Histor~
The purpose of this agenda report is to accept a bid and award the contract for materials
for the construction of picnic shelters and gazebos in 2005 consistent with the 2005-
2009 Capital Improvement Program (C.I.P.).
The construction of a picnic shelter at Crystal Lake Park is identified in the 2006 C.I.P.
Additionally, a proposed park in Hawks Ridge area is identified in the 2005 C.I.P. for
the construction of a shelter.
The Hawks Ridge development did not materialize as staff had projected. Conversely,
the Crystal Lake development came online a year ahead of its anticipated date. By
constructing the shelter at Crystal Lake Park in 2005 rather than 2006, we would be
demonstrating an effort to complete our parks before or during the construction of the
affected homes that are being built adjacent to the parks.
The shelters and gazebos will be constructed at the following parks (see attached
aerials):
Shelters
Cardinal Ridge Park
Northwood Park
Crystal Lake Park
The Ponds Athletic Complex
Gazebos
Meadow View Park
Woods In The Wilds Park
The City Council has previously authorized a request for bids at the March 21, 2005
City Council meeting.
Bids were opened April 12, 2005. Monnens Lumber from Prior Lake was the only
vendor that submitted a bid.
Issues:
The parks maintenance division of public works will construct these shelters and
gazebos. The Sentence to Service (S.T.S.) program will also be assisting with
C:\Documents and Settings\cgreen~Local Settings\Temporary Inte~t~I~~~rd contract materials for picnic shelters and gazebos. DOC
Phone 952.447.4230 / Fax 952.447.4245
FISCAL IMPACT:
construction.
The picnic shelter design is a prototype prepared by Oertel Architects in an effort to
save money on design and structural engineering fees. The gazebo design is a
prototype used for the construction of the gazebo at Lakefront Park.
Budget Impact:
There is $120,000 identified for the construction of four shelters and two gazebos in the
2005 C.I.P.; this will pay for materials and concrete slabs for the structures.
The following bid was received from Monnens Lumber:
Materials for picnic shelters $38,000.68
Materials for gazebos $31,400.00
Total $69,400.68
Staff's estimate for the lumber to construct the shelters and gazebos was $70,937.72.
The following is a break-down of the remaining expenditures needed to construct the
shelters and gazebos:
1. Concrete floors (lowest of 2 quotes) $27,456.00
2. Concrete footings $6,000.00
3. Sonit Tubes $2,000.00
4. Hardware $3,000.00
5. Base (gravel) $5,000.00
6. Paint and stain $2,000.00
7. Pulverized black dirt $3,000.00
8. Miscellaneous $1,544.00
Total $50,000.00
Labor costs will be charged to the park maintenance budget and will be reduced with
the assistance of the Sentence to Service Program.
ALTERNATIVES:
There are three alternatives for the City Council to consider:
1. Approve a resolution accepting a bid and awarding the City's standardized contract
for materials for the construction of picnic shelters and gazebos.
2. Table this agenda item for a specific reason.
3. Deny this agenda item for a specific reason and provide staff with direction.
RECOMMENDED
MOTION:
REVIEWED BY:
Staff recommends alternative number 1.
Bud~7on Works Director
Frank B°yle~7 ~v~nager
CSDocuments and Settings\cgreen2~ocal Settings\Temporary Intemet Files\OLK162~accept bid award contract materials for picnic shelters and gazebos. DOC
16200 Eagle Creek Avenue S.E.
Prior Lake, MN 55372-1714
RESOLUTION 05-XX
RESOLUTION ACCEPTING A BID AND AWARDING THE CITY'S STANDARDIZED
CONTRACT FOR MATERIALS FOR THE CONSTRUCTION OF PICNIC SHELTERS AND
GAZEBOS
MOTION BY:
WHEREAS,
SECOND BY:
The picnic shelters at Cardinal Ridge Park, Northwood Park, The Ponds
Athletic Facility are scheduled for construction as identified in the 2005 Capital
Improvement Program; and
To demonstrate an effort to complete our parks in a timely manner, the
construction of the shelter at Crystal Lake Park has been accelerated from the
2006 C.I.P. to the 2005 C.I.P.; and
The gazebos at Woods In The Wild Park and Meadow View Park are scheduled
for construction as identified in the 2005 Capital Improvement Program; and
At the March 21, 2005 City Council meeting plans and specifications were
approved and staff received authorization to solicit bids for materials to
construct shelters and gazebos; and
The total cost for the shelters and gazebos as identified, in an amount not to
exceed $120,000; and
Bids have been solicited and one bid was received for the purchase of materials
to construct four shelters and two gazebos as follows:
Vendor Material Cost Material Cost
For Shelters For Gazebos
Monnens
Lumber $38,000.68 $31,400.00
Total Cost
$69,400.68; and
C:\Documents and Settings\cgreen~_ocal Settings\Temporary Intemet Files\OL.K.162Xaccept bid award contract materials for picnic shelters and
gazebos. DOC WWW. cit~ofpriorlake, corn
Phone 952.447.4230 / Fax 952.447.4245
Staff is authorized the following expenditures to complete the construction of
four shelters and two gazebos:
Item Cost
Concrete floors $27,456.00
Concrete footings $6,000.00
Sonit tubes $2,000.00
Hardware $3,000.00
Base (gravel) $5,000.00
Paint and stain $2,000.00
Pulverized black dirt $3,000.00
Miscellaneous $1544.00
Total $50,000.00; and
Shelters and gazebos provide shelter from the elements for picnics, gatherings
and summer playground recreational activities for children.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA, that:
