CITY COUNCIL AGENDA REPORT
MEETING DATE: JANUARY 12, 2015
AGENDA#: 6B
PREPARED BY: SENG THONGVANH, PROJECT ENGINEER
PRESENTER: LARRY POPPLER
AGENDA ITEM: CONSIDER APPROVAL OF THREE RESOLUTIONS:
1) ACCEPTING THE IMPROVEMENTS FOR HICKORY SHORES 3RD
ADDITION
2) ACCEPTING THE IMPROVMEENTS FOR HICKORY SHORES 4T"
ADDITION
3) ACCEPTING THE IMPROVEMENTS FOR THE MAPLE GLEN 4T"
ADDITION
DISCUSSION: Introduction
The purpose of this agenda item is to consider individual resolutions
accepting the developer installed improvements for the following
developments:
Hickory Shores 31 Addition
Hickory Shores 4th Addition
Maple Glen 4th Addition
This action is housekeeping in nature and is called for as part of the
development agreement between each developer and the city. In essence,
this is the process through which privately installed improvements come
into public ownership pursuant to Prior Lake City Code.
History
Hickory Shores 3rd Addition
The Hickory Shores 3rd Addition is part of the overall Hickory Shores
Development and is located south of Trunk Highway 13 and west of Crystal
Lake. On May 7, 2012, the City Council adopted Resolution 12-071
entering into a Development Contract with D.R. Horton, Inc. for the Hickory
Shores 3rd Addition Development. Since that City Council action, the
developer has been completing the construction of the improvements as
outlined in the Development Contract. The Development Contract and
approved construction drawings outline the necessary developer installed
improvements as well as other items needed for this development to be
accepted by the City.
Hickory Shores 4t'Addition
The Hickory Shores 4th Addition is part of the overall Hickory Shores
Development and is a continuation from the Hickory Shores 3rd Addition.
On June 18, 2012, the City Council adopted resolution 12-097 entering into
Phone 952.447.9800 / Fax 952.447.4245/www.cityofpriorlake.com
a Development Contract with D.R. Horton, Inc. for the Hickory Shores 4th
Addition Development. Since that City Council action, the developer has
been completing the construction of the improvements as outlined in the
Development Contract. The Development Contract and approved
construction drawings outline the necessary developer installed
improvements as well as other items needed for this development to be
accepted by the City.
Maple Glen 4rh Addition
The Maple Glen 4th Addition is part of the overall Maple Glen Development
and is located south of Trunk Highway 13 and north of 180th Street. On
October 8, 2012 the City Council adopted resolution 12-165 entering into a
Development Contract with D.R. Horton, Inc. for the Maple Glen 4th
Addition Development. Since that City Council action, the developer has
been completing the construction of the improvements as outlined in the
Development Contract. The Development Contract and approved
construction drawings outline the necessary developer installed
improvements as well as other items needed for this development to be
accepted by the City.
The Development Contract for each of these developments details the
mechanisms for City acceptance of the developer installed improvements.
In 2005, the City amended the Standard Development Contract to include
City Council authorization to accept the improvements in addition to the
final written acceptance by the City Engineer.
Current Circumstances
The developers for each of the projects described above have now
completed the improvements as outlined in the Development Contracts.
The improvements have been inspected by the City and have been found
to be in compliance with City standards and the approved drawings. In
some cases minor field changes were necessary during construction.
These improvements including any field adjustments were documented in
the completed as-built drawings. These as-built drawings were completed
by the developer and reviewed by the City. The property iron certification
letter has been received by the City.
Conclusion
The City Engineer has reviewed the improvements and recommends that
the city council accept the improvements for these developments.
ISSUES: Once the improvements are accepted, the public improvements will then be
turned over to the City and the security for the development returned to the
developer. It will then be the responsibility of the City to perform
maintenance over the public improvements and take over operational costs
for the street lighting on the project.
FINANCIAL Hickory Shores 3rd Addition
IMPACT: An escrow in the amount of $12,295 for consulting and construction
inspection was received by the City for this development. These dollars
have been reserved in the Developers Agreement Special Revenue fund
for payment. Any remaining escrow funds intended for construction
inspection will be returned to the developer at the conclusion of a
successful warranty period (1 year).
2
Hickory Shores 4'Addition
An escrow in the amount of $38,369 for consulting and construction
inspection was received by the City for this development. An additional
$4,000 was received for consulting and construction inspection to cover
additional inspection time spent on the Development. These dollars have
been reserved in the Developers Agreement Special Revenue fund for
payment. Any remaining escrow funds intended for construction inspection
will be returned to the developer at the conclusion of a successful warranty
period (1 year).
Oversizing for watermain construction was paid by the City to the
Developer through the Development Contract. The costs for these
improvements have been reconciled with the Developer through the
Development Contract and no additional compensation is necessary.
Maple Glen 4'Addition
An escrow in the amount of $19,589 for consulting and construction
inspection was received by the City for this development. An additional
$1,500 was received for consulting and construction inspection to cover
additional inspection time spent on the Development. These dollars have
been reserved in the Developers Agreement Special Revenue fund for
payment. Any remaining escrow funds intended for construction inspection
will be returned to the developer at the conclusion of a successful warranty
period (1 year).
