HomeMy WebLinkAboutRidgemont Avenue
Volume I, Number I
July 31, 1995
Construction Update
Ridge..ont Avenae
CONSUIJTING E~GINEERS
Sewer & Water Installation Complete,
Grading & Storm Sewer Installation Slated
The City of Prior Lake, MSA Consulting
Engineers, and S.M. Hentges and Sons would like
to thank residents for their patience during the
street reconstruction on Ridgemont Avenue. The
work being done is much more than just repaving.
This is a total street reconstruction project, includ-
ing underground utility work, which will provide
a quality road for the next 20 years
Utility Installation
The installation of sanitary sewer and
watermain will be completed by the end of this
week. Storm sewer crossings will be installed
early next week and will complete the under-
ground work.
Getting Around
To assist traffic in getting
through the construction area,
the contractor, S.M. Hentges &
Sons, provides a flagman during
working hours. Because Ridgemont
Avenue is your only route to and from
your homes, the contractor has arranged his work
so that your route remains passable. The surface is
to be graded hourly during working operations.
We ask that you be patient with the sticky condi-
tions on rainy days, until the contractor has a
chance to grade the road and the sun has a chance
to dry out the wet soil.
Construction of a temporary detour road was
evaluated during the design of the project. How-
ever, due to site constraints, it was determined that
a temporary detour road was not feasible - there is
simply no place to construct one.
Subgrade Correction
In the next week or so, unstable soil will be
removed from areas that are especially soft to
drive on. It will be replaced with crushed rock,
which will provide a stable sub grade to support
the new road surface, and provide a temporary
driving surface. The city is working closely with
the contractor to expedite the placement of the
crushed rock.
In addition, 4-inch drain tile will be put in
place to help sub grade drainage. This will extend
the life of the new pavement.
Continued on back
Estimated Schedule.
Next Three Weeks
Week of July 31
- Storm sewer installation
- Placement of crushed rock
Week of August 7
- Crushed rock placement
Week of August 14
- Curb and gutter installed
· Wet weather could affect this schedule
(Continued from front)
Schedule
The Ridgemont Avenue Street Reconstruc-
tion Project began this past July 17. The
scheduled completion date is September 14,
1995. To many of you it may appear that
little progress has been made. This is
because the underground portion of this
type of project takes longer and results in
more disruption to residents, than the
above ground work. This particular
project has also been complicated by
the fact that there have been
several rain days since its begin-
ning. Two inches of rain fell on July 21st, which
virtually stopped work.
Nevertheless, despite the rain and unforeseen
delays in the underground phase, the City, MSA
and the contractor feel confident of meeting the
completion date. Residents should notice a great
deal of progress in the next two weeks.
Who To Call
Dave Thompson is the proj ect inspector.
Dave is accessible in Prior Lake every day. He
can be reached through his pager at 637-6100.
When calling the pager, wait for the beep, enter
your phone number, then hang up.
Your number will appear on
Dave's pager and he will call you
back as soon as he is able.
Dave is the quickest and
most efficient means for you to
get answers regarding the proj ect.
However, if you are unable to reach Dave, you can
call Paul Boetcher at the MSA office at 644-4389,
or the contractor (S.M. Hentges) at 492-5700.
We thank you again for your cooperation and
patience during these periods of rainy weather.
After the crushed rock has been placed over the
next several days, the rain will have less impact on
the condition of the roadway and travel should
improve throughout the area. Your continued
cooperation and helpful phone calls are sincerely
appreciated by the City and the Engineer. .
RIDGEMONT AVENUE CONSTRUCTION UPDATE
JULY 31, 1995
The Ridgemont Avenue project involves watermain and sanitary sewer extensions, minor storm
sewer work, and total reconstruction of the street, including placement of concrete curb and
gutter. A sidewalk will also be constructed along the Lake Front Park side of the street.
The construction cost estimate that was presented to those persons attending the public
informational meeting and public hearing is attached and totals $226,700. The low bidder (S. M.
Hentges) bid the project as follows:
Street and Storm Sewer
Sanitary Sewer
Watermain
$123,861
27,870
30.653
Total
$182,3~4
By subtracting the bid price of $182,384 from the estimate of $226,700, it can be determined that
the bid price is $44,316 lower than the estimate.
The estimated cost was based on subcutting the street one foot and replacing the excavated
material with granular borrow (pit run sand). However, during design, the subcut and granular
borrow were deleted in an effort to reduce construction costs and the resulting high assessment
rates (please see attachment). In lieu of subcut and granular borrow, a one-foot subcut and
recompaction were specified. This measure saved $25,000 to $30,000 in construction costs,
which was reflected in the difference between the estimated construction cost of $226,700 and the
bid price of $182,834.
The Contractor, S. M. Hentges, is now working on the underground construction. The sanitary
sewer is in and work is proceeding on the watermain. A minor amount of storm sewer
construction will follow the watermain work. Barring rain delays, the underground work should
be completed on or about August 2, 1995. Actual street construction will begin after the
underground construction is completed.
