HomeMy WebLinkAbout7B - Ridgemont Ave/Creekside
AGENDA #:
PREP ARED BY:
SIJBJECT:
7B
PAUL BOETTCHER, ACTING ASSISTANT CITY
ENGINEER
CONSIDER APPROVAL OF RESOLUTION 95-37
APPROVING PLANS AND SPECIFICATIONS AND
AUTHORIZING ADVERTISEMENT FOR BIDS FOR THE
FOLLOWING COMBINED PRO.JECTS;
a) PROJECT 93-01 INDUSTRIAL PARK STORM
SEWER
b) PROJECT 93-03 TH. 13/MITCHELL POND STORM
SEWER
c) PROJECT 95-01 RIDGEMONT A VENUE
d) PROJECT 95-02 CREEKSIDE CIRCLE
DATE:
AND APPROVAL OF RESOLUTIONS 95-38, 95-39, 95-40,
AND 95-41 DECLARING COSTS TO BE ASSESSED AND
SETTING ASSESSMENT HEARING DATES FOR
RIDGEMONT AVENUE AND CREEKSIDE CIRCLE
MAY 15,1995
INTRODUCTION:
The purpose of this Agenda item is to approve plans and
specifications, to receive authorization to advertise for bids for
Project 93-01, 93-03, 95-01, and 95-02 as noted above, and to set
an Assessment Hearing date for Projects 95-01 and 95-02.
BACKGROUND:
Project 93-01. Industrial Park Storm Sewer, was part of the 1993
Improvement Projects and Resolution 93-16 ordered plans for the
improvements. Several options were reviewed and the end result
was to construct a storm sewer from the top of the hill with a
sediment sump manhole and discharge to the vegetated area near
Markley Lake. The property owner has agreed to grant a drainage
and utility easement for the storm sewer construction. There is a
city disposal area at the top of the hill which the city will clean up
in order to construct the pipe. This improvement will prevent
further uncontrolled slope erosion. The estimated construction cost
is $20,000. In the event that the easement is not acquired this
storm sewer area will be deleted from the total project.
16200 Eagle Creek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
Project 93-03. TH. 13/Mitchell Pond Storm Sewer, was part of the
1993 Improvement Projects and Resolution 93-30 requested
MnDOT provide financial assistance for this work. MSA
Consulting Engineers has prepared plans and submitted them to
MnDOT for cost sharing analysis and approval. This project will
correct an eroded area from TH. 13 to Mitchell Pond by the
construction of a storm sewer pipe in the ravine and filling over the
pipe and restoring the vegetation. The estimated construction cost
is $89,000. MnDOT has indicated cost sharing of 31.4%, or
$30,353.
Project 95-0 1. Rid~emont Avenue, is proposed to be reconstructed
from the existing curb and gutter, north 1600 feet to Rutledge
Street as shown on Exhibit 2, 3 and 4. Reconstruction to an urban
section of a 30 foot width with concrete barrier curb and a sidewalk
along the west side is proposed. Sanitary sewer and water will be
extended 900 feet to the south limits where no utilities currently
exist. This project is a hold-over from the 1994 Capital
Improvement Project and will be assessed to the benefiting
property owners and included in the 429 Bond issue. Resolution
95-09 ordered preparation of plans for this project. The estimated
construction cost is $227,000. The sidewalk will be paid out of the
park fund.
Project 95-02. Creekside Circle, is proposed to be reconstructed
from TH. 13, north 1400 feet to the cul-de-sac as shown on
Exhibits 5 and 6. Reconstruction was proposed as a 24 foot wide
rural section for the first 1000 feet and then as 24 foot wide urban
section the last 400 feet. During the detailed survey and final plan
preparation it was determined that curb and gutter would work well
along the west side and subsequently the curb and gutter was added
to the east side, too, in order to better define the street and to
protect the pavement edge. Some additional storm sewer was
required near the south end. It is anticipated the reduction in ditch
excavation, driveway culverts and restoration area will about offset
the cost of the additional curb and gutter. This project is a hold-
over from the 1994 Capital Improvement Project and will be
assessed to the benefiting property owners and included in the 429
Bond issue. Resolution 95-09 ordered preparation of plans for this
project. The estimated construction cost is $120,000.
