CITY COUNCIL AGENDA REPORT
MEETING DATE: MARCH 14, 2016
AGENDA #: 5B
PREPARED BY: SENG THONGVANH, PROJECT ENGINEER
PRESENTER: SENG THONGVANH
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING THE
DEVELOPER INSTALLED IMPROVEMENTS FOR THE MAPLE GLEN
5TH ADDITION
DISCUSSION: Introduction
The purpose of this agenda item is to consider a resolution accepting the
developer installed improvements for the Maple Glen 5th Addition.
This action is housekeeping in nature and is called for as part of the
development agreement between the developer and the city. In essence,
this is the process through which privately installed improvements come
into public ownership pursuant to Prior Lake City Code.
History
The Maple Glen 5th Addition is part of the overall Maple Glen Development
and is located south of Trunk Highway 13 and north of 180th Street. On
May 13, 2013 the City Council adopted resolution 13-055 entering into a
Development Contract with D.R. Horton, Inc. for the Maple Glen 5th
Addition Development. Since that City Council action, the developer has
been completing the construction of the improvements as outlined in the
Development Contract. The Development Contract and approved
construction drawings outline the necessary developer installed
improvements as well as other items needed for this development to be
accepted by the City.
The Development Contract for the development details the mechanisms for
City acceptance of the developer installed improvements. In 2005, the City
amended the Standard Development Contract to include City Council
authorization to accept the improvements in addition to the final written
acceptance by the City Engineer.
Current Circumstances
The developer for the project described above has now completed the
improvements as outlined in the Development Contracts. The
improvements have been inspected by the City and have been found to be
in compliance with City standards and the approved drawings. In some
cases minor field changes were necessary during construction. These
improvements including any field adjustments were documented in the
completed as-built drawings. These as-built drawings were completed by
the developer and reviewed by the City. The property iron certification
letter has been received by the City.
2
Conclusion
The City Engineer has reviewed the improvements and has written the
acceptance letter for these developments. It is now appropriate for the City
Council to accept the improvements for these developments.
ISSUES: Once the improvements are accepted, the public improvements will then be
turned over to the City and the security for the development returned to the
developer. It will then be the responsibility of the City to perform
maintenance over the public improvements and take over operational costs
for the street lighting on the project.
FINANCIAL
IMPACT:
Within the development contract for the development, revenue was
received for city administration and for city contracted construction
observation. Staff will review the City administration expenditures at the
conclusion of the warranty period and will invoice the developer if revenue
received is insufficient to cover expenses. The project security will not be
released until the warranty period has passed and project expenses
rectified. Escrow was received by the City for the development for
construction observation and any remaining escrow funds will be returned
at the conclusion of a successful warranty period. This one year warranty
period starts when the project is accepted.
Oversizing for street construction was paid by the City to the Developer
through the Development Contract. The costs for these improvements
have been reconciled with the Developer through the Development
Contract and no additional compensation is necessary.
ALTERNATIVES: 1. Approve a resolution accepting the public improvements for the Maple
Glen 5th Addition Development as part of the consent agenda.
2. Deny this item for a specific reason and provide staff with direction.
3. Table this item until some date in the future.
RECOMMENDED
MOTION:
Motion and second for approval of alternative #1.
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 16-xxx
A RESOLUTION ACCEPTING THE DEVELOPER INSTALLED IMPROVEMENTS FOR MAPLE GLEN
5TH ADDITION CITY PROJECT #DEV12-000006
Motion By: Second By:
WHEREAS, On May 13, 2013, the City Council adopted Resolution 13-055 which authorized the City
to enter into a Development Contract with D.R. Horton, Inc. for the plat known as Maple
Glen 5th Addition; and
WHEREAS, The Development Contract outlined the improvements the developer was responsible for
installing; and
WHEREAS, These improvements and all other Development Contract responsibilities are now
complete to the satisfaction of the City; and,
WHEREAS,
WHEREAS,
The City has received the as-built drawings and property iron certification letter; and
The City Engineer has reviewed the improvements and has written the acceptance letter
for this development.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The City Council hereby accepts the improvements for the Maple Glen 5th Addition development.
3. Any remaining escrow dollars for construction inspection will be returned to the developer at the
conclusion of the warranty period.
4. The oversizing amount for street construction was paid to the developer in accordance with the
Development Contract. No further compensation to the developer is needed for this project.
PASSED AND ADOPTED THIS 14TH DAY OF MARCH 2016.
VOTE Hedberg Keeney McGuire Morton Thompson
Aye ☐ ☐ ☐ ☐ ☐
Nay ☐ ☐ ☐ ☐ ☐
Abstain ☐ ☐ ☐ ☐ ☐
Absent ☐ ☐ ☐ ☐ ☐
______________________________
Frank Boyles, City Manager
Phone 952.447.9800 / Fax 952.447.4245 / www.cityofpriorlake.com
4646 Dakota Street SE
Prior Lake, MN 55372
March 7, 2016
Mike Suel
Land Manager
D.R. Horton, Inc.
20860 Kenbridge Court, Suite 100
Lakeville, MN 55044
RE: LETTER OF ACCEPTANCE
LETTER OF CREDIT REDUCTION
PROJECT #DEV12-000006 – MAPLE GLEN 5TH
Dear Mr. Suel:
The improvements including any punch list items for the Maple Glen 5th Development have been
completed. The property pin certification letter and warranty bond have been received for the
development. Therefore, the City accepts the improvements for Maple Glen 5th Addition, City Project
#DEV12-000001. The City Council resolution accepting the improvements is attached.
A warranty bond in the amount of $236,202 was received for the Maple Glen 5th Development. The
warranty bond term is for a period of one year and will expire on March 15, 2017. Prior to March 15,
2017 the City will perform a warranty period inspection to ensure all applicable improvement items
have met City requirements. If all items pass inspection, the project will be closed out at that time.
Also, in accordance with the development contract “…once the City has accepted the project, as-builts
have been completed, all punch list items are completed and warranty bond submitted, the Irrevocable
letter of Credit may be reduced to 5%”. With the completion of the aforementioned items, the City
hereby authorizes the reduction of the Letter of Credit #SLCMMSP06901 to $47,240. Please provide
the LOC in the revised amount to remain in place during the warranty period.
If you have any questions please call me (952) 447-9834.
Sincerely,
Seng Thongvanh, P.E.
Project Engineer
CITY OF PRIOR LAKE
Cc. US Bank
Larry Poppler, City Engineer/Inspections Director