AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING BIDS AND
AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE
CITY'S STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2015
STREET OVERLAY PROJECT AND CONCRETE REPAIRS
DISCUSSION: Introduction
The purpose of this agenda item is to accept the bids and authorize the
Mayor and City Manager to execute the City's Standardized Construction
Contract with McNamara Contracting, Inc. for the 2015 street overlay and
concrete repairs as identified in the 2015 Street Department portion of the
General Fund Budget.
History
Staff utilizes a pavement management system for rating the condition of
streets throughout the City. Staff then uses this system as a tool when
identifying area for maintenance and repair. Over time we have learned
that aggressive street maintenance extends the life of roadways saving
Prior Lake Taxpayers money.
Streets that are generally suitable for an overlay have an OCI between 45
and 65. Roads of this condition are typically not considered for
reconstruction or reclamation for at least 10 years which is the approximate
lifespan of an overlay. In addition the sub base of the road has to be
sound or the overlay is ineffective. It is ideal to consider roads that have
modern drainage systems including concrete curb and gutter and storm
sewer.
These maintenance activities include patching, concrete repairs and
resurfacing of road segments necessary to keep the streets usable until
they are reconstructed.
Streets to be overlaid in 2015 are in the Carriage Hills area. The following
streets have been identified by staff.
Canter Lane NE Chestnut Lane NE—Coachman Lane NE
Trotters Trail NE Chestnut Lane NE—Coachman Lane NE
Bridle Ridge Court To Bridle Ridge Trail NE
Fox Hunt Court To Surrey Lane NE
Phone 952.447.9800 / Fax 952.447.4245/www.cityofpriorlake.com
Bridle Ridge Trail NE Brougham Blvd to Bridle Ridge Ct NE
Brougham Boulevard NE Carriage Lane NE to Bridle Ridge TrI NE
Carriage Lane NE Chestnut Lane NE to Coachman Ct NE
Surrey Lane NE Fox Hunt Ct to Chestnut Lane NE
Chestnut Lane NE Canter Lane NE to Trotters Trail NE
Carriage Lane NE Carriage Hills Parkway NE to
Brougham Boulevard NE To Bridle Ridge Trail NE
Bridle Ridge Trail NE Bridle Ridge Ct NE to Coachman Lane NE
Surrey Lane NE Carriage Hills Pkwy NE to Fox Hunt Ct NE
Bridle Ridge Court NE To Bridle Ridge Trail NE
Fox Hunt Ct NE To Surrey Lane NE
Butterfield Court NE To Rosewood Road NE
Hemlock Circle NE To Bluebird Trail NE
Beach Street NE To Bluebird Trail NE
Bluebird Trail NE Hemlock Circle NE to Beach Street NE
Bluebird Trail NE Hemlock Circle NE to Rosewood Road NE
Beach Street NE To Chestnut Lane NE—Coachman Lane NE
Rosewood Road NE Butterfield Court NE to Beach Street NE
Beach Street NE To Bluebird Trail NE
Rosewood Road NE Bluebird Trail NE to Butterfield Court NE
These roads were originally built in the late 80s to early 90s. There is
approximately 2.2 linear miles of street identified in this project. As part of
the overlay there will also be 1,650 linear feet of spot curb replacements
and 11 concrete pedestrian ramp updates to bring them in compliance with
ADA requirements.
Current Circumstances
Advertisement for bid were published in both.the Prior Lake American and
Minnesota Construction eAdvertising with bids due and opened July 13th,
2015 at 11:00 am for the Street Overlay Project. The City received 3 bids
for the Street Overlay project which are listed in the chart below
Company Address Total
McNamara Rosemont MN $302,226.50
Contracting
Bituminous Roadways Mendota Heights, MN $319,056.00
Hardrives Rogers, MN $367,743.78
Conclusion
Staff is recommending awarding the construction contract to the lowest
bidder, McNamara Contracting in the amount of$302,226.50. McNamara
Contracting has previously worked for the City of Prior Lake and has
completed these projects successfully.
ISSUES: The amended 2015 Street Budget set aside $ 553,987.00 for pavement
management maintenance (overlay, seal coat, crack sealing, striping and
patching). $ 210,707.00 will be utilized for the Street JPA, $302,226.50 for
2
this overlay project with the remaining $41,054 for other overlay and
patching repairs during the course of the year.