DISCUSSION:
These four projects have been grouped together for bidding
purposes in order to create a sizable project to obtain competitive
bid prices. The combined estimated construction costs total
ALTERNATIVES:
$447,000. The Mitchell Pond project requires fill material which
can be acquired from the Creekside Circle site, also saving money.
Under the Cooperative Agreement conditions with MnDOT for
Mitchell Pond, the project cannot be advertised until MnDOT has
reviewed and approved the plans which is currently underway.
MnDOT had indicated award to be required by June 30, 1995,
however they have stated funds can be advance encumbered to
allow award after June 30, 1995. MnDOT had indicated approval
about May 15 which would allow advertisement in the legal paper
on May 20 and a bid opening on June 12 and award on June 19,
1995. Construction could then begin about July 5. Waiting for
MnDOT approval is potentially worth $30,000 of cost sharing. If
MnDOT's approval is after May 15 the ad and bid dates may be
pushed back two weeks or more, thus delaying the construction
start too.
In order to proceed with timely construction in July and August, it
is desired to schedule the Assessment Hearing date prior to the
receiving of bids. It is recommended that the Ridgemont Avenue
assessments be set at 100% of the Public Hearing amounts and that
the Creekside Circle assessments be set at 105% of the Public
Hearing amounts. If bids are substantially lower than these
estimated assessments, the property owners can be re-notified with
adjusted rates. Authorizing the Assessment Hearing at this May 15
Council meeting would allow for mailed notices to go out on June
1 for a June 19 meeting. Not moving forward with setting the
Assessment Hearing tonight would delay the project by three
weeks.
The alternatives are as follows:
1. Approve the Resolution approving the plans, authorizing
Advertisement for Bids with a bid opening date of June 12,
1995, at 10:00 A.M., and set an Assessment Hearing date of
June 19, 1995. All of the above are contingent on MnDOT
approval. If MnDOT's approval is delayed, the City
Manager and City Engineer would have the authority to
advertise and bid one week later, however, the Award and
Assessment Hearing could remain on June 19, 1995.
2. Table this item for a specific reason.
3. Deny the project at this time.
RECOMMENDATION: The recommendation is to approve a Resolution approving plans
and specifications and authorizing advertisement for bids on June
12, 1995, for the combined projects.
The recommendation is also to approve Resolutions declaring costs
to be assessed and setting an Assessment Hearing date of June 19,
1995.
FINANCIAL IMP ACT:
Project 93-01 and 93-03 will be paid through Ad Valorem Tax
Levy.
Projects 95-01 and 95-02 will be paid through Special
Assessments, Ad Valorem Tax Levy, and Trunk Reserve.
ACTION REQUIRED:
Make a motion to approve the Resolutions as recommended.
AG515B
RESOLUTION 95-37
RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND
AUTHORIZING ADVERTISEMENT FOR BIDS FOR
THE FOLLOWING PROJECT:
PROJECT 93-01 INDUSTRIAL PARK STORM SEWER
PROJECT 93-03 TH. 13/MITCHELL POND STORM SEWER
PROJECT 95-01 RIDGEMONT AVENUE
PROJECT 95-02 CREEKSIDE CIRCLE
AND SET AN ASSESSMENT HEARING DATE FOR
RIDGEMONT AVENUE (95-01) AND CREEKSIDE CIRCLE (95-02)
MOTION BY SECONDED BY:
WHEREAS, pursuant to Resolution 93-16 which the City Council approved on March 15,
1993, the City Engineer and the City's Engineering Consultant, MSA Consulting
Engineers, have prepared plans and specifications for storm sewer improvement
project in the Industrial Office Park by the construction of grading, storm sewer,
landscaping and appurtenant work; and
WHEREAS, pursuant to Resolution 93-30 which the City Council approved on May 17, 1993,
the City Engineer and the City's Engineering Consultant, MSA Consulting
Engineers, have prepared plans and specifications for the storm sewer
improvement project from TH. 13 to Mitchell Pond by the construction of
grading, storm sewer, landscaping, and appurtenant work; and
WHEREAS, pursuant to Resolution 95-09 which the City Council approved on February 6,
1995, the City Engineer and the City's Engineering Consultant, MSA Consulting
Engineers, have prepared plans and specifications for the street improvement
project Ridgemont Avenue by the construction of grading, sanitary sewer,
watermain, storm sewer, aggregate base, concrete curb and gutter, bituminous
surfacing, sidewalk, landscaping, and appurtenant work; and
WHEREAS, pursuant to Resolution 95-09 which the City Council approved on February 6,
1995, the City Engineer and the City's Engineering Consultant, MSA Consulting
Engineers, have prepared plans and specifications for the street improvement
project on Creekside Circle by the construction of grading, storm sewer, aggregate
16200 Eagle Creek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
base, concrete curb and gutter, bituminous surfacing, landscaping, and
appurtenant work;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOT A, that
1. Such plans and specifications, a copy of which is attached hereto and made
a part of hereof, and hereby approved.