1. The recitals set forth above are incorporated herein.
2. Staff is authorized to enter into the City's standardized contract for the purchase of materials
from Monnens Lumber for a total cost of $69,400.68.
3. Staff is authorized expenditures to complete the construction of picnic shelters and gazebos for a
total cost not to exceed $50,000.00.
Passed this 2nd day of May 2005.
{ Seal }
YES NO
Haul~en Haul~en
Flemin~ Flemin~
LeMair LeMair
Petersen Petersen
Zieska Zieska
Frank Boyles, City Manager
C:~Documents and Settings\cgreen\Local Settings\Temporary Internet Files\OLK162Xaccept bid award contract materials for picnic shelters and
gazebos. DOC
Scott County
Page 1 of 2
ponds park
This drawing is neither a legally recorded map nor a
survey and is not intended to be used as one. This
drawing is a compilation of records, information, and
data located in various city, county, and state offices,
and other sources affecting the area shown, and is to be
used for reference purposes only. Scott County is not
responsible for any inaccuracies herein contained. If
discrepeancies are found, please contact the Scott
County Surveyors Office.
N
March 9, 2005
http://www, co. scott.mn, us/servlet/com esri. esrimap. Esrimap?ServiceName=overview&Client... 3/9/05
Scott County
Page 1 of 2
Northwood Road
This drawing is neither a legally recorded map nor a
survey and is not intended to be used as one. This
drawing is a compilation of records, information, and
data located in various city, county, and state offices,
and other sources affecting the area shown, and is to be
used for reference purposes only. Scott County is not
responsible for any inaccuracies herein contained. If
March 8, 2005
http://www, co. scott.mn.us/servlet/com esri. esrimap. Esrimap?ServiceName=overview&Client... 3/8/05
Scott County Page 1 of 2
Stonecrest
This drawing is neither a legally recorded map nor a
survey and is not intended to be used as one. This
drawing is a compilation of records, information, and
data located in various city, county, and state offices,
and other sources affecting the area shown, and is to be
used for reference purposes only. Scott County is not
responsible for any inaccuracies herein contained. If
http://www, co. scott.mn.us/servlet/comesri, esrimap. Esrimap?ServiceName=overview&Client... 3/8/05
Scott County Page 1 of 2
Cardinal Ridge
This drawing is neither a legally recorded map nor a
survey and is not intended to be used as one. This
drawing is a compilation of records, information, and
data located in various city, county, and state offices,
and other sources affecting the area shown, and is to be
used for reference purposes only. Scott County is not
responsible for any inaccuracies herein contained. If
March 8, 2005
http://www, co.scott.mn, us/servlet/com esri. esrimap. Esrimap?ServiceName=overview&Client... 3/8/05
Scott County
,)
Page 1 of 1
This drawing is neither a legally recorded map nor a
survey and is not intended to be used as one. This
drawing is a compilation of records, information, and
data located in various city, county, and state offices,
and other sources affecting the area shown, and is to be
used for reference purposes only. Scott County is not
responsible for any inaccuracies herein contained. If
discrepeancies are found, please contact the Scott
County Surveyors Office.
N
March 9, 2005
http://www.co.scott.mn.us/servlet/com esri. esrimap. Esrimap?ServiceName=overview&Client...
3/9/05
Scott County
Page 1 of 1
This drawing is neither a legally recorded map nor a
survey and is not intended to be used as one. This
drawing is a compilation of records, information, and
data located in various city, county, and state offices,
and other sources affecting the area shown, and is to be
used for reference purposes only. Scott County is not
responsible for any inaccuracies herein contained. If
discrepeancies are found, please contact the Scott
County Surveyors Office.
March 9, 2005
http://www, co. scott.mn, us/servlet/com.esri, esrimap. Esrimap?ServiceName=overview&Client... 3/9/05