The City's goal is to complete about 3.4 miles of street overlay per year,
however there will be about 3 miles completed between the overlay
contract and other in-house work.
This year the City seal coated 10.37 miles of street which is above the
recommended 6.75 miles. We seal coated more area this year to catch up
in our seal coating and to adjust our timing to be consistent with new
industry recommendations to seal coat roads for the first time within 2-3
years of initial construction.
FINANCIAL Funds for this project will be drawn from the Street Department portion of
IMPACT: the general fund budget of which $ 553,987.00 is identified for the City's
street maintenance programs. We will utilize $ 210,707 for the JPA and
$302,226.50 for the Overlay. The remaining funds from the balance will be
used for other pavement maintenance throughout the City.
ALTERNATIVES: 1. Motion and a second as part of the consent agenda to approve the
resolution which accepts the bids and authorized the Mayor and City
Manager to execute the City's Standardized Construction Contract with
McNamara Contracting for the 2015 Street Overlay Project.
2. Table this item for a specific reason and provide staff with direction
3. Direct staff not to proceed with the project.
RECOMMENDED Alternative #1
MOTION:
3
O� pRlp,
U
4646 Dakota Street SE
' sso`t' Prior Lake,MN 55372
RESOLUTION 15-xxx
A RESOLUTION ACCEPTING BIDS AND AUTHORIZING THE MAYOR AND CITY MANAGER TO
EXECUTE THE CITY'S STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2015 STREET
OVERLAY PROJECT AND CONCRETE REPAIRS
Motion By: Second By:
WHEREAS, The following streets have been identified by staff for overlay maintenance in 2015:
Canter Lane NE Chestnut Lane NE—Coachman Lane NE
Trotters Trail NE Chestnut Lane NE—Coachman Lane NE
Bridle Ridge Court To Bridle Ridge Trail NE
Fox Hunt Court To Surrey Lane NE
Bridle Ridge Trail NE Brougham Blvd to Bridle Ridge Ct NE
Brougham Boulevard NE Carriage Lane NE to Bridle Ridge Trl NE
Carriage Lane NE Chestnut Lane NE to Coachman Ct NE
Surrey Lane NE Fox Hunt Ct to Chestnut Lane NE
Chestnut Lane NE Canter Lane NE to Trotters Trail NE
Carriage Lane NE Carriage Hills Parkway NE to
Brougham Boulevard NE To Bridle Ridge Trail NE
Bridle Ridge Trail NE Bridle Ridge Ct NE to Coachman Lane NE
Surrey Lane NE Carriage Hills Pkwy NE to Fox Hunt Ct NE
Bridle Ridge Court NE To Bridle Ridge Trail NE
Fox Hunt Ct NE To Surrey Lane NE
Butterfield Court NE To Rosewood Road NE
Hemlock Circle NE To Bluebird Trail NE
Beach Street NE To Bluebird Trail NE
Bluebird Trail NE Hemlock Circle NE to Beach Street NE
Bluebird Trail NE Hemlock Circle NE to Rosewood Road NE
Beach Street NE To Bluebird Trail NE
Rosewood Road NE Butterfield Court NE to Beach Street NE
Beach Street NE To Bluebird Trail NE
Rosewood Road NE Bluebird Trail NE to Butterfield Court NE
WHEREAS, The City of Prior Lake is committed to improving the streets within the City by providing
continued maintenance; and
WHEREAS, Continued maintenance of City streets will reduce the need of costly reconstruction in the near
future; and
WHEREAS, A total of 3 bids (provided in the chart below) were received for the identified improvements,
with the low bid from McNamara Contracting at a cost of$302,226.50.
Company Address Total
McNamara Contracting Rosemount, MN $302,226.50
Bituminous Roadways Mendota Heights, MN $319,056
Hardrives Rogers, MN $367,743.78
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City's Standardized Construction
Contract for the identified street overlays with McNamara Contracting for an estimated cost of
$302,226.50
PASSED AND ADOPTED THIS 27th DAY OF JULY 2015.
VOTE Hedberg Keeney McGuire Morton Thompson
Aye ❑ ❑ ❑ ❑ ❑
Nay ❑ ❑ ❑ ❑ ❑
Abstain ❑ ❑ ❑ ❑ ❑
Absent ❑ ❑ ❑ ❑ ❑
Frank Boyles, City Manager