2. The City Manager shall prepare and cause to be inserted in the official paper
and in the Construction Bulletin an advertisement for bids upon the making
of such improvement under such approved plans and specifications. The
advertisement shall be published not less than 21 days prior to bid opening,
shall specify the work to be done, shall state that bids will be opened, and
that all bids will be received by the City until 10:00 A.M. on June 12, 1995,
at which time they will be publicly opened at City Hall by the City
Engineer.
3. The City reserves the right to reject any and all bids for any reason as
determined solely by the City.
4. The City Manager shall also have the authority to modify the bid date to
June 19, 1995, at 10:00 A.M., if MnDOT approval is delayed and this
schedule change remains in accordance with State Statutes.
Passed and adopted this 15 day of May, 1995.
YES
NO
Andren
Greenfield
Kedrowski
Schenck
Scott
Andren
Greenfield
Kedrowski
Schenck
Scott
Frank Boyles
City Manager
City of Prior Lake
{Seal }
AG515B
RESOLUTION 95-38
RESOLUTION DECLARING COSTS TO BE ASSESSED AND
ORDERING PREPARATION OF PROPOSED ASSESSMENT FOR
PROJECT 95-02 CREEKSIDE cmCLE STREET IMPROVEMENTS
MOTION BY: SECONDED BY:
WHEREAS, an Engineer's Estimate has been prepared and costs have been determined for the improvements
ofProiect 95-02 and the estimated contract price for such improvements is $125 90000, and the
estimated expenses incurred or to be incurred in the making of such improvement amount to
$37 80000, so that the total cost of the improvement will be $163 700.00.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF PRIOR LAKE,
MINNESOTA:
1. The portion of the cost of such improvement is to be paid by the City's Ad Valorem Tax
Levy and is hereby declared to be $65 500.00, and the portion of the cost to be assessed
against benefited property owners is declared to be $98 200.00.
2. Assessments shall be payable on an equal principal installment method extending over a
period of lQ years. The first installment shall be the annual principal plus interest
calculated from the public hearing date to the end of this year plus twelve months of the
next year and shall bear interest at the rate of a minimum of 8% and not more than 1 %
above the net effective interest rate of the bond issuance per annum from the date of the
adoption of the assessment resolution.
3. The City Manager, with the assistance of the City Engineer shall forthwith calculate the
proper amount to be specially assessed for such improvement against every assessable lot,
piece or parcel of land within the district affected, without regard to cash valuation, as
provided by law, and he shall file a copy of such proposed assessment in his office for
public inspection.
4. The City Manager shall upon the completion of such proposed assessment, notify the
Council thereof.
Passed and adopted this 15 day of May, 1995.
{ Seal}
YES
NO
Andren
Greenfield
Kedrowski
Schenck
Scott
Andren
Greenfield
Kedrowski
Schenck
Scott
Frank Boyles
City Manager
City of Prior Lake
16200 Eagle Creek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
RESOLUTION 95-39
RESOLUTION DECLARING COSTS TO BE ASSESSED AND
ORDERING PREP ARA TION OF PROPOSED ASSESSMENT FOR
PROJECT 95-01 RIDGEMONT A VENUE STREET IMPROVEMENTS
MOTION BY: SECONDED BY:
WHEREAS, an Engineer's Estimate has been prepared and costs have been determined for the improvements
of Project 95-01 and the estimated contract price for such improvements is $226 700.00, and the
estimated expenses incurred or to be incurred in the making of such improvement amount to
$6800000, so that the total cost of the improvement will be $294 700.00.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF PRIOR LAKE,
MINNESOT A:
1. The portion of the cost of such improvement is to be paid by the City's Ad Valorem Tax
Levy and Trunk Reserve is hereby declared to be $32 590.00, and $11268200
respectively, and the portion of the cost to be assessed against benefited property owners
is declared to be $149 428.00.