Oversizing for street construction was paid by the City to the Developer
through the Development Contract. The costs for these improvements have
been reconciled with the Developer through the Development Contract and
no additional compensation is necessary.
ALTERNATIVES: 1. Approve a resolution as part of the consent agenda accepting the
improvements for the Hickory Shores 3rd Addition Development.
2. Approve a resolution as part of the consent agenda accepting the
improvements for the Hickory Shores 4th Addition Development.
3. Approve a resolution as part of the consent agenda accepting the
improvements for the Maple Glen 4th Addition Development.
4. Deny this item for a specific reason and provide staff with direction.
5. Table this item until some date in the future.
RECOMMENDED Motion and second to approve alternatives#1, #2, and#3.
MOTION:
3
i
O� PRIpr�r
U txt
4646 Dakota Street SE
:�,J PM_Sott Prior Lake, MN 55372
i
I
RESOLUTION 15-xxx
A RESOLUTION ACCEPTING THE DEVELOPER INSTALLED IMPROVEMENTS FOR HICKORY
SHORES 3RD ADDITION CITY PROJECT#DEV12-000002
Motion By: Second By:
WHEREAS, On May 7, 2012, the City Council adopted Resolution 12-071 which authorized the City to
enter into a Development Contract with D.R. Horton, Inc. for the plat known as Hickory
Shores 3rd Addition; and
WHEREAS, The Development Contract outlined the improvements the developer was responsible for
installing; and
WHEREAS, These improvements and all other Development Contract responsibilities are now complete
to the satisfaction of the City; and,
WHEREAS, The City has received the as-built drawings and property iron certification letter; and
WHEREAS, The City Engineer has reviewed the improvements and has written the acceptance letter for
this development.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council hereby accepts the improvements for the Hickory Shores 31d Addition development.
3. Any remaining escrow dollars for construction inspection will be returned to the developer at the
conclusion of the warranty period.
PASSED AND ADOPTED THIS 12TH DAY OF JANUARY 2015.
VOTE Hedberg Keeney McGuire Morton Thompson
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager
O� PR12
U t�
4646 Dakota Street SE
:�IjzsOl-P Prior Lake, MN 55372
i
RESOLUTION 15-xxx
A RESOLUTION ACCEPTING THE DEVELOPER INSTALLED IMPROVEMENTS FOR HICKORY
SHORES 4TH ADDITION CITY PROJECT#DEV12-000004
Motion By: Second By:
WHEREAS, On June 18, 2012, the City Council adopted Resolution 12-097 which authorized the City to
enter into a Development Contract with D.R. Horton, Inc. for the plat known as Hickory
Shores 4th Addition; and
WHEREAS, The Development Contract outlined the improvements the developer was responsible for
installing; and
WHEREAS, These improvements and all other Development Contract responsibilities are now complete
to the satisfaction of the City; and,
WHEREAS, The City has received the as-built drawings and property iron certification letter; and
WHEREAS, The City Engineer has reviewed the improvements and has written the acceptance letter for
this development.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council hereby accepts the improvements for the Hickory Shores 4th Addition development.
3. Any remaining escrow dollars for construction inspection will be returned to the developer at the
conclusion of the warranty period.
4. The oversizing amount for watermain construction was paid to the developer in accordance with the
Development Contract. No further compensation to the developer is needed for this project.
PASSED AND ADOPTED THIS 12TH DAY OF JANUARY 2015.
VOTE Hedberg Keeney McGuire Morton Thompson
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager
O� FR.I()
U tri
4646 Dakota Street SE
NEW"V, Prior Lake,MN 55372
RESOLUTION 15-xxx
A RESOLUTION ACCEPTING THE DEVELOPER INSTALLED IMPROVEMENTS MAPLE GLEN 4TH
ADDITION CITY PROJECT#DEV12-000001
Motion By: Second By:
WHEREAS, On October 8, 2012, the City Council adopted Resolution 12-165 which authorized the City
to enter into a Development Contract with D.R. Horton, Inc. for the plat known as Maple
Glen 4th Addition; and
WHEREAS, The Development Contract outlined the improvements the developer was responsible for
installing; and
WHEREAS, These improvements and all other Development Contract responsibilities are now complete
to the satisfaction of the City; and,
WHEREAS, The City has received the as-built drawings and property iron certification letter; and
WHEREAS, The City Engineer has reviewed the improvements and has written the acceptance letter for
this development.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council hereby accepts the improvements for the Maple Glen 4th Addition development.
3. Any remaining escrow dollars for construction inspection will be returned to the developer at the
conclusion of the warranty period.
4. The oversizing amount for street construction was paid to the developer in accordance with the
Development Contract. No further compensation to the developer is needed for this project.
PASSED AND ADOPTED THIS 12TH DAY OF JANUARY 2015.
VOTE Hedberg Keeney McGuire Morton Thompson
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager