Conduct a public hearing on the proposed
projects within the 2017-2021 CIP and
Street Reconstruction Plan
Public hearing required by state statute
when planning to issue CIP and Street
Reconstruction bonds
Purpose
2
The CIP is a multi-year planning document.
It identifies projects for the next five years.
Some projects are more developed than
others.
Some projects are dependent on partners
including the County, MNDOT, SMSC, etc.
What is CIP?
3
Transportation Plan
Equipment Replacement Plan
Park Plan
Technology Plan
Facilities Management Plan
Water Plan
Sewer Plan
Storm Water/Water Quality
Multi-Year Plans Included in CIP
4
Streets -$8,531,863
County Wide Yellow Flashing Signal Conversion
(Partnership Project)
CSAH 83 (Partnership Project)
CSAH 21 Bridge Deck Replacement (Partnership
Project)
Franklin Trail (TH 13 to CR 21 South)
Albany/CJ Circle/Five Hawks/Cates
Park Avenue
Balsam/Sunrise/Spruce/Spruce Ct.
Sycamore
2017 Projects -Public Works
5
Option A –Public Improvement to extend
Arcadia to TH 13, No Pleasant ¾ Access
Option B –Public Improvement Project to
extend Arcadia to Pleasant and build the ¾
Access for Pleasant at TH 13
A decision on which option is not necessary,
but funding in the CIP should allow for
flexibility. Feasibility Report would provide
information for future decision.
Arcadia Options (2019)
6
Transportation Plan -A
7
Transportation Plan -B
8
Street Reconstruction Plan
(Subset of Transportation Plan)
9
Year Improvement Project Type Total
Reconstruction
Bonding
Total Project
Cost
2017 Flashing Signal Conversion Partnership $75,000 $1,110,000
2017 CSAH 21 Bridge Deck Replacement Partnership $175,000 $875,000
2018 CSAH 21 and CSAH 87 Partnership $350,000 $3,449,800
2019 Fish Pt Road (Fawn Meadows to CSAH
21)Pavement/Rehab $600,000 $600,000
2019 CSAH 21/TH 13/Main Ave/Arcadia
Signal Partnership $500,000 $9,772,268
2021 Northwood Rd (Fremont to Knollridge)Pavement/Rehab $900,000 $900,000
Total $2,600,000 $16,707,068
Water -$3,007,500
Watermain replacements associated with street projects
($1,804,500)
AMRS Replacement ($850,000)
Water Equipment Replacement Plan
Summit Preserve Booster Station
Sanitary Sewer -$1,685,589
Sewer replacements associated with street projects
($775,000)
AMRS Replacement ($850,000)
Sewer System Equipment Replacement
2017 Projects (Cont.)
10
Storm Water/Water Quality -$756,418
Storm Sewer Replacements associated with
street projects ($371,418)
Stormwater Infrastructure Repairs
Stormwater Pond Maintenance ($300,000)
Parks -$213,406
Park Amenity Replacements
Trail Replacements
2017 Projects (Cont.)
11
Facilities -$232,139
Library/Club Prior Roof Overlay
Maintenance Center Parking Lot Replacement
Vehicles and Equipment -$860,704
5 Ton, Single Axle Truck
Jet Vac
Police Squads
12
2017 Projects (Cont.)
Technology -$59,500
Building Permits and Code Enforcement
Copiers/Printers
2017 Projects (Cont.)
13
Moved Parks Capital Costs from the General
Fund to the Revolving Park Fund (Fund 430)
Added Capital Park Fund (Fund 225) Revenues
and Expenditures to the Plan (Use of funds
restricted by statute)
Added 3 trail gap closing projects starting in
2020
Deferred additional Park Plan tax levy until
2024
Park Plan Changes
14
Modified Reclamation projects to include
assessment revenue
Allocated additional stormwater funding to
existing reconstruction projects
Spread out projects from remaining 4 years of
the 2016 –2020 CIP over next 5 years
Additional operational budget may be needed
to maintain deferred projects
Transportation Plan Changes
15
Replacement of the old maintenance shop
EAB
TMDL storm water projects
Flood mitigation projects
Fire Station #3 (west side of city)
Pike Lake Park
TH13 trail gap projects
Downtown Buildings
Items on the Horizon
16
Impact of CIP -Debt
17
Impact of CIP -Debt
18
Impact of CIP –Tax Levy
19
2017 2018 2019 2020 2021
Debt:
Existing CIP 308,087 146,124 (388,007) (275,570) 7,103
New CIP - 515,000 616,000 393,000 488,000