2. Assessments shall be payable on an equal principal installment method extending over a
period of lQ years. The first installment shall be the annual principal plus interest
calculated from the public hearing date to the end of this year plus twelve months of the
next year and shall bear interest at the rate of a minimum of 8% and not more than ] %
above the net effective interest rate of the bond issuance per annum from the date of the
I
adoption of the assessment resolution.
3. The. City Manager, with the assistance of the City Engineer shall forthwith calculate the
proper amount to be specially assessed for such improvement against every assessable lot,
piece or parcel of land within the district affected, without regard to cash valuation, as
provided by law, and he shall file a copy of such proposed assessment in his office for
public inspection.
4. The City Manager shall upon the completion of such proposed assessment, notify the
Council thereof.
Passed and adopted this 15 day of May, 1995.
{Seal}
YES
NO
Andren
Greenfield
Kedrowski
Schenck
Scott
Andren
Greenfield
Kedrowski
Schenck
Scott
Frank Boyles
City Manager
City of Prior Lake
16200 Eagle Creek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
RESOLUTION 95-40
RESOLUTION FOR HEARING ON PROPOSED ASSESSMENT FOR
RIDGEMONT AVENUE STREET IMPROVEMENT PROJECT 95-01
MOTION BY: SECONDED BY:
WHEREAS, by a resolution passed by the Council on May 15, 1995, the City Manager was directed to
prepare a proposed assessment of the cost of improvements for Project 95-01; and
WHEREAS, the City Manager notifies the Council that such proposed assessment will be completed and filed
in his office for public inspection.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF PRIOR LAKE,
MINNESOTA:
1. A hearing shall be held on the 19th day of June 1995 in City Council Chambers at ~
f...M.. to pass upon such proposed assessment and at such time and place all persons
owning property affected by such improvement will be given the opportunity to be heard
with reference to such assessment.
2. The City Manager is hereby directed to cause a notice of the hearing on the proposed
assessment to be published once in the official newspaper at least two weeks prior to the
hearing, and he shall also cause mailed notice to be given to the owner of each parcel
described in the assessment roll not less than two weeks prior to the hearing.
3. The owner of any property so assessed may, at any time prior to certification of the
assessment to the County Auditor. pay the whole of the assessment on such property, with
interest accrued to the date of payment to the City Finance Director: except that no
interest will be charged if the entire assessment is paid within 30 days from the adoption
of the assessment. He may, at any time thereafter, pay to the City Finance Director the
entire amount of the assessment remaining unpaid, excepting the installment portion
appearing upon the current year's property tax statement.
Passed and adopted this 15 day of May, 1995.
{Seal}
YES
NO
Andren
Greenfield
Kedrowski
Schenck
Scott
Andren
Greenfield
Kedrowski
Schenck
Scott
Frank Boyles
City Manager
City of Prior Lake
16200 Eagle Creek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
l\-10TION BY:
WHEREAS,
WHEREAS,
RESOLUTION 95-41
RESOLCTION FOR HEARJNG ON PROPOSED ASSESSJ\IENT FOR
CREEKSIDE CIRCLE STREET IMPROVEMENT PROJECT 95-02
S-rCONDED BY:
by a resolutit)l1 passed by the Council on May 15., 1995. the City tvlanager was directed to
prepare a proposed a3sessment of the cost of irriprovements for Proiect o~-O'''; and
the City l\.lanager notifies the Council that such ?roposed assessment will be compieted and filed
in his office for public inspection.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF PRIOR LAKE,
l\lINNESOTA:
1. A hearing shall be held on the J Oth day of June ll}~)S in City Council Chambers at ~
~ M. to pass upon such proposed assessment and at such time and place all pe:'sons
owning praperry affected l:Iy such ilnprovement w;li be given the oppommir:,/ to be heard
with reference to such assessment.