Since the project began, there have been a number of rainfall events, including a 2-inch rainfall
on July 21, 1995. A large number of resident complaints have been received. The complaints
peak after each rainfall event. In addition to making the subgrade slippery and difficult to drive
on, the rainfall has increased the moisture content of the sub grade to well over its optimum
moisture content for compaction.
To reduce the moisture content of the subgrade to make it suitable for compaction, it will be
necessary to "farm" the soil by scarifying, windrowing, and turning it to get it to dry out. This
process will take time and will result in only one lane being available for traffic for extended
periods of time. Based on the number of resident complaints received to date from the 150
homeowners that must use Ridgemont Avenue, it is MSA's opinion that this will lead to an
intolerable situation.
102/023-2702.jul
An alternate to subcutting the subgrade and "farming" the soil would be to remove the subcut
material and replace it with granular borrow or crushed rock. Crushed rock would be better
because it would provide a better temporary driving surface that would minimize resident
complaints.
The primary advantage of this alternate would be to reduce the impacts of the Ridgemont Avenue
reconstruction to the 150 homeowners who must travel through the construction zone. A
secondary advantage would be extended pavement life. The disadvantage of this alternate would
be that it could potentially add back the $25,000 to $30,000 that was saved.
However, based on the large number of complaints received from residents to date, it is staff's
opinion that the alternate method of construction be implemented. Although the alternate method
of construction would increase the Ridgemont Avenue project cost by $25,000 to $30,000, the
resulting project cost of $207,000 to $212,000 would still be less than the $226,700 estimated
construction cost that was presented to residents during the public information meeting/public
hearing process.
102/023-2702.jul
If' "'-""...._-~.~"""---_.. ...._"'~.....,_.--_.,-.._-".-.._"*----~......~---'-'-,-~"~~--'-',--~._..",_.,-----".,.",,-
V. PROJECT COST - RIDGEMONT AVENUE
ESTIMATED STREET AND STORM
CONSTRUCTION COST
$171,500
ESTIMATED SANITARY SEWER
CONSTRUCTION COST
33,800
ESTIMATED W A TERMAIN
CONSTRUCTION COST
21,400
INDIRECT COSTS (30%)
68,000
ESTIMATED TOTAL PROJECT COST
$294,700
Project Assessment (100% - S, W, & Streets)
Project Assessment (60% - Street Only)
Project Tax Levy (40% - Street Only)
$213,207
$48,903
$32,590
For Street Where Sewer and Water Will Be Extended
Project Assessment (100% - S, W, & Streets) $213,207
Project Assessable Front Footage 1,824 FF
Project Assessment Rate $116.89/FF
For Street Where Sewer and Water Exist
Project Assessment (60% - Street Only)
Project Assessable Front Footage
Project Assessment Rate
$48,903
1,051 FF
$46.53/FF
102/023-2702.jul
--T"'-
EXlS11NG S'TCRM
10 BE REMOVED
~S1:
RUllEDGE ST
HOPE ST.
EXISnNG~ ..
WETLANDS .
.
PROPOSED 15-RCP
PROPOSED C.B.'S
PL023EX1
MS
~~
~
o 300
. .
J::::::::::::::::::::::::::::::::::~::::::l STRt.a:.1 ~
>-0--+-0 EXIS'nNQ SRIW SEER
.. c__ PRCP.~ SEWER
STORM SEWER AN)
STREET I~VEMENTS
RDGBAONT AVE.
'1..------ .-~.-.~.-----._.__..-.._._..__..__._..-.....-.........-~.....--.-..........-..---r---
~XC=fJD[g3Dir
~
4d
..
28.
3rt FACE 10 FACE
H
.. GUTTER
2.~____
4- CONCRElE W
(8- . DRI~AYS)
4- a.ASS 5
(~) -It-
1 1/2- T't'PE 41A 81lUM1NOUS WEAR COURSE
TAO< COAT
~ TVPE 318 811\UNOUS BASE COURSE
6- CLASS 5 AGGREGATE BASE
12- SUBGRADE PREP ARA nON (F NECESSARY)
ST A 5+50 TO Sf A 14+92
33'
33'
30' FACE TO FACE
H
5' VARIES
...- CONCRETE WAlK
(6- . DRI~AYS)
.- CLASS 5
PL023EX1
MS
CIISIJLDK IIIiIIIIa
ak GU11ER
~-4R!rs
2.00% ----..
k~t-
1 1/2- T'I'PE 41A BlllJ..,NOUS WEAR COURSE
TACK COAT
3- T'I'PE 31 B BlllJWlNOUS BASE COURSE
6- ClASS 5 AGGREGATE BASE
12- SUBGRADE PREPARAllCIf (IF NEC[SSARY)
Sf A -0+50 TO STA 5+50
TYPICAL S1lEET SECTION
7 TON DESIGN
RDGEMONT AVE.
ROW
~~IHJO~Dir
~