CITY COUNCIL AGENDA REPORT
MEETING DATE: JULY 25, 2016
AGENDA #: 5K
PREPARED BY: JAKE THEISEN, MAINTENANCE SUPERINTENDENT
PRESENTED BY: JAKE THEISEN
AGENDA ITEM: CONSIDER APPROVAL OF A RESOLUTION ACCEPTING BIDS AND
AUTHORIZING THE MAYOR AND CITY MANAGER TO EXECUTE THE
CITY’S STANDARDIZED CONSTRUCTION CONTRACT FOR THE 2016
STREET OVERLAY PROJECT AND CONCRETE REPAIRS
DISCUSSION: Introduction
The purpose of this agenda item is to accept the bids and authorize the
Mayor and City Manager to execute the City’s Standardized Construction
Contract with McNamara Contracting, Inc. for the 2016 Overlay Project.
History
Streets are considered a community asset in the 2040 Vision and Strategic
Plan. Our transportation system is a large investment and needs to be
maintained to ensure longevity and safety. The Council selected
“maintaining city streets at an average OCI of 70” as one of its long term
goals in the 2016 priority elements update.
Over time we have learned that aggressively pursuing the right
preventative method at the right time can extend the life of roadways
significantly. Preventative methods are cost effective procedures that
prolong the life of a street and postpone a full street reconstruction. These
methods fall into two main categories, crack sealing/seal coating and
overlays.
Pavement management projects are primarily completed through two main
projects. The first is in collaboration with other south metro cities through a
Joint Powers Agreement that is administered by Burnsville. This work
includes the crack sealing, seal coating and long-line striping. Separate
from this agreement the City annually completes an overlay project.
Current Circumstances
The City of Prior Lake utilizes a pavement management system to rate
street conditions which are then used to determine the appropriate
pavement management activity. This rating is called the Overall Condition
Index (OCI) which ranges from 100 for a new pavement to 0 for a
pavement that has completely failed.
Streets that are generally suitable for an overlay have an OCI between 45
and 65. Roads of this condition are typically not ready for reconstruction or
2
reclamation for at least 10 years. In addition, the sub base of the road has
to be sound or the overlay is ineffective. An overlay is an asphalt structural
improvement that entails the placement of 1.5-2.5 inches of new
bituminous over the existing pavement surface. Typically the edge of the
pavement and sometimes the full pavement width is milled down to allow
the crown of the road to be reestablished ensuring proper drainage. The
improvements also include spot subgrade repairs, concreate repairs, and
upgrade of all pedestrian ramps to comply with the ADA standards.
Streets to be overlaid IN 2016 have been identified by staff.
Fish Point Road 250’ South of Victoria Curve to 160th St SE
Willow Lane SW 170th St SW to Pershing St SW
These roads were originally built in the late 80s to early 90s. There is
approximately 1 linear mile of street identified on the project. As part of the
overlay there will also be 1,150 linear feet of spot curb replacements and
25 concrete pedestrian ramp updates.
Mountable Curb B618 Curb Concrete Pedestrian Ramps
600 feet 550 feet 25
An advertisement for bid was published in both the Prior Lake American
and Minnesota Construction eAdvertising with bids due and opened July
18th, 2016 at 11:00 am. The City received 4 bids which are listed in the
chart below.
Company Address Total
McNamara Rosemount $210,085.00
Prior Lake Black Top Prior Lake $257,548.50
HardDrives Rosemount $254,587.75
Midwest Asphalt Hopkins $248,060.00
Conclusion
Staff is recommending awarding the construction contract to the lowest
responsible bidder, McNamara Contracting in the amount of $210,085.
McNamara Contracting has previously worked for the City of Prior Lake
and has completed these projects successfully.
ISSUES: The amended 2016 Street Budget considered $ 490,436.00 for pavement
management (overlay, seal coat, crack sealing, striping and patching).
$190,000 was utilized for the Street JPA, $210,085 for the overlay project
with the remaining $ 90,351 for other overlay and patching repairs.
The City’s goal is to complete about 3.4 miles of street overlay per year,
however there will be about 1 mile completed between the overlay contract
and other in-house work. This reduction allowed the City to complete
8.7 miles of seal coating that is 2.0 miles above the goal of 6.75. The
increase in seal coating allowed us to catch up on the mileage for this
maintenance type and to adjust our timing to allow seal coating within the
3
first 2-3 years of initial construction of streets to be in line with new industry
recommendations.
FINANCIAL
IMPACT:
Funds for this project will be drawn from the Street Department portion of
the general fund budget of which $ 490,436.00 is identified for the City’s
street maintenance programs. We utilized $ 190,000 for the JPA and have
identified $210,085 for the Overlay. The remaining funds from the balance
will be used for other pavement maintenance throughout the City.
Beginning in 2017, a portion of such projects will be paid through special
assessment.
ALTERNATIVES: 1. Motion and a second as part of the consent agenda to approve the
resolution which accepts the bids and authorized the Mayor and City
Manager to execute the City’s Standardized Construction Contract with
McNamara Contracting for the 2016 Street Overlay Project.
2. Remove this item from the consent agenda for additional discussion.
RECOMMENDED
MOTION:
Alternative #1
4646 Dakota Street SE
Prior Lake, MN 55372
RESOLUTION 16-xxx
A RESOLUTION ACCEPTING BIDS AND AUTHORIZING THE MAYOR AND CITY
MANAGER TO EXECUTE THE CITY’S STANDARDIZED CONSTRUCTION CONTRACT FOR
THE 2016 STREET OVERLAY PROJECT AND CONCRETE REPAIRS
Motion By: Second By:
WHEREAS, The following streets have been identified by staff for overlay maintenance in
2016:
Willow Ln SW 170th Street SW – Pershing Street SW
Fish Point Road SE 250’ South of Victoria Curve SE – 160th St
SE
WHEREAS, The City of Prior Lake is committed to improving the streets within the City by
providing continued maintenance; and
WHEREAS, Continued maintenance of City streets will reduce the need of costly reconstruction
in the near future; and
WHEREAS, A total of 4 bids were received for the identified improvements as follows:
Company Address Total
McNamara Contracting Rosemount, MN $210,085.00
Prior Lake Black Top Prior Lake, MN $257,548.50
Hardrives Rosemount, MN $254,587.75
Midwest Asphalt Rogers, MN $248,060.00
;and
WHEREAS, McNamara Contracting is the lowest responsible bidder with a bid amount of
$210,085.
NOW THEREFORE, BE IT HEREBY RESOLVED BY THE CITY COUNCIL OF PRIOR LAKE,
MINNESOTA as follows:
1. The recitals set forth above are incorporated herein.
2. The Mayor and City Manager are hereby authorized to execute the City’s Standardized
Construction Contract for the identified street overlays with McNamara Contracting for an
estimated cost of $210,085.00
PASSED AND ADOPTED THIS 25th DAY OF JULY 2016.