2. The City Manager is hereby directec to cause a notice of the hearing or! the proposed
asseS.5ment to be published once in the official n~\"spaper at least t'NO weeks prior to the
hearing, and he shall also CaUse ma~led notice to be given tv the own~; of each parcel
des:i'ined in. the :.i~$essmem roll !1(.': less th(;.r~ l\\Q \veeks prio: to thl' he~~ring.
3. The owne" of 3.!1.y prop~:ry 50 assessed maY. at ~n~' time prio: to c-=nif:cation 0: the
"~5~s.sm~;:t to the County .t"udiw!'. P3Y the v.'hoie ~)f the a'3sessm::nt an su~h prope.ty, with
imeiest a;;:rued te. th~ d~te of payment. to i.fle City :=i:1ance DIrector, excep: that no
interest wiU be charged if the entire assessment ~5 paid within 30 days from the adoption
of the assessment. He may, at an~' time thereafter, pay to the City Finance Director the
enure amOU:lt or the assessmem remaining unpaid. eXL:cpting the installment portion
3'ppear:ng upon rhe CUr7cn: year' s plo~erty tax stat~ment.
Passed and adopted this 15 day of 1\'13Y, 1995.
{ Seal}
YES
NO
Andre-n
Greeaneld
Kedrowski
Schencl~
Scott
Andren
Greenfield
Kedrowski
Schenck
Scott
Fr~a1\. 30yies
:=ity l\1:mager
City 0: Frior L,<~e
16200 Eagle Creek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTUNITY EMPLOYER
,
~
ATTACHMENT FOR AGENDA 7B
CC>>0CiG Sl:
RUn.EDGE ST
EXISnNG~."
WETLANDS ..
..
HOPE ST.
EXlSllNG S1ORt.f
TO BE REMOVED
~
~
~
PROPOSED 1S-RCP
o
iE
PROPOSED C.B.'S
PL023EX1
~
o 300
. .
J:::::::.:::::.:::::::::::~::::::::.::::::l S ~ I IYPROVEWENlS
>---0--+-0 EXISllNG STORM SEER
~. c__ PROP. STOIaI SEWER
MS
STORM SEWER AN)
STREET IMPROVEMENTS
RIDGEMONT AVE.
~~IMJD~Dii
~
CISOL1IC IICIIIIIS
(~) -I 1--
1 1/2- TYPE ~1A BllUMINOUS WEAR COURSE
TACK COAT
3- rtPE 31S SrnJMINOUS BASE COURSE
6- ClASS 5 AGGREGATE BASE
12- SUBGRADE PREP AM liON (F NECESSARY)
Sf A 5+50 TO Sf A 14+92
4CI
4- CONCRElE W
(6- . DRIVEWAYS)
4- ClASS 5
R
33'
5' VARIES
26'
ROW
JO' FACE TO F' ACE
I
!
I
I
ac GUTTER
2.~___
33'
ROW
30' FACE TO FACE
H
Ie GUlTER
2.00%___
(~) -J 1--
1 1/2- nPE ~1A BITUMINOUS WEAR COURSE
TACK COAT
3- T'tPE 31 B BITUMINOUS BASE COURSE
6- ClASS 5 AGGREGATE BASE
12- SUBCRAOE PREPARA lION (IF' NECESSARY)
STA -0+50 TO STA 5+50
PL023EX1
MS
TYPICAL STREET SECTION
7 TON DESIGN
RlDGEMONT AVE.
CDISUI.B II.1um
~~IXJD~Oli
~
.:~
/"
PL023EX1
MS
CDI.\1IL11K IaIIIS
,/
CONDONSsr:
RU11...EDGE ST
EXlSllNG
6- WA TERMAI
HOPE ST.
EXISllNG
8- SANITARY
PROPOSED
S-DIP WA lERMAIN
~
o 300
. .
o 0 EXISllNC SANITARY SEER
· · · PROP. SANITARY SEWER
-1-1- EXlSllNG WATERMAIN
--e_t- PROP. WA lERYAlN
UTIUlY IMPROVEMENTS
RlDGEMONT AVE.