GESP Lease Payment 25,000 20,614 (0) - -
Market Referendum (66,700) (790,801) 7,200 7,000 11,720
Change in Debt Levy 266,387 (109,063) 235,193 124,430 506,823
2017-2021 CIP Projected Change in Debt Levy
Impact of CIP –Tax Levy
20
Tax Levies:2017 2018 2019 2020 2021
Equipment Revolving Fund 375,000 550,000 600,000 600,000 600,000
Revolving Park Equip Fund 213,400 412,955 494,330 648,560 792,230
Facilities Management Fund - - - 30,000 50,000
Debt Service 3,691,956 3,582,893 3,818,086 3,942,516 4,449,339
Total CIP Tax Levies 4,280,356 4,545,848 4,912,416 5,221,076 5,891,569
2017-2021 CIP Projected CIP Tax Levy
Projected Tax Levy
21
2016 2017 2018 2019 2020 2021
Tax Levies:
General 7,172,793 7,237,434 7,580,298 7,992,810 8,450,981 8,841,521
Equipment Revolving Fund 325,000 375,000 550,000 600,000 600,000 600,000
Revolving Park Equip Fund - 213,400 412,955 494,330 648,560 792,230
Facilities Management Fund - - - - 30,000 80,000
EDA Fund 155,000 140,000 140,000 140,000 140,000 140,000
Debt Service 3,425,569 3,691,956 3,582,893 3,818,086 3,942,516 4,449,339
11,078,362 11,657,790 12,266,146 13,045,226 13,812,057 14,903,090
Breakdown of Change in Levies:
General 101,063 64,641 342,864 412,512 458,171 390,540
Equipment Revolving Fund 75,000 50,000 175,000 50,000 - -
Revolving Park Equip Fund - 213,400 199,555 81,375 154,230 143,670
Facilities Management Fund - - - - 30,000 50,000
EDA Fund (4,000) (15,000) - - - -
Debt 512,213 266,387 (109,063) 235,193 124,430 506,823
Total Change 684,276 579,428 608,356 779,080 766,831 1,091,033
General 1.43%0.90%4.74%5.44%5.73%4.62%
Equipment Revolving Fund 30.00%15.38%46.67%9.09%0.00%0.00%
Revolving Park Equip Fund n/a n/a 93.51%19.71%31.20%22.15%
Facilities Management Fund n/a n/a n/a n/a n/a 166.67%
EDA Fund -2.52%-9.68%0.00%0.00%0.00%0.00%
Debt 17.58%7.78%-2.95%6.56%3.26%12.86%
Total Change 6.58%5.23%5.22%6.35%5.88%7.90%
Projected
1
2
3
4
5
Impact of CIP –Rate Changes
22
2016 2017 2018 2019 2020 2021
Water <25000 4.40$ 4.53$ 4.67$ 4.81$ 4.95$ 5.10$
Water >25000 6.06$ 6.25$ 6.43$ 6.63$ 6.82$ 7.03$
Sewer-MCES 2.22$ 2.27$ 2.33$ 2.39$ 2.45$ 2.51$
Sewer-City 2.52$ 2.77$ 2.85$ 2.94$ 3.03$ 3.12$
Storm Water 13.52$ 13.93$ 14.34$ 14.77$ 15.22$ 15.67$
CFAC-Water 5.00$ 5.00$ 5.00$ 5.00$ 5.00$ 5.00$
CFAC-Sewer 5.00$ 5.00$ 5.00$ 5.00$ 5.00$ 5.00$
Impact of CIP –Average User
23
Based on 8,000 gallons / cycle
2016 2017 2018 2019 2020 2021
Costs Per Month:48.32$ 50.25$ 51.57$ 52.92$ 54.31$ 55.74$
$$ Change from PY 3.31$ 1.94$ 1.31$ 1.35$ 1.39$ 1.43$
% Change from PY 7.3%4.0%2.6%2.6%2.6%2.6%
Annual Costs:579.82$ 603.06$ 618.81$ 635.01$ 651.69$ 668.85$
$$ Change from PY 39.70$ 23.24$ 15.75$ 16.21$ 16.68$ 17.16$
% Change from PY 7.3%4.0%2.6%2.6%2.6%2.6%
Tonight –Public Hearing
Council Discussion and Direction
Plan Adoption -August 22, 2016
Council Discussion
24
•Trunk Fees established in 2005
•Since then, the construction costs have increased 36% as
reported by the Construction Cost Index (CCI).
•The CIP plan reflects increases in the sewer, stormwater, and
street oversizing trunk fees based on the CCI.
•Staff recommends an incremental increase in the rate of 10%
per year for 2016-2019.
•Water fees were adjusted based on the proposed increases as
presented in the water plan fee analysis.
•The Comprehensive Plan Update will inform further
adjustments.
Trunk Fees
25
Trunk Fee Increases
26
2015 2016 2017 2018 2019 2020
Trunk Fees (per acre):
Water $ 5,500 $ 6,692 $ 6,960 $ 7,238 $ 7,528 $ 7,829
Sewer 3,040 3,344 3,678 4,046 4,451 4,629
Stormwater 2,790 3,069 3,376 3,713 4,085 4,248
Street Oversizing Fees 4,920 5,412 5,953 6,549 7,203 7,492
Trunk Connection Fees:
Water 900 1,095 1,139 1,184 1,232 1,281
Sewer 600 660 726 799 878 914
Tower 1,000 1,400 1,456 1,514 1,575 1,638
Trunk Fund
Year End Balance 2020
No Change Incremental Increase Full CCI increase
Utility $1.174M $1.902M $2.408M
Street Oversizing $0.292 $0.412 $0.528
Tower $0.414 $0.895 $0.895