RESOLUTION 15-093
A RESOLUTION ACCEPTING BIDS AND AWARDING THE CITY'S STANDARDIZED CONSTRUCTION
CONTRACT FOR THE CREDIT RIVER ROAD IMPROVEMENT PROJECT
(CITY PROJECT#TRN15-000006)
Motion By: McGuire Second By: Thompson
WHEREAS, Pursuant to an advertisement for bids for Credit River Road Improvement Project(City
Project#TRN15-000006) which includes sanitary sewer, forcemain, lift station, water
main, storm sewer, aggregate base, concrete curb and gutter, bituminous pavement, turf
restoration and appurtenant work; and
WHEREAS, Bids were received, opened, and tabulated according to law; and
WHEREAS, The following bids were received complying with the advertisement:
COMPANY BID AMOUNT
CHARD TILING & EXCAVATING $2,776,073.50
RYAN CONTRACTING $2,852,760.50
GEISLINGER & SONS, INC. $3,198,584.81
NORTHWEST ASPHALT $3,723,632.80
and;
WHEREAS, Chard Tiling & Excavating is the lowest responsible bidder.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. Chard Tiling & Excavating is the lowest responsible bidder.
3. The Mayor and City Manager are hereby authorized to enter into the City's standard contract with
Chard Tiling & Excavating in the name of the City of Prior Lake for the Credit River Road Improvement
Project (Project#TRN15-000006) in the amount of$2,776,073.50.
4. The City Manager is hereby authorized and directed to return to all bidders the deposits that
accompanied their respective bids.
5. The City Council authorizes funding for this project as shown in the following table:
Assessments* $283,500.00
Sewer Fund $236,664.06
Water Fund $398,719.39
Water Quality Fund $18,068.32
Street Oversize Fund $179,538.08
Trunk Sewer Fund $1,156,264.34
Tax Lev $836,668.34
Project Total Cost $3,109,422.54
6. Construction costs will be recorded in the Construction Fund (#501-43500.00-55050.00 TRN15-
000006) for the Credit River Road Improvement Project.
7. The City Council authorizes the intent to issue General Obligation Bonds for this project.
8. The City Council authorizes an inter-fund loan from the Water Fund if necessary to provide interim
funding until additional bonds are issued in 2015.
9. Proceeds from the bond sale will be deposited in the Construction Fund.
PASSED AND ADOPTED THIS 26th DAY OF MAY 2015.
VOTE Hedberg Keeney McGuire Morton Thompso
Aye Z X EK EK EK
Nay ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑ 94*
Frank Boyle , ity Manager
2