~~IXlD~Dir
~
.,,~~
PROPOSED 15-RCP STORM SEWER
9
10
EXISTING 18" RCP
STORM SEWER
13
PROPOSED BEEHIVE
o APRON IN DITCH
NO 1S-RCP STORM SEWER 4
14
15
3
CURB AND GUTTER
BOTH SIDES OF SlREET
o '\~
~---( ~ .
y..\~""
~U~'/..
~
o 200
l:~::::::::::::::::::::~::~::::~:~:::~ S T tct.t.1 IMPROVEMEHlS
>-0--+-0 EXlS11NG SlQIW SEWER
.. c__ ~ Sl~ SEWER
PL027EX1
MS
PROPOSED CONSTRUCTION ~~IXlD~Dir
CREEKSIDE CFtCLE ~
CDISIIL11I JaIIIS
~
~.,.
>,'
~
R
66'
ROW
24' FACE TO FACE
. I
EXISTING
DITCH
2.00%____
18-
~ I -(TYP.)
1 1/2- TYPE 41A BITUMINOUS \\EAR COURSE
TACK COAT
J- TYPE J1B BITUMINOUS BASE COURSE
4- CLASS 5 AGGREGATE BASE
12- SUBCUT / SELECT GRANULAR BORROW
URBAN STREET SECTION
PL027EXl
MS
PROPOSED TYPICAL S r Ht:t: I SECTIONS
7 TON DESIGN
CREEKSIDE CIRCLE
~~IMlD~OlF
~
CDISIII.1IC IaIIIS
RESOLUTION 93-16
RESOLUTION ORDERING IMPROVEMENTS AND PREPARATION OF PLANS
ON BUSINESS OFFICE PARK (PROJECT#93-11) AND OTHER 1993
CITY IMPROVEMENT PROJECTS
MOTIONED BY
WHITE
SECONDED BY FITZGERALD
WHEREAS, pursuant to Resolution 93-05 which the
adopted on February 16, 1993 calling
Hearing to be held at 8:00 P.M. on March
the following improvements:
City Council
for a Public
IS, 1993 for
AREA 1 - BUSINESS OFFICE PARK
Proposed Business Office Park located south of CSAH 21 and
within section 1 by the construction of grading, sanitary
sewer, watermain, storm sewer, aggregate base, concrete curb
and gutter, bituminous surfacing and appurtenant work:
AREA 4 - CSAH 21 IMPROVEMENTS
CSAH 21 from 2000 feet east of Franklin Trail to east City
limit line by the construction of storm sewer, concrete curb
and gutter, lighting, sidewalk, landscaping and appurtenant
work;
/
AREA 5 - EXISTING INDUSTRIAL PARK STORM SEWER
From the existing Industrial Park and City Maintenance Shop
areas within Section 1 to Markley Lake by the construction of
a storm sewer/ponding system and appurtenant work:
AREA 6 - CSAH 42 FROM FERNDALE AVENUE TO BOONE AVENUE
CSAH 42 from Ferndale Avenue to T.H. 13 by the construction
of storm sewer, watermain, sanitary sewer crossing, concrete
curb and gutter, intersection lighting, bikeway, landscaping,
and appurtenant work:
AREA 7 - FISH POINT ROAD EXTENSION IN THE GREENBRIAR PARCEL
Fish Point Road from CSAH 44 south to approximately 1,500
feet within the Greenbriar property, by the construction of
grading, aggregate base, storm sewer, concrete curb and
gutter, bituminous surfacing, sidewalk and appurtenant work;
4629 Dakota 51. 5.E.. Prior Lake. Minnesota 55372 ! Ph. (612) 447-4230 / Fax (612) 447-4245
A'~ [QLAl. OPPORTL':--;ITY E.I\.1PLOYER
~--------~-------'-----'-".."
RESOLUTION 93-30
RESOLUTION REQUESTING MINNESOTA DEPARTMENT OF TRANSPORTATION
FINANCIAL ASSISTANCE IN THE UPGRADING OF THE STORM SEWER OUTLET
FROM T.H. 13 TO MITCHELL POND
MOTION BY
KEDROWSKI
SECONDED BY
WHITE
WHEREAS, the storm runoff from the T.H. 13 drainage system west
of Cand~ Cove Trail runs overland across the rear of
propertles adjacent to the highway; and
WHEREAS, the volume and velocity of this overland flow causes
concerns relative to safety and erosion; and
WHEREAS, the City understands T.H. 13 is planned to be upgraded
in the future at which time the drainage issues would
have to be addressed, and
WHEREAS, the City feels that immediate improvements to the
drainage system in the area would provide a benefit to
the trunk highway system.
