KEN SHERMAN, ENGINEERING TECHNICIAN
CONSIDER APPROVAL OF RESOLUTION 95-72
APPROVING PLANS AND SPECIFICATIONS FOR
CITY PROJECT 94-07, UPGRADE LIFT STATION #3
AND AUTHORIZE ADVERTISEMENT FOR BIDS.
AUGUST 21, 1995
INTRODUCTION:
The purpose of this agenda item is to consider approval of
resolution 95-72, approving the plans and specifications for
city project #94-07 upgrading lift station #3. This project
was originally scheduled for .1994 but is being completed
this year as part of the staffs initiative to bring all the
projects up to date. The attached resolution approves plans
and specifications and also authorizes city staff to advertise
the project for bids.
BACKGROUND:
Lift Station No. 3 is located off Franklin Trail in the
Brooksville Hills 5th Addition and was built in 1971 to
serve the Brooksville Hills area. The Cardinal Ridge
subdivision is also to be served by this lift station. The lift
station is close to capacity currently and needs to be
upgraded to handle the increased sewage flow generated by
Cardinal Ridge.
Lift Station No. 3 has an existing capacity of 180 gallons
per minute. Calculations show that with the addition of
Cardinal Ridge 2nd Addition, the lift station will be over
capacity and it is necessary to increase the capacity. A
sewer study was done by City Staff for this area in 1988
that indicated an upgrade of the lift station is necessary
once the area east of Brooksville Hills develops. With the
amount of development in the Cardinal Ridge and
Brooksville Hills area it is time to increase the pumping
capacity of the lift station.
The construction items include replacing both pumps in the
lift station. Since the construction cost is estimated to be
1620(ft!brgr~reek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORlUNrTY EMPLOYER
over $25,000.00, an advertisement for bids and public bid
opening is required. Plans are available in the engineering
department. The attached resolution 95-72 sets the bid
opening on September 19, 1965. Construction would be
done this year pending Council authorization. A map has
been also enclosed showing the lift station location and
sewer service area.
The estimate for the project is as follows:
Pump Replacement
Control Panel
Internal Pipe Replacement
Contingency (15%)
Engineering
Total
$10,000
$10,000
$12,500
$5,000
$5.000
$42,500
An alternate bid has been added to the bid proposal for
work outside the manhole. The alternate bid adds the
replacement of 4" pipe with 6" pipe outside the lift station.
This work would be prudent for two reasons:
1. The 4" line feeds into a six inch line. Replacing the 4"
pipe with a 6" would improve the overall flow from the lift
station.
2. The existing 4" pipe has been broken and repaired. This
break occurred due to settlement of the backfill around the
lift station. This kind of settlement is not likely to reoccur.
The velocity in the 4" pipe is presently at the maximum
recommended. Larger pumps will increase the chance of
rupturing the repair clamps.
The cost of replacing the pipe, estimated at $15,000, is
high, however, as there are several utilities, including cable,
power and telephone in the vicinity of the pipe. This means
that the pipe would need to be hand excavated. The bid
alternate will provide a means to evaluate whether
replacing the pipe now would be more cost effective than
replacing the pipe at the time of a future break. A break in
the winter, especially, could be costly and difficult, with the
prospect of hand digging in frost conditions.
AG821LS3.DOC
The initial feasibility study, dated November of 1993,
indicated a cost of between $35,000 to $40,000. This
preliminary estimate encompassed all the work shown
above including the bid alternate. The total estimated cost
of the project, today, with the addition of the bid alternate,
is $58, 000.
The sanitary sewer lift station upgrade is needed to serve
the overall area and not just the plat of Cardinal Ridge. The
appropriate funding source is Trunk Reserve Fund. The
controls and pumps have served their useful life and this is
an appropriate time for their replacement.
DISCUSSION:
At the March 21, 1994, Council meeting, MSA Consulting
Engineers were given authorization to prepare plans and
specifications for project 94-07. The council is now asked
to give approval to the plans and specifications and
authorize the advertisement for bids.
ALTERNATIVES:
The alternatives are as follows:
1. Approve resolution 95-72
2. Deny this item for a specific reason.
3. Table this item for specific reason.
RECOMMENDATION: The recommendation IS Alternative No.1, approve
resolution 95-72.
FINANCIAL IMP ACT: This amount will be paid from the Trunk Reserve Fund and
a sufficient fund balance exists to cover this expenditure.
ACTION REQUIRED:
AG82 1 LS3.DOC
RESOLUTION 95-72
RESOLUTION APPROVING PLANS AND SPECIFICATIONS
AND ORDERING ADVERTISEMENT FOR BIDS ON
UPGRADING LIFT STATION #3
(PROJECT 94-07)
MOTION BY:
SECONDED BY:
WHEREAS:
pursuant to a motion which the City Council approved on
March 21, 1994, the City Engineer and the City's
engineering consultant MSA, has prepared plans and
specifications for upgrading lift station #3.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF PRIOR
LAKE, MINNESOTA, that:
1. Such plans and specifications, a copy of which is
attached hereto and made a part of hereof, are hereby
approved.
2. The City Manager shall prepare and cause to be inserted
in the official paper and in the Construction Bulletin an
advertisement for bids upon the making of such
improvement under such approved plans and
specifications. The advertisement shall be published not
less than 10 days prior to bid opening, shall specify the
work to be done, shall state that bids will be opened, and
that all bids will be received by the City until 10:00 A.M.
on September 19, 1995, at City Hall, 16200 Eagle Creek
Avenue. All bids received by this deadline will be opened
immediately at the City Hall
No bids will be considered unless sealed and filed with
the City Manager at the city hall by the 10:00 A.M.
deadline set forth above and accompanied by a cash
deposit, cashier's check, bid bond, or certified check
payable to the City of Prior Lake for five (5) percent of the
amount of such bid.
1620~gmxtreek Ave., Prior Lake, Minnesota 55372-1714 / Ph. (612) 447-4230 / Fax (612) 447-4245
AN EQUAL OPPORTIJNITY EMPLOYER
3. The City reserves the right to reject any and all bids for
any reason as determined solely by the City.
Passed and adopted this 7th day of August, 1995.
YES NO
Andren Andren
Greenfield Greenfield
Kedrowski Kedrowski
Schenck Schenck
Scott -- Scott
Frank Boyles
City Manager