of issuance of bonds;
b. costs in an amount not in excess of $100,000 or five percent of the proceeds of an issue;
or
c. "preliminary expenditures" up to an amount not in excess of 20 percent of the aggregate
issue price of the issue or issues that are reasonably expected by the City to finance the
project for which the preliminary expenditures were incurred. The term "preliminary
expenditures" includes architectural, engineering, surveying, bond issuance, and similar
costs that are incurred prior to commencement of acquisition, construction or rehabilitation
of a project other than land acquisition, site preparation, and similar costs incident to the
commencement of construction.
10. This Declaration is an expression of the reasonable expectations of the City based on the facts and
circumstances known to the City as the date hereof. The anticipated original expenditures for the
Projects and the principal amount of the bonds are consistent with the City's budgetary and financial
circumstances. No sources other than proceeds of bonds to be issued by the City are, or are
reasonably expected to be reserved, allocated on a long term basis, or otherwise set aside pursuant to
the City's budget or financial policies to pay such Project expenditures.
11. This Declaration is intended to constitute a Declaration of the Official Intent for the purposes of the
Reimbursement Regulations.
2
PASSED AND ADOPTED THIS 22ND DAY OF DECEMBER 2014.
VOTE Hedberg Keeney McGuire Morton Soukup
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager
3