NOW THEREFORE BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF
PRIOR LAKE, MINNESOTA, that the Minnesota Department of
Transportation financially assist the City of Prior Lake with the
upgrading of the T.H. 13 drainage system in the area of Candy
Cove Trail.
Passed and adopted this 11-th day of
YES
May
, 1993.
NO
Andren
Fitzgerald
Kedrowski
Scott
White
x
X-
X-
X-
X-
Andren
Fitzgerald
Kedrowski
Scott
White
f--
{Seal}
~
Lake
4629 Dakota St. S.E.. Prior Lake. Minnesota 55372 / Ph. (612) 4474230
AN EQLAL OPPORTCNITY EMPWYER
EiX ~612) 447-4245
RESOLUTION 95-09
'It ~~
INNESO RESOLUTION ORDERING IMPROVEMENTS AND PREPARATION OF
PLANS ON 1995 IMPROVEMENT PROJECTS
(RIDGEMONT AVENUE - PROJECT 95-01;
CREEKSIDE CIRCLE - PROJECT 95-02; AND
TITUS ADDITION - PROJECT 95-03)
MOTION BY:
WHEREAS:
KEDROWSKI
SECONDED BY:
SCHENCK
pursuant to Resolution 94-61 which the City Council adopted on December 5,
1994 calling for a Public Hearing to be held on the proposed 1995 improvement
projects.
)
Area 1 - Ridl:emont Avenue
Ridgemont Avenue from the existing concrete curb and gutter to Rutledge Street,
including sanitary sewer, watermain, storm sewer, grading, aggregate base,
concrete sidewalk, bituminous surfacing, and appurtenant work.
') Area 2 - Creekside Circle
Street reconstruction of Creekside Circle, including grading, aggregate base,
storm sewer, concrete curb and gutter, bituminous surfacing, and appurtenant
work.
Area 3 - Titus Addition - This project was deleted by Council.
Area 4 - Construction of Restrooms/Storage in Memorial Park
Construction of restrooms/storage beneath the grandstand in Memorial Park.
Area 5 - CSAH 18 from City Limits to CSAH 42
CSAH 18 from the City limits to CSAH 42 by the construction of storm sewer,
utility crossings, concrete curb and gutter, sidewalk, landscaping, and
appurtenant work.
~ - CSAH 44 from T.H. 13 to East City Limit Line
CSAH 44 from T.H. 13 to East City limit line by the construction of storm sewer,
concrete curb and gutter, sidewalk, trail, lighting, landscaping, traffic control
signal, and appurtenant work.
~ - County Road 83 from County Road 82 to CSAH 42
County Road 83 from County Road 82 to CSAH 42 by the construction of a trail
system.
16200 Eagle Creek Ave.. Prior Lake. rvlinnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
", . ::.'.)1 ',\L '.;[V';:CR;-'\r:--' ~~:'!!,'_,.:'::::~
RS953.WRT
Area 8 - Construction of Restrooms/Shelter in Grainwood Park
Construction of restrooms and shelter at Grainwood Crossing Park.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND CITY COUNCIL OF PRIOR
LAKE, MINNESOTA, that:
1. Such improvement is hereby ordered as proposed in the Council
Resolution 94-61 adopted December 5, 1994, for such streets and areas
in accordance with the report and the assessment of property as described
in the report for all or a portion of the cost of the improvement pursuant
to Minnesota Statutes Chapter 429 at an estimated total cost of the
improvements of $1,297,968.00.
2. The City Engineer and the city's engineering consultant, MSA
Consulting Engineers, is hereby designated as the Engineer for this
improvement. He shall prepare plans and specifications for the making
of this improvement.
Passed and adopted this 6th day of February, 1995.
YES
NO
Andren
Greenfield
Kedrowski
Schenck
Scott
Absent
_X_
_X_
_X_
_X_
Frank Boy s
City Man ge
City of Prior Lake
{ Seal }
~.